HUNT FM 499 (0009-22-005)

Items: 40

County: HUNT
Length: N/A
Highway: FM 499
District: PARIS
Control Number: 0009-22-005
DBE Goal: N/A
Project: BR 2B20(256)
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $727,126.10
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$727,126.10
Over/Under Est: -14.64% -$106,449.63
Over/Under Est: -9.97% -$72,517.26
Amt Left: 5.47% $33,932.37
Over/Under Est: -6.71% -$48,782.79
Amt Left: 9.29% $57,666.84
Delta: -3.63% -$23,734.47
Over/Under Est: 0.55% $4,000.42
Amt Left: 17.8% $110,450.05
Delta: -7.78% -$52,783.21
Over/Under Est: 2.21% $16,094.09
Amt Left: 19.74% $122,543.72
Delta: -1.65% -$12,093.67
Over/Under Est: 2.92% $21,234.34
Amt Left: 20.57% $127,683.97
Delta: -0.69% -$5,140.25
$834,863.00
Over/Under Est: 14.82% $107,736.90
Amt Left: 34.51% $214,186.53
Delta: -11.56% -$86,502.56

Bid Items & Bid Tabulations

40 Total 0 of 40
HUNT  |  FM 499  |  PARIS  |  0009-22-005  |  09/03/2020  |  $727,126.10  |  BR 2B20(256)  |  BRIDGE REPL  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
STATELINE CONSTRUCTION, LLC
HIGHWAY 19 CONSTRUCTION LLC
LONGVIEW BRIDGE AND ROAD, LTD.
INTEGRITY SERVICES, LLC
EAST TEXAS BRIDGE, INC.
PIERCE R & B LLC
PREPARING ROW
STA 6.900 $2,500.000 $2,000.000 $2,250.000 $2,500.000 $3,000.000 $1,500.000 $8,000.000 $5,000.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 3.000 $400.000 $500.000 $800.000 $500.000 $1,800.000 $950.000 $800.000 $1,000.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 9.000 $500.000 $800.000 $1,250.000 $500.000 $3,500.000 $1,280.000 $1,200.000 $1,500.000
EXCAVATION (ROADWAY)
CY 264.000 $22.000 $20.000 $15.000 $20.000 $16.750 $10.000 $20.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 474.000 $30.000 $20.000 $15.000 $30.000 $22.000 $20.000 $20.000 $32.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 456.000 $2.500 $3.000 $3.000 $5.000 $3.000 $2.000 $4.000 $3.250
CELL FBR MLCH SEED(TEMP)(WARM)
SY 228.000 $2.500 $4.000 $3.000 $0.010 $4.400 $2.000 $3.300 $4.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 228.000 $2.500 $4.000 $3.000 $0.010 $4.400 $2.500 $3.300 $4.500
VEGETATIVE WATERING
MG 15.470 $50.000 $1.000 $22.000 $100.000 $50.000 $35.000 $12.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 456.000 $5.000 $2.000 $4.500 $5.000 $2.200 $3.000 $4.000 $3.000
REWORK BS MTL (TY B) (8") (ORD COMP)
SY 845.000 $10.000 $35.000 $12.500 $11.000 $10.000 $9.700 $9.000 $10.000
D-GR HMA(SQ) TY-B PG64-22
TON 295.000 $110.000 $120.000 $128.000 $120.000 $135.000 $150.000 $130.000 $150.000
D-GR HMA(SQ) TY-D SAC-A PG64-22
TON 118.000 $115.000 $120.000 $130.000 $120.000 $160.000 $150.000 $130.000 $200.000
CEM STABIL BKFL
CY 59.000 $160.000 $175.000 $265.000 $180.000 $250.000 $220.000 $225.000 $250.000
DRILL SHAFT (36 IN)
LF 252.000 $275.000 $160.000 $185.000 $247.000 $230.000 $258.000 $180.000 $300.000
CL C CONC (ABUT)
CY 37.700 $1,000.000 $1,200.000 $1,075.000 $900.000 $960.000 $1,200.000 $1,000.000 $1,400.000
REINF CONC SLAB
SF 1,870.000 $22.000 $26.000 $22.100 $23.000 $26.750 $22.000 $24.000 $34.000
APPROACH SLAB
CY 51.400 $525.000 $650.000 $650.000 $500.000 $550.000 $475.000 $585.000 $625.000
PRESTR CONC GIRDER (TX28)
LF 218.000 $200.000 $220.000 $185.000 $187.000 $165.000 $181.670 $175.000 $280.000
RIPRAP (MOW STRIP)(4 IN)
CY 56.000 $500.000 $450.000 $435.000 $450.000 $500.000 $495.000 $475.000 $625.000
RAIL (TY T631)
LF 142.000 $100.000 $70.000 $75.000 $68.000 $75.000 $92.960 $75.000 $100.000
GABION MATTRESSES (GALV)
CY 467.000 $375.000 $225.000 $295.000 $280.000 $280.000 $375.000 $325.000 $220.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $20,000.000 $12,550.000 $20,000.000 $18,000.000 $25,000.000 $20,000.000 $25,000.000
MOBILIZATION
LS 1.000 $60,330.100 $50,000.000 $60,000.000 $100,000.000 $65,000.000 $79,715.430 $70,000.000 $83,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,600.000 $2,800.000 $2,250.000 $1,000.000 $3,000.000 $2,000.000 $7,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $35.000 $5.000 $42.000 $25.000 $44.000 $35.000 $55.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $10.000 $1.000 $12.000 $10.000 $20.000 $12.000 $10.000 $15.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 20.000 $100.000 $1.000 $45.000 $10.000 $250.000 $150.000 $125.000 $125.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,454.000 $5.000 $1.000 $3.000 $3.000 $2.850 $2.020 $3.500 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,454.000 $2.000 $1.000 $1.000 $1.000 $1.350 $0.900 $1.000 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 862.500 $25.000 $18.000 $23.000 $17.500 $19.250 $25.850 $20.000 $22.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $5.000 $5.000 $3.000 $5.000 $5.500 $5.500 $6.000 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,750.000 $2,500.000 $2,550.000 $2,375.000 $2,600.000 $2,640.000 $2,600.000 $2,750.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $500.000 $200.000 $200.000 $200.000 $220.000 $275.000 $300.000 $250.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 2.000 $60.000 $30.000 $45.000 $75.000 $80.000 $67.200 $100.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $60.000 $30.000 $30.000 $29.000 $32.000 $50.000 $40.000 $37.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 826.000 $1.500 $2.000 $5.000 $4.000 $5.000 $2.060 $5.000 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 826.000 $1.500 $2.000 $5.000 $4.000 $5.000 $2.060 $5.000 $3.000
REFL PAV MRKR TY II-A-A
EA 11.000 $6.000 $5.000 $25.000 $75.000 $22.000 $5.600 $25.000 $20.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $14,000.000 $6,000.000 $9,500.000 $10,000.000 $20,000.000 $10,875.000 $8,000.000 $20,000.000
Totals: $727,126.100 $620,676.470 $654,608.840 $678,343.310 $731,126.525 $743,220.185 $748,360.440 $834,863.000