Show Job Controls
Bid Cobra

HOWARD SH 350 (0693-01-037)

Items: 70

County: HOWARD
Length: N/A
Highway: SH 350
District: ABILENE
Control Number: 0693-01-037
DBE Goal: N/A
Project: STP 2021(097)
Guaranty: N/A
Time: 92 WORKING DAYS
Engineer's Estimate: $3,411,024.45
Date: 11/04/2020 (5 years ago)
Contract Number: N/A
Type: MILL, SPOT REPAIR, OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$3,411,024.45
1
$3,221,956.62
Over/Under Est: -5.54% -$189,067.83
Over/Under Est: 17.14% $584,645.08
Amt Left: 24.01% $773,712.91
$4,187,154.00
Over/Under Est: 22.75% $776,129.55
Amt Left: 29.96% $965,197.38
Delta: -4.79% -$191,484.47
Over/Under Est: 41.6% $1,418,918.80
Amt Left: 49.91% $1,607,986.63
Delta: -15.35% -$642,789.25

Bid Items & Bid Tabulations

70 Total 0 of 70
HOWARD  |  SH 350  |  ABILENE  |  0693-01-037  |  11/04/2020  |  $3,411,024.45  |  STP 2021(097)  |  MILL, SPOT REPAIR, OVERLAY  |  92 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
TIERRA LEASE SERVICE, LLC
CONTRACT PAVING CO.
NOBLES ROAD CONSTRUCTION, INC.
PREPARING ROW
STA 196.250 $250.000 $80.110 $450.000 $450.000 $160.000
REMOVING CONC (RIPRAP)
SY 119.300 $30.000 $24.420 $30.000 $15.000 $120.000
SUBGRADE WIDENING (DENS CONT)
STA 19.550 $350.000 $717.280 $1,500.000 $1,500.000 $2,000.000
BACKFILL (TY A)
STA 177.210 $150.000 $149.720 $250.000 $450.000 $445.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,901.000 $3.340 $2.990 $10.000 $10.000 $16.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,901.000 $0.160 $1.260 $1.000 $15.000 $5.000
BROADCAST SEED (TEMP) (WARM)
SY 951.000 $0.220 $1.050 $1.000 $1.080 $5.000
BROADCAST SEED (TEMP) (COOL)
SY 950.000 $0.220 $1.050 $1.000 $1.080 $5.000
VEGETATIVE WATERING
MG 21.000 $30.000 $98.690 $65.000 $48.000 $210.000
ASPH (MULTI OPTION)
GAL 39,414.000 $4.000 $3.290 $3.250 $6.000 $5.500
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 730.000 $125.000 $181.950 $145.000 $130.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 10,000.000 $60.000 $69.810 $85.000 $70.000 $119.000
PLANE ASPH CONC PAV(0" TO 2")
SY 6,572.000 $4.500 $5.250 $2.250 $4.000 $4.000
PLANE ASPH CONC PAV (2")
SY 4,823.000 $1.750 $5.910 $2.750 $4.000 $7.000
RIPRAP (CONC)(4 IN)
CY 11.000 $480.000 $735.000 $900.000 $1,000.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 80.000 $445.000 $735.000 $700.000 $756.000 $850.000
MOBILIZATION
LS 1.000 $339,017.680 $64,995.990 $250,000.000 $310,000.000 $425,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $20,000.000 $12,600.000 $3,100.000 $5,000.000 $10,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 680.000 $6.500 $4.880 $5.250 $5.022 $5.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 680.000 $1.400 $1.050 $1.250 $2.000 $2.100
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 13,781.000 $40.000 $18.630 $30.000 $40.000 $44.000
RUMBLE STRIPS (SHOULDER)
LF 32,990.000 $0.140 $0.190 $0.150 $0.270 $0.190
RUMBLE STRIPS (CENTERLINE)
LF 17,651.000 $0.150 $0.260 $0.220 $0.518 $0.520
MTL W-BEAM GD FEN (TIM POST)
LF 950.000 $23.000 $31.500 $34.500 $40.000 $23.100
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $3,675.000 $2,300.000 $2,500.000 $2,050.000
SHORT RADIUS
LF 50.000 $35.000 $36.750 $40.000 $40.000 $30.500
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,300.000 $2,100.000 $1,375.000 $1,500.000 $1,680.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 50.000 $30.000 $31.500 $36.000 $40.000 $24.500
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 100.000 $60.000 $105.000 $88.500 $85.000 $57.500
REMOVE METAL BEAM GUARD FENCE
LF 850.000 $2.900 $3.150 $2.250 $3.240 $3.150
