HOWARD IH 20 (0005-05-112)

Items: 85

County: HOWARD
Length: N/A
Highway: IH 20
District: ABILENE
Control Number: 0005-05-112
DBE Goal: N/A
Project: BR 1702(476)
Guaranty: N/A
Time: 309 WORKING DAYS
Engineer's Estimate: $6,107,331.35
Date: 07/12/2017 (8 years ago)
Contract Number: N/A
Type: INSTALL CRASHWALLS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$6,107,331.35
$7,767,027.74
Over/Under Est: 27.18% $1,659,696.39
$7,843,203.00
Over/Under Est: 28.42% $1,735,871.65
Amt Left: 0.98% $76,175.26
Over/Under Est: 42.13% $2,573,311.15
Amt Left: 11.76% $913,614.76
Delta: -10.68% -$837,439.50
Over/Under Est: 63.65% $3,887,041.49
Amt Left: 28.68% $2,227,345.10
Delta: -15.13% -$1,313,730.34

Bid Items & Bid Tabulations

85 Total 0 of 85
HOWARD  |  IH 20  |  ABILENE  |  0005-05-112  |  07/12/2017  |  $6,107,331.35  |  BR 1702(476)  |  INSTL CRASHWALLS  |  309 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
GILVIN-TERRILL, LTD.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
REMOVING CONC (RIPRAP)
CY 61.000 $175.000 $600.000 $300.000 $270.000 $380.230
REMOVING CONC (CURB AND GUTTER)
LF 17.000 $35.000 $60.000 $110.000 $90.000 $60.790
REMOVING CONC (CTB)
LF 50.000 $35.000 $25.000 $100.000 $120.000 $238.080
BACKFILL (TY A)
LF 5,962.000 $4.000 $10.000 $10.000 $13.000 $11.940
REWORK BS MTL (TY C) (10"-14")(OC)
SY 30.000 $5.000 $210.000 $150.000 $160.000 $365.290
PRIME COAT (AE-P)
GAL 24.000 $12.000 $28.000 $110.000 $55.000 $63.840
ASPH (MULTI OPTION)
GAL 54.000 $10.000 $50.000 $110.000 $29.000 $26.650
AGGR(TY-B GR-3 SAC-B)
CY 2.000 $250.000 $5,800.000 $200.000 $3,900.000 $3,090.710
D-GR HMA(SQ) TY-D PG70-22
TON 16.000 $300.000 $2,500.000 $300.000 $815.000 $497.450
PLANE ASPH CONC PAV(0" TO 1")
SY 1,990.000 $4.000 $14.000 $15.000 $7.000 $11.300
PLANE ASPH CONC PAV (2")
SY 116.000 $5.000 $52.000 $110.000 $56.000 $79.870
FLOWABLE BACKFILL
CY 5.000 $225.000 $900.000 $500.000 $628.000 $536.530
CL C CONC (VEH DEFL WALL)(HPC)
CY 1,178.100 $1,200.000 $1,100.000 $1,520.000 $1,550.000 $1,726.060
REINF CONC SLAB (HPC)
SF 6,900.000 $25.000 $45.000 $35.250 $50.000 $72.740
SILICONE RESIN PAINT FINISH
SF 600.000 $10.000 $6.000 $10.000 $115.000 $20.450
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 199.000 $60.000 $80.000 $150.000 $220.000 $225.960
CONC STR REPAIR (EPOXY MORTAR)
SF 751.000 $90.000 $125.000 $150.000 $80.000 $227.900
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 53.000 $120.000 $120.000 $150.000 $300.000 $105.680
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 4,140.000 $190.000 $115.000 $150.000 $95.000 $149.250
RIPRAP (CONC)(4 IN)
CY 450.000 $575.000 $700.000 $750.000 $750.000 $688.120
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 128.000 $600.000 $780.000 $750.000 $830.000 $707.530
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 728.000 $38.000 $25.000 $75.000 $90.000 $35.650
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 1,055.000 $25.000 $40.000 $15.000 $58.000 $41.820
CLEANING EXISTING JOINTS
LF 218.000 $6.000 $15.000 $15.000 $57.000 $30.680
MULTI-LAYER POLYMER OVERLAY
SY 1,990.000 $60.000 $38.000 $75.000 $110.000 $49.660
STR STEEL (SHEAR CONNECTOR)
LB 1,638.000 $15.000 $10.000 $7.500 $95.000 $49.570
CLEAN & PAINT EXIST STR (SPL PROT SYS)
LS 1.000 $350,000.000 $585,000.000 $650,000.000 $700,000.000 $279,745.000
RAIL (TY SSTR)(HPC)
LF 540.000 $46.000 $145.000 $120.000 $320.000 $557.330
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 65.000 $92.000 $200.000 $75.000 $125.000 $111.750
HEADER TYPE EXPANSION JOINT
CF 305.700 $350.000 $275.000 $350.000 $225.000 $581.380
JOINT SEALANT
LF 620.000 $11.000 $15.000 $15.000 $115.000 $23.910
SHOT BLASTING
SY 1,990.000 $7.000 $8.000 $10.000 $22.000 $6.210
REMOVE STR (CONC)
EA 28.000 $3,000.000 $3,000.000 $1,500.000 $2,700.000 $6,240.240
REMOV STR (APPROACH SLAB)
EA 2.000 $3,500.000 $10,500.000 $2,000.000 $13,000.000 $6,273.490
REMOV STR (BRIDGE SLAB)
LF 230.000 $500.000 $550.000 $100.000 $400.000 $138.980
REMOVE STR (RAIL)
LF 44.000 $21.000 $200.000 $85.000 $225.000 $286.670
MOBILIZATION
LS 1.000 $540,884.700 $776,000.000 $780,000.000 $200,000.000 $1,182,023.200
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $7,000.000 $21,200.000 $20,000.000 $8,000.000 $11,130.190
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $2.500 $7.000 $5.000 $30.000 $4.090
