HOWARD FM 846 (1872-02-017)

Items: 64

County: HOWARD
Length: N/A
Highway: FM 846
District: ABILENE
Control Number: 1872-02-017
DBE Goal: N/A
Project: STP 1502(216)
Guaranty: N/A
Time: 311 WORKING DAYS
Engineer's Estimate: $10,710,570.05
Date: 05/05/2015 (11 years ago)
Contract Number: N/A
Type: EMB, EXC, STRS, SET, SURF, MBGF
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$10,710,570.05
1
Awarded
$9,519,743.52
Over/Under Est: -11.12% -$1,190,826.53
$10,089,270.77
Over/Under Est: -5.8% -$621,299.28
Amt Left: 5.98% $569,527.25
$11,121,238.96
Over/Under Est: 3.83% $410,668.91
Amt Left: 16.82% $1,601,495.44
Delta: -10.23% -$1,031,968.19
Over/Under Est: 9.23% $988,184.07
Amt Left: 22.89% $2,179,010.60
Delta: -5.19% -$577,515.16
Over/Under Est: 29.21% $3,128,119.88
Amt Left: 45.37% $4,318,946.41
Delta: -18.29% -$2,139,935.81

Bid Items & Bid Tabulations

64 Total 0 of 64
HOWARD  |  FM 846  |  ABILENE  |  1872-02-017  |  05/05/2015  |  $10,710,570.05  |  STP 1502(216)  |  EMB, EXC, STRS, SET, SURF, MBGF  |  311 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SBBI, INC.
DELHUR INDUSTRIES, INC.
REECE ALBERT, INC.
PRICE CONSTRUCTION, LTD.
ALLEN BUTLER CONSTRUCTION, INC.
PREPARING ROW
AC 13.510 $3,000.000 $2,304.000 $3,000.000 $3,533.150 $1,270.080 $7,500.000
REMOVING STAB BASE AND ASPH PAV (1")
SY 26,270.000 $3.000 $6.500 $1.720 $0.780 $0.830 $3.300
EXCAVATION (ROADWAY)
CY 1,000.000 $10.770 $10.500 $30.000 $23.200 $14.610 $13.000
EMBANKMENT (ORIGINAL)(ORD COMP)(TY B)
CY 33,140.000 $6.500 $18.000 $12.000 $13.130 $24.950 $25.720
BACKFILL (TY B)
STA 849.680 $165.000 $313.000 $230.000 $161.870 $237.650 $376.140
BLADING
HR 64.000 $150.000 $213.000 $300.000 $243.170 $207.320 $200.000
SPEC EXCAV WORK (BACKHOE)
HR 60.000 $150.000 $90.000 $300.000 $215.720 $112.370 $300.000
FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS)
CY 105,904.000 $45.000 $31.000 $39.180 $44.690 $44.560 $49.960
REWORK BS MTL (TY B) (6") (DENS CONT)
STA 12.000 $1,000.000 $1,333.000 $1,200.000 $8,105.090 $4,442.130 $3,333.330
REWORK BS MTL (TY C)(7")(DENS CONT)
STA 739.180 $1,000.000 $383.000 $674.400 $356.300 $1,199.900 $603.912
PRIME COAT (RC-250)
GAL 79,303.000 $5.000 $8.000 $5.020 $4.630 $5.100 $4.460
ASPH (AC-20-5TR)
GAL 89,877.000 $5.500 $6.500 $4.180 $4.770 $4.110 $3.590
AGGR(TY-PB GR-3 SAC-B)
CY 3,110.000 $95.000 $108.000 $122.310 $142.550 $152.220 $165.110
AGGR(TY-PB GR-4 SAC-B)
CY 2,299.000 $100.000 $146.000 $122.310 $134.330 $153.880 $183.530
AGGR(TY-PB GR-5 SAC-B)
CY 2,115.000 $110.000 $173.000 $122.310 $196.670 $218.170 $189.670
ASPH (AC 20-5TR OR CRS-1P)
GAL 105,738.000 $5.500 $7.000 $4.180 $3.990 $4.230 $3.450
CMP (GAL STL 24 IN)
LF 84.000 $86.000 $109.000 $102.000 $243.840 $125.710 $367.116
CMP (GAL STL 30 IN)
LF 9.000 $94.340 $230.000 $228.000 $477.380 $165.410 $550.500
CMP (GAL STL 48 IN)
LF 30.000 $170.000 $173.000 $273.600 $280.430 $198.490 $533.717
CONC BOX CULV (5 FT X 3 FT)
LF 180.000 $500.000 $1,064.000 $660.000 $471.940 $727.810 $463.930
CONC BOX CULV (8 FT X 4 FT)
LF 4.000 $960.000 $3,549.000 $3,000.000 $5,241.490 $992.460 $5,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 6.000 $6,400.000 $3,006.000 $5,472.000 $7,337.070 $8,998.330 $5,000.000
SET (TY I)(S= 8 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $8,100.000 $8,440.000 $7,296.000 $9,359.190 $13,894.480 $5,000.000
SET (TY I)(S= 8 FT)(HW= 6 FT)(4:1) (C)
EA 10.000 $12,000.000 $5,707.000 $11,940.000 $7,234.600 $14,886.940 $5,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 4.000 $2,500.000 $1,872.000 $2,280.000 $996.880 $1,323.280 $1,154.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $2,800.000 $2,556.000 $3,192.000 $1,043.430 $1,455.610 $1,567.600
SET (TY II) (24 IN) (CMP) (4: 1) (C)
EA 22.000 $3,000.000 $1,604.000 $2,280.000 $1,931.060 $1,654.100 $1,567.600
SET (TY II) (30 IN) (CMP) (4: 1) (C)
EA 8.000 $3,500.000 $2,086.000 $2,280.000 $2,217.660 $2,646.570 $2,128.600
