Show Job Controls
Bid Cobra

HUNT FM 36 (0642-01-021)

Items: 34

County: HUNT
Length: N/A
Highway: FM 36
District: PARIS
Control Number: 0642-01-021
DBE Goal: N/A
Project: STP 2021(218)HES
Guaranty: N/A
Time: 80 WORKING DAYS
Engineer's Estimate: $664,553.86
Date: 01/07/2021 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (9)
E
Engineer's Estimate
$664,553.86
$636,886.78
Over/Under Est: -4.16% -$27,667.08
Over/Under Est: 0.74% $4,943.94
Amt Left: 5.12% $32,611.02
$732,446.28
Over/Under Est: 10.22% $67,892.42
Amt Left: 15% $95,559.50
Delta: -9.40% -$62,948.48
Over/Under Est: 12.02% $79,906.74
Amt Left: 16.89% $107,573.82
Delta: -1.64% -$12,014.32
Over/Under Est: 15.44% $102,595.54
Amt Left: 20.45% $130,262.62
Delta: -3.05% -$22,688.80
Over/Under Est: 25.11% $166,881.74
Amt Left: 30.55% $194,548.82
Delta: -8.38% -$64,286.20
Over/Under Est: 32.35% $214,984.24
Amt Left: 38.1% $242,651.32
Delta: -5.79% -$48,102.50
Over/Under Est: 63.33% $420,856.04
Amt Left: 70.42% $448,523.12
Delta: -23.41% -$205,871.80
$1,111,446.50
Over/Under Est: 67.25% $446,892.64
Amt Left: 74.51% $474,559.72
Delta: -2.40% -$26,036.60