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $0.800 $2.000 $1.000 $11.000 $1.890
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $5.000 $11.000 $7.500 $72.000 $13.790
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $1.450 $2.000 $1.000 $25.000 $3.340
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,440.000 $29.000 $64.000 $65.000 $180.000 $59.460
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 15,870.000 $6.000 $25.000 $5.000 $16.000 $15.590
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 1,440.000 $11.000 $13.000 $5.000 $25.000 $42.230
PERM CTB(SGL SLOPE)(TY 1)(42)(HPC)
LF 3,592.000 $55.000 $130.000 $120.000 $250.000 $293.020
PERM CTB(SGL SLOPE)(TY 1)(54)(HPC)
LF 435.000 $80.000 $165.000 $135.000 $250.000 $413.490
PERM CTB(F-SHAPE)(TY 1)(HPC)
LF 50.000 $40.000 $100.000 $130.000 $250.000 $654.670
CONC CURB & GUTTER (TY II)
LF 20.000 $50.000 $240.000 $40.000 $75.000 $91.420
MTL W-BEAM GD FEN (TIM POST)
LF 126.000 $24.000 $25.000 $25.000 $30.000 $21.290
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,500.000 $1,800.000 $2,000.000 $2,500.000 $1,691.630
SHORT RADIUS
LF 498.000 $30.000 $30.000 $30.000 $40.000 $25.540
MTL BEAM GD FEN TRANS(THRIE BEAM)28"
EA 11.000 $1,600.000 $1,700.000 $1,500.000 $2,200.000 $1,550.570
REMOVE METAL BEAM GUARD FENCE
LF 3,048.000 $3.250 $2.000 $2.000 $5.000 $2.040
REMOVE TERMINAL ANCHOR SECTION
EA 25.000 $350.000 $200.000 $120.000 $500.000 $146.240
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,600.000 $2,300.000 $2,500.000 $3,000.000 $2,164.770
GUARDRAIL END TREATMENT (REMOVE)
EA 11.000 $300.000 $300.000 $150.000 $300.000 $185.060
CRASH CUSH ATTEN (INSTL)
EA 23.000 $16,000.000 $22,000.000 $14,500.000 $28,000.000 $13,435.470
CRASH CUSH ATTEN (MOVE & RESET)
EA 74.000 $1,800.000 $2,000.000 $650.000 $1,800.000 $1,336.030
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $800.000 $3,000.000 $425.000 $1,100.000 $885.930
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $8,000.000 $8,000.000 $7,500.000 $15,000.000 $9,471.860
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 8.000 $35.000 $35.000 $24.000 $65.000 $69.830
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 80.000 $15.000 $30.000 $11.000 $69.000 $176.860
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 76,320.000 $1.000 $0.950 $1.750 $1.000 $0.800
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 75,600.000 $1.000 $0.950 $1.750 $1.000 $0.790
PAVEMENT SEALER 4"
LF 2,600.000 $0.250 $0.730 $0.500 $0.600 $0.490
PAVEMENT SEALER 24"
LF 94.000 $3.000 $1.680 $3.000 $2.000 $2.910
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 14,251.000 $0.650 $0.500 $1.500 $1.000 $0.760
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 9,420.000 $0.650 $0.500 $1.500 $1.000 $0.660
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 6,000.000 $0.650 $0.500 $1.500 $1.000 $0.670
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 94.000 $4.500 $27.930 $33.000 $18.000 $18.040
PREFAB PAV MRK TY B (Y)(4")(SLD)
LF 2,600.000 $4.500 $6.700 $6.250 $6.000 $5.230
REFL PAV MRKR TY II-A-A
EA 19.000 $3.000 $5.590 $3.000 $8.000 $11.740
REFL PAV MRKR TY II-C-R
EA 717.000 $4.000 $4.470 $3.000 $6.000 $3.910
ELIM EXT PAV MRK & MRKS (4")
LF 14,213.000 $0.500 $6.000 $3.000 $1.000 $0.610
PAV SURF PREP FOR MRK (4")
LF 2,600.000 $0.200 $0.850 $0.600 $1.000 $0.470
PAV SURF PREP FOR MRK (24")
LF 94.000 $3.000 $2.800 $3.250 $2.000 $2.800
CONCRETE RAIL REPAIR (IN-KIND)
LF 12.000 $500.000 $1,250.000 $650.000 $450.000 $941.850
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 336.000 $25.000 $55.000 $40.000 $19.000 $105.670
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 55.000 $75.000 $55.000 $125.000 $58.000 $273.440
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 170.000 $15.000 $55.000 $15.000 $33.000 $40.550
REP STL BRIDGE MEMBER(STRAIGHTEN MEMB)
EA 1.000 $3,000.000 $45,000.000 $5,000.000 $42,000.000 $20,588.720
CARBON FIBER REINF POLYMER PROTECTION
SF 1,173.000 $60.000 $74.000 $15.000 $132.000 $157.930
CONCRETE BEAM REPAIR (CFRP)
EA 41.000 $8,000.000 $5,100.000 $12,250.000 $4,100.000 $13,812.110
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $12,000.000 $30,000.000 $15,000.000 $10,000.000 $36,611.630
Totals: $6,107,331.350 $7,767,027.740 $7,843,203.000 $8,680,642.500 $9,994,372.852