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $270.000 $525.000 $300.000 $650.000 $315.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,900.000 $3,675.000 $3,475.000 $3,500.000 $3,150.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $265.000 $525.000 $525.000 $550.000 $315.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 37.000 $560.000 $674.100 $700.000 $783.000 $760.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $790.000 $847.350 $875.000 $945.000 $920.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,600.000 $886.200 $915.000 $999.000 $970.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $940.000 $1,255.800 $1,300.000 $1,242.000 $1,210.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 17.000 $940.000 $798.000 $825.000 $918.000 $895.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 6.000 $900.000 $1,106.700 $1,125.000 $1,188.000 $1,155.000
REMOVE SM RD SN SUP&AM
EA 63.000 $80.000 $55.290 $135.000 $108.000 $105.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 8.000 $80.000 $77.700 $80.000 $135.000 $131.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 20.000 $80.000 $42.000 $27.000 $37.800 $37.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 385.000 $0.400 $0.290 $1.100 $1.080 $0.480
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 38,200.000 $0.200 $0.290 $0.320 $0.320 $0.370
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,327.000 $0.850 $0.590 $0.380 $0.450 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 153.000 $2.600 $3.150 $2.700 $3.000 $7.350
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 2,044.000 $0.400 $0.290 $0.320 $0.500 $0.370
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 38,200.000 $0.200 $0.290 $0.320 $0.500 $0.370
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 8,595.000 $1.000 $1.050 $1.620 $5.000 $1.050
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,914.000 $1.050 $4.070 $1.100 $0.800 $2.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,327.000 $0.900 $0.900 $0.920 $1.400 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 385.000 $0.400 $0.450 $1.080 $0.500 $0.680
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 38,450.000 $0.360 $0.450 $0.540 $0.700 $0.680
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,075.000 $0.400 $0.450 $0.700 $0.700 $0.680
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 27,820.000 $0.350 $0.450 $0.540 $0.550 $0.680
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 153.000 $13.000 $23.100 $16.200 $25.000 $19.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 10.000 $254.000 $341.250 $232.200 $275.000 $262.000
PREFAB PAV MRK TY C (W) (WORD)
EA 10.000 $312.000 $420.000 $302.400 $300.000 $295.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 6.000 $35.000 $57.750 $108.000 $200.000 $48.000
REFL PAV MRKR TY I-C
EA 87.000 $3.000 $3.680 $3.780 $6.000 $6.500
REFL PAV MRKR TY II-A-A
EA 589.000 $2.800 $3.680 $3.780 $4.000 $5.000
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $700.000 $1,456.620 $1,620.000 $550.000 $500.000
REMOVAL OF CABLES
LF 345.000 $1.500 $4.260 $5.400 $10.000 $5.000
SP MIXES SP-B PG64-22
TON 1,226.000 $100.000 $122.340 $170.000 $120.000 $141.000
SP MIXES SP-D SAC-B PG70-22
TON 10,839.000 $90.000 $109.000 $130.000 $120.000 $117.000
TACK COAT
GAL 151.000 $5.000 $59.530 $5.500 $25.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,800.000 $5,838.820 $7,500.000 $20,000.000 $15,750.000
TMA (STATIONARY)
DAY 40.000 $155.000 $383.460 $375.000 $400.000 $840.000
TMA (MOBILE OPERATION)
DAY 12.000 $200.000 $495.660 $375.000 $600.000 $525.000
SOLAR POWERED LED ROADSIDE SIGN
EA 2.000 $3,500.000 $3,242.400 $3,250.000 $1,200.000 $2,625.000
Totals: $3,411,024.450 $3,221,956.639 $3,995,669.530 $4,187,154.008 $4,829,943.250