Bid Items & Bid Tabulations

34 Total 0 of 34
HUNT  |  FM 36  |  PARIS  |  0642-01-021  |  01/07/2021  |  $664,553.86  |  STP 2021(218)HES  |  HAZARD ELIM & SAFETY  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBRAN ENTERPRISES LLC
SJ&J CONSTRUCTION, LLC
CDM HOLDINGS, LLC
HIGHWAY 19 CONSTRUCTION LLC
STATELINE CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
ED BELL CONSTRUCTION COMPANY
HODGES AND SON CONSTRUCTION COMPANY, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 14.000 $325.000 $440.000 $200.000 $2,500.000 $1,000.000 $700.000 $1,000.000 $525.000 $500.000 $2,500.000
ROAD GRADER WORK (ORD COMP)
STA 14.000 $200.000 $440.000 $1,000.000 $100.000 $500.000 $800.000 $500.000 $1,000.000 $500.000 $450.000
BLOCK SODDING
SY 2,557.000 $3.500 $2.000 $6.000 $5.000 $5.000 $4.000 $5.500 $5.250 $6.000 $6.000
VEGETATIVE WATERING
MG 15.300 $20.000 $1.000 $10.000 $10.000 $100.000 $12.000 $10.000 $525.000 $1.000 $50.000
TEMPORARY SPL SHORING
SF 1,134.000 $30.000 $1.000 $25.000 $50.000 $25.000 $28.000 $55.000 $10.000 $35.000 $55.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 44.000 $125.000 $220.000 $180.000 $150.000 $180.000 $135.000 $150.000 $235.000 $180.000 $185.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 16.000 $300.000 $990.000 $450.000 $530.000 $450.000 $625.000 $500.000 $550.000 $780.000 $1,000.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 130.000 $400.000 $770.000 $550.000 $600.000 $500.000 $675.000 $625.000 $600.000 $900.000 $1,000.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 33.000 $550.000 $990.000 $950.000 $700.000 $750.000 $880.000 $800.000 $700.000 $1,200.000 $1,000.000
CONC BOX CULV (9 FT X 3 FT)(EXTEND)
LF 17.000 $750.000 $990.000 $1,050.000 $1,000.000 $800.000 $1,125.000 $1,000.000 $800.000 $1,200.000 $1,000.000
RC PIPE (CL III)(24 IN)
LF 4.000 $75.000 $330.000 $130.000 $200.000 $250.000 $465.000 $125.000 $300.000 $120.000 $85.000
WINGWALL (PW - 2) (HW=4 FT)
EA 2.000 $7,500.000 $9,900.000 $11,750.000 $8,455.000 $8,000.000 $9,850.000 $8,000.000 $8,000.000 $10,000.000 $6,500.000
WINGWALL (PW - 2) (HW=5 FT)
EA 12.000 $9,500.000 $9,900.000 $8,000.000 $9,800.000 $11,677.000 $10,250.000 $9,000.000 $9,000.000 $15,000.000 $11,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 4.000 $10,000.000 $9,900.000 $13,000.000 $12,500.000 $12,250.000 $18,975.000 $10,000.000 $10,500.000 $25,000.000 $15,000.000
SET (PIPE RUNNER ASSEMBLY)
EA 4.000 $1,500.000 $4,400.000 $2,000.000 $1,000.000 $2,500.000 $1,000.000 $1,500.000 $1,000.000 $2,000.000 $2,500.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 6.000 $585.000 $2,200.000 $800.000 $900.000 $600.000 $700.000 $750.000 $2,000.000 $1,800.000 $1,850.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $800.000 $2,200.000 $1,100.000 $1,100.000 $750.000 $900.000 $900.000 $2,500.000 $2,000.000 $2,850.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $2,000.000 $2,750.000 $1,900.000 $1,580.000 $1,800.000 $1,685.000 $1,350.000 $4,500.000 $2,400.000 $3,500.000
CLEAN EXIST CULVERTS
EA 9.000 $1,000.000 $1,100.000 $1,000.000 $1,000.000 $1,000.000 $1,000.000 $1,200.000 $1,500.000 $5,000.000 $2,500.000
REMOV STR (WINGWALL)
EA 19.000 $950.000 $330.000 $300.000 $500.000 $500.000 $350.000 $1,000.000 $2,500.000 $4,000.000 $2,500.000
MOBILIZATION
LS 1.000 $58,141.260 $10,000.000 $50,000.000 $45,000.000 $60,000.000 $50,000.000 $80,000.000 $100,000.000 $100,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $1.000 $6,000.000 $2,290.000 $5,000.000 $3,600.000 $5,000.000 $21,000.000 $5,000.000 $8,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 51.000 $425.000 $550.000 $200.000 $600.000 $850.000 $625.000 $850.000 $400.000 $600.000 $850.000
REMOVE SM RD SN SUP&AM
EA 5.000 $100.000 $110.000 $100.000 $100.000 $100.000 $200.000 $45.000 $100.000 $100.000 $650.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 48.000 $50.000 $55.000 $90.000 $50.000 $35.000 $25.000 $100.000 $110.000 $50.000 $100.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,455.000 $0.950 $1.000 $2.500 $1.000 $1.000 $1.100 $1.100 $1.150 $1.200 $6.000
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 155,200.000 $0.550 $0.580 $0.500 $0.580 $0.580 $0.600 $0.650 $0.600 $0.600 $0.750
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 89,666.000 $0.600 $0.580 $0.550 $0.580 $0.600 $0.600 $0.650 $0.600 $0.600 $0.750
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 12,860.000 $0.550 $0.650 $0.600 $0.650 $0.650 $0.700 $0.700 $0.650 $0.700 $0.750
REFL PAV MRKR TY I-C
EA 73.000 $3.250 $4.400 $1.000 $4.000 $4.000 $4.400 $4.400 $4.000 $5.000 $5.000
REFL PAV MRKR TY II-A-A
EA 1,750.000 $3.000 $4.400 $3.000 $3.400 $3.400 $3.850 $3.750 $4.000 $5.000 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $1.000 $100.000 $6,500.000 $5,000.000 $7,500.000 $15,000.000 $5,250.000 $10,000.000 $16,000.000
TMA (STATIONARY)
DAY 69.000 $250.000 $1.000 $100.000 $150.000 $200.000 $125.000 $275.000 $157.500 $200.000 $350.000
TMA (MOBILE OPERATION)
HR 120.000 $85.000 $1.000 $150.000 $1.000 $10.000 $75.000 $30.000 $63.000 $50.000 $85.000
Totals: $664,553.860 $636,886.780 $669,497.800 $732,446.280 $744,460.600 $767,149.400 $831,435.600 $879,538.100 $1,085,409.900 $1,111,446.500