HOWARD IH 20 (0005-05-110)

Items: 43

County: HOWARD
Length: N/A
Highway: IH 20
District: ABILENE
Control Number: 0005-05-110
DBE Goal: N/A
Project: NH 2017(833)
Guaranty: N/A
Time: 89 WORKING DAYS
Engineer's Estimate: $6,397,011.35
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$6,397,011.35
$5,321,335.32
Over/Under Est: -16.82% -$1,075,676.03
$5,593,146.31
Over/Under Est: -12.57% -$803,865.04
Amt Left: 5.11% $271,810.99
$6,103,043.44
Over/Under Est: -4.6% -$293,967.91
Amt Left: 14.69% $781,708.12
Delta: -9.12% -$509,897.13
Over/Under Est: 0.5% $32,167.63
Amt Left: 20.82% $1,107,843.66
Delta: -5.34% -$326,135.54
Over/Under Est: 0.99% $63,267.87
Amt Left: 21.4% $1,138,943.90
Delta: -0.48% -$31,100.24
Over/Under Est: 9.01% $576,667.64
Amt Left: 31.05% $1,652,343.67
Delta: -7.95% -$513,399.77

Bid Items & Bid Tabulations

43 Total 0 of 43
HOWARD  |  IH 20  |  ABILENE  |  0005-05-110  |  03/07/2017  |  $6,397,011.35  |  NH 2017(833)  |  OVERLAY  |  89 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PRICE CONSTRUCTION, LTD.
FNF CONSTRUCTION, INC.
REECE ALBERT, INC.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
NOBLES ROAD CONSTRUCTION, INC.
AUSTIN BRIDGE & ROAD SERVICES, LP
BLADING
HR 20.000 $200.000 $213.730 $130.000 $204.230 $321.520 $200.000 $150.000
ASPH (MULTI OPTION)
GAL 76,245.000 $3.700 $2.590 $3.000 $2.850 $2.720 $3.080 $3.800
AGGR(TY-B GR-4 SAC-B)
CY 2,019.000 $90.000 $80.170 $200.000 $129.160 $108.460 $134.500 $100.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 23,297.000 $130.000 $109.530 $100.000 $123.150 $115.100 $125.000 $128.150
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 34,770.000 $46.000 $45.830 $34.500 $50.280 $52.940 $45.400 $54.240
PLANE ASPH CONC PAV (1.5")
SY 211,814.000 $1.250 $0.810 $1.750 $0.910 $1.560 $1.500 $1.450
DRILL SHAFT (24 IN)
LF 92.000 $145.000 $120.750 $145.000 $122.910 $115.000 $121.000 $100.350
DRILLED SHAFT (12 IN)
LF 62.000 $40.000 $147.000 $174.000 $149.630 $140.000 $147.000 $67.650
RIPRAP (MOW STRIP)(4 IN)
CY 225.000 $500.000 $500.000 $500.000 $534.390 $862.860 $525.000 $630.000
MOBILIZATION
LS 1.000 $500,000.000 $113,530.720 $560,000.000 $154,180.440 $600,000.000 $600,000.000 $693,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $9,500.000 $12,460.030 $5,000.000 $40,106.010 $8,000.000 $16,950.000 $11,500.000
RUMBLE STRIPS (SHOULDER)
LF 92,362.000 $0.250 $0.130 $0.130 $0.130 $0.150 $0.160 $0.150
MTL W-BEAM GD FEN (TIM POST)
LF 4,400.000 $25.000 $20.000 $19.100 $21.380 $17.750 $21.000 $22.300
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $2,000.000 $2,205.000 $2,250.000 $2,244.440 $1,390.000 $2,205.000 $1,963.750
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,600.000 $1,000.000 $1,260.000 $1,068.780 $840.000 $1,050.000 $1,011.650
REMOVE METAL BEAM GUARD FENCE
LF 4,400.000 $4.000 $2.500 $1.600 $2.670 $1.000 $2.650 $1.500
REMOVE TERMINAL ANCHOR SECTION
EA 9.000 $300.000 $250.000 $160.000 $267.200 $80.000 $262.000 $238.060
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $3,000.000 $2,500.000 $2,400.000 $2,671.960 $1,950.000 $2,625.000 $2,231.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $325.000 $250.000 $250.000 $267.200 $150.000 $262.000 $238.050
ALUMINUM SIGNS (TY A)
SF 53.000 $27.000 $22.050 $25.000 $22.440 $21.000 $22.050 $29.300
ALUMINUM SIGNS (TY G)
SF 931.000 $24.000 $26.250 $30.000 $26.720 $25.000 $26.250 $35.750
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $460.000 $735.000 $840.000 $748.150 $700.000 $735.000 $771.200
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $500.000 $866.250 $1,000.000 $881.740 $825.000 $865.000 $1,031.000
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 11.000 $80.000 $210.000 $240.000 $213.760 $200.000 $210.000 $177.550
INSTALL LRSS (STRUCT STEEL)
LB 6,226.000 $4.000 $5.090 $5.850 $5.180 $4.850 $5.000 $6.950
REMOVE LRSA
EA 14.000 $740.000 $787.500 $900.000 $801.590 $750.000 $787.000 $2,382.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 37.000 $68.000 $78.750 $122.000 $80.160 $57.000 $78.000 $54.500
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 12.000 $18.000 $26.250 $30.000 $26.720 $22.000 $26.000 $27.250
INSTL DEL ASSM (D-SY)SZ 2(WC)GND
EA 15.000 $75.000 $26.250 $30.000 $26.720 $57.000 $26.000 $13.100
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 12.000 $15.000 $26.250 $30.000 $26.720 $22.000 $26.000 $24.000
INSTL DEL ASSM (D-DW)SZ 2(WC)GND
EA 53.000 $38.000 $78.750 $90.000 $80.160 $58.000 $78.000 $54.500
INSTL OM ASSM (OM-2Y)(WC)GND
EA 22.000 $80.000 $78.750 $90.000 $80.160 $58.000 $78.000 $54.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 33.000 $25.000 $42.000 $50.000 $42.750 $24.000 $42.000 $24.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,476.000 $1.250 $1.680 $2.050 $1.820 $1.080 $1.450 $0.450
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 492.000 $1.200 $0.300 $1.150 $0.310 $1.800 $1.000 $0.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,214.000 $1.000 $0.610 $1.050 $0.620 $1.000 $0.890 $0.950
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 417.000 $2.500 $2.100 $2.750 $2.140 $3.150 $2.360 $0.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 12,600.000 $0.380 $0.300 $0.450 $0.310 $0.450 $0.370 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 50,530.000 $0.300 $0.300 $0.300 $0.310 $0.310 $0.310 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 50,797.000 $0.350 $0.300 $0.300 $0.310 $0.310 $0.310 $0.450
PREFAB PAV MRK TY C (W) (NUMBER)
EA 4.000 $320.000 $630.000 $265.000 $641.270 $270.000 $265.000 $272.550
REFL PAV MRKR TY II-C-R
EA 821.000 $4.000 $3.680 $4.500 $3.740 $4.180 $3.650 $3.800
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,000.000 $16,133.260 $12,000.000 $886.900 $11,775.910 $4,725.000 $20,500.000
Totals: $6,397,011.350 $5,321,335.320 $5,593,146.310 $6,103,043.440 $6,429,178.980 $6,460,279.220 $6,973,678.990