HUDSPETH SH 20 (0002-04-035)
Items: 58
County: HUDSPETH
Length: N/A
Highway: SH 20
District: EL PASO
Control Number: 0002-04-035
DBE Goal: 350.0%
Project: STP 2024(607)HES
Guaranty: N/A
Time: 143 WORKING DAYS
Engineer's Estimate: $3,760,933.97
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,760,933.97 | |||
| $3,814,947.90 |
1.44%
$54,013.93
|
|||
| $4,071,626.50 |
8.26%
$310,692.53
|
6.73%
$256,678.60
|
||
| $4,333,075.55 |
15.21%
$572,141.58
|
13.58%
$518,127.65
|
-6.42%
-$261,449.05
|
E
Engineer's Estimate
$3,760,933.97
1
Awarded
$3,814,947.90
Over/Under Est:
1.44%
$54,013.93
$4,071,626.50
Over/Under Est:
8.26%
$310,692.53
Amt Left:
6.73%
$256,678.60
$4,333,075.55
Over/Under Est:
15.21%
$572,141.58
Amt Left:
13.58%
$518,127.65
Delta:
-6.42%
-$261,449.05
| Subcontractor | Percentage | Amount |
|---|---|---|
| PMI PAVEMENT MARKING, LLC | 4.44% | $180,253.81 |
| MAJOR MOTION LOGISTICS, LLC | 1.35% | $54,806.90 |
| WEST TEXAS ROCK RESOURCES, LLC | 0.15% | $6,089.66 |
| Total: | 5.94% | $241,150.37 |
Bid Items & Bid Tabulations
58
Total
0 of 58