HUNT SH 34 (0173-06-055)

Items: 62

County: HUNT
Length: 5.0500 MILES
Highway: SH 34
District: PARIS
Control Number: 0173-06-055
DBE Goal: 0.0%
Project: C 173-6-55
Guaranty: $100,000.00
Time: 312 WORKING DAYS
Engineer's Estimate: $9,799,030.51
Date: 03/05/2025 (1 year ago)
Contract Number: 3253208
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00138848
Project Description: REHAB W/OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ATKINS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$9,799,030.51
1
$9,373,273.19
Over/Under Est: -4.34% -$425,757.32
Over/Under Est: 10.49% $1,028,295.31
Amt Left: 15.51% $1,454,052.63
Over/Under Est: 15.69% $1,537,909.21
Amt Left: 20.95% $1,963,666.53
Delta: -4.71% -$509,613.90
Over/Under Est: 34.74% $3,404,128.65
Amt Left: 40.86% $3,829,885.97
Delta: -16.46% -$1,866,219.44
Over/Under Est: 58.47% $5,729,459.65
Amt Left: 65.67% $6,155,216.97
Delta: -17.61% -$2,325,331.00
Subcontractor Percentage Amount
RK HALL, LLC 29.45% $2,760,428.95
COLD CREEK CONSTRUCTION, LTD 2.50% $234,331.83
J. H. ODEN CONTRACTING COMPANY 1.81% $169,656.24
STRIPE-A-ZONE, LLC 1.14% $106,855.31
AWP SAFETY 0.99% $92,795.40
MORRIS COUNTY CONTRACTORS, L.L.C. 0.76% $71,236.88
BARRICADES UNLIMITED 0.61% $57,176.97
SURFACE PREPARATION TECHNOLOGIES, LLC 0.34% $31,869.13
A. L. HELMCAMP, INC. 0.00% $0.00
Total: 37.60% $3,524,350.71

