HOWARD IH 20 (0005-06-121)

Items: 43

County: HOWARD
Length: N/A
Highway: IH 20
District: ABILENE
Control Number: 0005-06-121
DBE Goal: N/A
Project: F 2023(789)
Guaranty: N/A
Time: 106 WORKING DAYS
Engineer's Estimate: $7,550,032.59
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
RYAN SAYLES
LARISSA HALFORD
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$7,550,032.59
1
$8,336,656.83
Over/Under Est: 10.42% $786,624.24
$8,855,785.00
Over/Under Est: 17.29% $1,305,752.41
Amt Left: 6.23% $519,128.17

Bid Items & Bid Tabulations

43 Total 0 of 43
HOWARD  |  IH 20  |  ABILENE  |  0005-06-121  |  05/04/2023  |  $7,550,032.59  |  F 2023(789)  |  PREVENT MAINT  |  106 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
FNH CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 3,246.000 $5.400 $5.500 $30.000
FOG SEAL (CSS-1H)
GAL 1,015.000 $5.000 $24.360 $10.000
PLANE ASPH CONC PAV (1.5")
SY 364,312.000 $1.000 $2.230 $5.000
CLEANING AND SEALING EXISTING JOINTS
LF 400.000 $27.000 $52.800 $40.000
HEADER TYPE EXPANSION JOINT
CF 28.000 $550.000 $759.000 $1,000.000
JOINT SEALANT
LF 160.000 $38.000 $26.400 $100.000
MOBILIZATION
LS 1.000 $688,015.790 $592,271.360 $850,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $12,000.000 $34,125.720 $8,500.000
RUMBLE STRIPS (SHOULDER)
LF 150,012.000 $0.200 $0.210 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 10,542.000 $30.000 $26.400 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 9.000 $2,400.000 $4,293.610 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,600.000 $1,375.000 $1,850.000
MTL BM GD FEN TRANS (NON - SYM)
EA 4.000 $1,150.000 $1,100.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 10,425.000 $2.400 $1.380 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $275.000 $220.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 9.000 $290.000 $220.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 13.000 $3,690.000 $5,748.720 $3,250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 13.000 $320.000 $220.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 106.000 $50.000 $66.380 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 19.000 $40.000 $72.420 $100.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 15.000 $40.000 $72.420 $100.000
INSTL DEL ASSM (D-DW)SZ 2(WC)GND
EA 156.000 $45.000 $66.380 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 90.000 $45.000 $33.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 18.000 $41.000 $33.000 $100.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,349.000 $1.000 $4.930 $6.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 2,678.000 $1.900 $1.540 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,621.000 $1.000 $1.210 $2.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 4,232.000 $2.800 $2.750 $6.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 20,840.000 $0.600 $0.770 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 83,132.000 $0.600 $0.770 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 83,340.000 $0.650 $0.770 $1.000
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 763.000 $3.000 $3.030 $8.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $270.000 $385.000 $750.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 11.000 $190.000 $440.000 $750.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $390.000 $467.500 $750.000
REFL PAV MRKR TY II-C-R
EA 2,750.000 $4.000 $4.950 $6.000
SP MIXES SP-D SAC-B PG70-22
TON 8,663.000 $150.000 $158.740 $136.000
TACK COAT
GAL 10,520.000 $6.000 $5.410 $8.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 21,976.000 $188.000 $194.290 $165.000
TACK COAT
GAL 26,162.000 $6.000 $5.170 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 1.000 $14,000.000 $25,637.150 $18,500.000
TMA (STATIONARY)
DAY 110.000 $300.000 $428.170 $250.000
TMA (MOBILE OPERATION)
DAY 39.000 $700.000 $1,082.500 $550.000
Totals: $7,550,032.590 $8,336,656.830 $8,855,785.000