HUNT CR (0901-22-117)
Items: 38
County: HUNT
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-22-117
DBE Goal: N/A
Project: BR 2021(523)
Guaranty: N/A
Time: 229 WORKING DAYS
Engineer's Estimate: $1,377,957.36
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,377,957.36 | |||
| $1,348,336.46 |
-2.15%
-$29,620.90
|
|||
| $1,576,098.50 |
14.38%
$198,141.14
|
16.89%
$227,762.04
|
||
| $1,577,579.76 |
14.49%
$199,622.40
|
17%
$229,243.30
|
-0.09%
-$1,481.26
|
|
| $1,747,632.09 |
26.83%
$369,674.73
|
29.61%
$399,295.63
|
-10.78%
-$170,052.33
|
|
| $2,112,834.84 |
53.33%
$734,877.48
|
56.7%
$764,498.38
|
-20.90%
-$365,202.75
|
E
Engineer's Estimate
$1,377,957.36
1
Awarded
$1,348,336.46
Over/Under Est:
-2.15%
-$29,620.90
$1,576,098.50
Over/Under Est:
14.38%
$198,141.14
Amt Left:
16.89%
$227,762.04
$1,577,579.76
Over/Under Est:
14.49%
$199,622.40
Amt Left:
17%
$229,243.30
Delta:
-0.09%
-$1,481.26
$1,747,632.09
Over/Under Est:
26.83%
$369,674.73
Amt Left:
29.61%
$399,295.63
Delta:
-10.78%
-$170,052.33
$2,112,834.84
Over/Under Est:
53.33%
$734,877.48
Amt Left:
56.7%
$764,498.38
Delta:
-20.90%
-$365,202.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| DUSTIN ALLEN, INC. | 7.64% | $98,673.35 |
| A. E. MOORE CONSTRUCTION, INC. | 4.90% | $63,285.26 |
| FLEX SUPPLY, LLC | 1.67% | $21,568.65 |
| Total: | 14.21% | $183,527.26 |