SET (TY II) (33 IN) (CMP) (4: 1) (C)
EA 8.000 $4,000.000 $2,193.000 $3,192.000 $2,431.580 $3,308.210 $2,375.000
SET (TY II) (42 IN) (CMP) (3: 1) (C)
EA 6.000 $5,000.000 $2,213.000 $4,560.000 $2,912.790 $4,631.490 $3,672.500
SET (TY II) (48 IN) (CMP) (3: 1) (C)
EA 6.000 $5,200.000 $2,385.000 $5,040.000 $2,633.940 $5,293.130 $4,834.100
CLEAN EXIST CULVERTS
EA 14.000 $2,008.330 $1,449.000 $3,000.000 $5,398.430 $2,646.570 $1,500.000
REMOV STR (BOX CULVERT)
EA 1.000 $7,611.440 $56,693.000 $6,000.000 $22,545.750 $9,924.630 $21,000.000
MOBILIZATION
LS 1.000 $1,000,000.000 $230,000.000 $967,092.750 $1,084,533.700 $537,381.670 $1,565,316.304
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $8,000.000 $3,440.000 $7,794.000 $20,728.910 $22,053.210 $54,888.890
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 240.000 $35.000 $41.000 $24.200 $34.590 $52.930 $50.000
ROCK FILTER DAMS (REMOVE)
LF 240.000 $13.000 $11.000 $5.500 $14.530 $15.880 $50.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,110.000 $4.000 $6.000 $11.000 $4.540 $11.910 $9.900
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,110.000 $1.000 $3.000 $0.390 $1.560 $2.650 $2.200
CONSTRUCTING DETOURS
SY 254.000 $35.000 $102.000 $90.000 $82.040 $82.030 $112.130
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 60.000 $30.000 $136.000 $120.000 $50.570 $151.590 $30.270
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $30.000 $176.000 $180.000 $38.590 $152.050 $45.400
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 60.000 $15.000 $39.000 $180.000 $54.340 $48.480 $25.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $15.000 $59.000 $60.000 $40.750 $26.570 $25.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 60.000 $15.000 $39.000 $120.000 $54.340 $65.710 $30.270
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $15.000 $59.000 $120.000 $40.750 $39.140 $45.400
INTERSECTIONS (SURF TREAT)
SY 3,948.000 $35.000 $49.000 $36.000 $46.080 $30.940 $129.430
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 7,733.000 $30.000 $36.000 $36.000 $33.840 $30.900 $35.560
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 81.000 $450.000 $626.000 $368.500 $598.510 $595.480 $495.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $450.000 $698.000 $495.000 $731.510 $727.810 $605.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 28.000 $44.000 $188.000 $38.500 $133.000 $132.330 $110.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 169,860.000 $0.180 $0.300 $0.310 $0.370 $0.290 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 18,491.000 $0.450 $0.300 $0.330 $0.400 $0.340 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 52,000.000 $0.230 $0.300 $0.330 $0.400 $0.290 $0.230
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 170,460.000 $0.680 $1.000 $0.720 $0.860 $0.790 $0.830
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 16.000 $6.630 $6.000 $22.000 $26.600 $6.220 $4.950
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 18,491.000 $0.690 $1.000 $0.830 $1.000 $1.320 $0.830
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 53,308.000 $0.740 $1.000 $0.720 $0.860 $0.790 $0.830
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 8,122.000 $1.000 $0.700 $2.400 $3.870 $1.900 $5.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 16.000 $5.490 $17.000 $16.500 $19.950 $8.200 $13.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 170,460.000 $0.500 $0.500 $0.350 $0.430 $0.500 $0.390
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 18,491.000 $0.300 $0.500 $0.390 $0.470 $0.530 $0.390
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 52,600.000 $0.500 $0.500 $0.390 $0.470 $0.500 $0.390
REFL PAV MRKR TY II-A-A
EA 1,575.000 $2.650 $4.000 $3.300 $3.990 $3.970 $3.300
Totals: $10,710,570.050 $9,519,743.520 $10,089,270.772 $11,121,238.972 $11,698,754.125 $13,838,689.945