Bid Items & Bid Tabulations

62 Total 0 of 62
HUNT  |  SH 34  |  PARIS  |  0173-06-055  |  03/05/2025  |  $9,799,030.51  |  C 173-6-55  |  REHAB EXIST ROADWAY  |  312 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CDM HOLDINGS
D. L. LENNON INCORPORATED - CONTRACTOR
GREY SKY CONSTRUCTION LLC
TEXAS MATERIALS GROUP, INC.
A. K. GILLIS & SONS, LLC
PREPARING ROW
STA 266.840 $75.000 $999.000 $1,834.700 $3,745.000 $200.000 $1,643.000
RMV (0"-6") TRT/UNTRT BASE & ASPH PAV
SY 104,646.670 $4.850 $3.000 $7.650 $6.000 $6.000 $5.500
EXCAV (CHANNEL)
CY 16.000 $75.000 $100.000 $150.000 $50.000 $400.000 $500.000
BACKFILL (TY B)
STA 266.840 $80.000 $200.000 $380.000 $250.000 $330.000 $600.000
ROAD GRADER WORK (ORD COMP)
STA 266.840 $188.000 $100.000 $350.000 $250.000 $200.000 $600.000
BROADCAST SEED (TEMP_WARM)
SY 83,017.000 $0.150 $0.150 $0.200 $0.500 $0.130 $0.200
BROADCAST SEED (TEMP_COOL)
SY 83,017.000 $0.150 $0.150 $0.200 $0.500 $0.130 $0.200
STRAW/HAY MLCH SEED(PERM_RURAL_CLAY)
SY 166,034.000 $0.350 $0.300 $0.400 $0.750 $0.390 $0.600
VEGETATIVE WATERING
TGL 997.000 $17.000 $30.000 $35.000 $50.000 $40.000 $10.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 130,460.000 $21.000 $17.500 $23.320 $16.000 $22.000 $31.350
REWORK BS MTL (TY B)(10")(ORD COMP)
STA 266.840 $2,165.000 $750.000 $640.000 $550.000 $500.000 $2,750.000
CEMENT
TON 800.000 $285.000 $275.000 $260.000 $300.000 $300.000 $245.000
CEMENT TRT (NEW BASE)(6")
SY 130,460.000 $3.150 $3.000 $3.640 $6.000 $3.000 $5.750
PRIME COAT (MC-30)
GAL 36,528.800 $2.000 $6.000 $5.000 $5.000 $4.000 $8.360
D-GR HMA TY-C SAC-A PG70-22
TON 14,350.600 $138.000 $121.000 $126.190 $165.000 $218.000 $180.180
PLANE ASPH CONC PAV(0" TO 8")
SY 130,460.000 $2.850 $5.000 $3.880 $7.000 $6.000 $5.500
RIPRAP (MOW STRIP)(4 IN)
CY 39.000 $385.000 $700.000 $650.000 $550.000 $600.000 $650.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 54.000 $170.000 $285.000 $350.000 $150.000 $350.000 $494.520
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 1.000 $3,985.000 $11,500.000 $10,000.000 $16,500.000 $9,500.000 $10,000.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $2,680.000 $5,050.000 $7,000.000 $6,500.000 $8,000.000 $7,000.000
CLEAN EXIST CULVERTS
EA 10.000 $800.000 $2,000.000 $1,200.000 $1,500.000 $4,000.000 $1,200.000
MOBILIZATION
LS 1.000 $890,821.210 $900,000.000 $806,600.000 $1,100,000.000 $1,300,000.000 $1,190,138.795
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $4,500.000 $14,500.000 $6,578.000 $8,500.000 $77,000.000 $56,100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $15,000.000 $20,000.000 $20,000.000 $25,000.000 $19,500.000
TMA (STATIONARY)
DAY 312.000 $278.000 $500.000 $300.000 $250.000 $500.000 $500.000
TMA (MOBILE OPERATION)
HR 138.000 $48.000 $1.000 $75.000 $55.000 $80.000 $500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,200.000 $22.900 $51.000 $45.000 $40.000 $65.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 1,200.000 $5.420 $20.000 $10.000 $10.000 $12.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,530.000 $3.150 $4.000 $5.000 $4.000 $5.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,530.000 $1.250 $2.000 $1.000 $2.000 $1.000 $5.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 20,004.000 $0.720 $0.150 $3.190 $0.300 $0.190 $2.000
MILL RUMBLE STRIPS (CONC) (SHLDR)
LF 40,000.000 $0.720 $0.750 $4.190 $0.300 $0.190 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 680.000 $33.000 $29.000 $28.750 $30.000 $34.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,866.000 $2,350.000 $2,300.000 $1,850.000 $3,750.000 $3,900.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 27.000 $730.000 $1,290.000 $1,200.000 $1,500.000 $1,300.000 $1,300.000
REMOVE METAL BEAM GUARD FENCE
LF 550.000 $8.500 $2.500 $2.500 $5.000 $5.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $385.000 $200.000 $150.000 $500.000 $250.000 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $185.000 $2,900.000 $2,850.000 $3,520.000 $2,910.000 $2,900.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 4.000 $480.000 $525.000 $690.000 $1,100.000 $600.000 $600.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 33.000 $275.000 $375.000 $275.000 $1,100.000 $300.000 $300.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 2.000 $375.000 $400.000 $290.000 $1,100.000 $340.000 $340.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 76.000 $750.000 $740.000 $665.000 $1,100.000 $660.000 $660.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $1,125.000 $860.000 $727.000 $1,100.000 $700.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $932.500 $1,100.000 $1,078.000 $1,100.000 $850.000 $850.000
REMOVE SM RD SN SUP&AM
EA 86.000 $178.500 $145.000 $115.000 $500.000 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $7.000 $30.000 $25.000 $100.000 $38.000 $31.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 14.000 $65.000 $30.000 $63.000 $50.000 $15.000 $15.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 53,312.000 $0.250 $0.250 $0.300 $0.650 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 2,680.000 $0.280 $0.250 $0.300 $0.650 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 40,660.000 $0.250 $0.250 $0.300 $0.650 $0.300 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,530.000 $2.250 $1.000 $2.000 $6.000 $1.000 $2.250
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 2,136.000 $2.250 $1.000 $2.000 $6.000 $1.000 $2.250
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 262.000 $19.500 $13.500 $7.500 $20.000 $7.500 $7.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $120.000 $205.000 $145.000 $250.000 $145.000 $145.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $166.000 $245.000 $165.000 $250.000 $165.000 $165.000
REF PAV MRK TY I(W)18"(YLD TRI)(090MIL)
EA 7.000 $35.000 $60.000 $75.000 $150.000 $75.000 $75.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 53,312.000 $0.750 $0.750 $1.000 $0.650 $1.000 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 40,660.000 $1.250 $0.750 $1.000 $0.650 $1.000 $1.000
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 2,680.000 $1.350 $0.750 $1.500 $0.650 $1.500 $1.500
REFL PAV MRKR TY II-A-A
EA 1,111.000 $3.250 $5.250 $4.300 $6.000 $4.300 $43.000
UNDERSEAL COURSE
GAL 7,827.600 $1.750 $6.180 $6.180 $6.000 $6.000 $11.880
REINFORMT GRID FOR ASPHALT PVMT OVERLA
SY 130,460.000 $9.000 $7.340 $7.340 $4.000 $6.750 $9.740
Totals: $9,799,030.510 $9,373,273.188 $10,827,325.816 $11,336,939.720 $13,203,159.160 $15,528,490.144
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $97,990.31
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $195,980.61
Total: $293,970.92