HOUSTON COUNTY ROAD 4700 (0911-28-061)

Items: 48

County: HOUSTON
Length: 0.0000 MILES
Highway: COUNTY ROAD 4700
District: LUFKIN
Control Number: 0911-28-061
DBE Goal: 4.0%
Project: BR 2B23(196)
Guaranty: $31,000.00
Time: 208 WORKING DAYS
Engineer's Estimate: $1,498,562.00
Date: 07/02/2025 (11 months ago)
Contract Number: 7253230
Type: BRIDGE REPLACEMENT
Project ID: A00140933
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESSE SISCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,498,562.00
$1,408,211.50
Over/Under Est: -6.03% -$90,350.50
$1,478,124.50
Over/Under Est: -1.36% -$20,437.50
Amt Left: 4.96% $69,913.00
$1,479,745.50
Over/Under Est: -1.26% -$18,816.50
Amt Left: 5.08% $71,534.00
Delta: -0.11% -$1,621.00
Over/Under Est: -0.95% -$14,211.00
Amt Left: 5.41% $76,139.50
Delta: -0.31% -$4,605.50
Over/Under Est: 1.92% $28,812.20
Amt Left: 8.46% $119,162.70
Delta: -2.90% -$43,023.20
$1,699,830.01
Over/Under Est: 13.43% $201,268.01
Amt Left: 20.71% $291,618.51
Delta: -11.29% -$172,455.81
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 9.22% $129,837.10
ODUM SERVICES, LLC 6.92% $97,448.24
DIAMOND ELITE BARRICADES, LLC 1.56% $21,968.10
TORO BRAVO CONSTRUCTION, LLC 1.46% $20,559.89
TORO BRAVO CONSTRUCTION, LLC 0.49% $6,900.24
Total: 19.65% $276,713.57

Bid Items & Bid Tabulations

48 Total 0 of 48
HOUSTON  |  COUNTY ROAD 4700  |  LUFKIN  |  0911-28-061  |  07/02/2025  |  $1,498,562.00  |  BR 2B23(196)  |  BRIDGE REPL  |  208 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BLACKSMITH VENTURES LLC
SKYLINE BRIDGE LLC
THK CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
TRUE ROADS CONSTRUCTION, LLC
TALBERT COMPANIES LLC
PREPARING ROW
STA 7.400 $2,000.000 $4,000.000 $3,000.000 $2,000.000 $4,000.000 $9,000.000 $4,567.100
EXCAV (ROADWAY)
CY 2,401.000 $20.000 $10.000 $17.000 $18.000 $20.000 $22.000 $38.150
EMBANK (FNL)(OC)(TY C)
CY 336.000 $30.000 $25.000 $60.000 $20.000 $25.000 $35.000 $52.320
FURN & PLACE TOPSOIL (4")
SY 1,866.000 $4.000 $5.000 $5.000 $3.500 $3.000 $6.000 $4.970
BLOCK SODDING
SY 200.000 $10.000 $50.000 $12.000 $11.000 $10.000 $12.000 $9.679
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 1,946.000 $2.000 $1.000 $2.500 $1.100 $2.500 $1.200 $1.591
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 973.000 $2.000 $1.000 $2.500 $1.100 $2.000 $1.200 $0.436
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 973.000 $2.000 $1.000 $2.500 $1.100 $2.000 $1.200 $0.436
VEGETATIVE WATERING
TGL 44.000 $10.000 $10.000 $1.000 $10.000 $1.000 $30.000 $20.492
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 1,439.000 $45.000 $90.000 $52.000 $50.000 $50.000 $38.000 $37.060
CEM STABIL BKFL
CY 76.400 $350.000 $250.000 $325.000 $350.000 $290.000 $400.000 $272.500
TEMPORARY SPL SHORING
SF 290.000 $45.000 $10.000 $35.000 $40.000 $120.000 $75.000 $65.400
DRILL SHAFT (24 IN)
LF 618.000 $300.000 $295.000 $285.000 $275.000 $200.000 $340.000 $239.800
CL C CONC (ABUT)
CY 39.200 $1,200.000 $1,500.000 $1,400.000 $1,100.000 $2,100.000 $1,625.000 $1,526.000
CL C CONC (CAP)
CY 26.400 $1,750.000 $1,700.000 $1,800.000 $1,500.000 $2,200.000 $1,550.000 $1,635.000
CL C CONC (COLUMN)
CY 9.100 $2,000.000 $2,000.000 $2,100.000 $2,500.000 $2,200.000 $2,300.000 $1,744.000
REINF CONC SLAB (SLAB BEAM)
SF 4,030.000 $28.000 $21.000 $29.000 $28.000 $30.000 $25.000 $30.520
PRESTR CONC SLAB BEAM (5SB12)
LF 760.000 $280.000 $225.000 $275.000 $290.380 $250.000 $265.000 $201.105
RIPRAP (STONE PROTECTION)(24 IN)
CY 886.100 $290.000 $225.000 $200.000 $190.000 $210.000 $210.000 $305.200
RAIL (TY T223)
LF 358.000 $200.000 $75.000 $175.000 $200.000 $160.000 $150.000 $196.200
TYPE A JOINT
LF 104.000 $50.000 $30.000 $95.000 $20.000 $100.000 $48.000 $130.800
RC PIPE (CL III)(18 IN)
LF 90.000 $90.000 $85.000 $70.000 $80.000 $60.000 $125.000 $87.200
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $1,500.000 $2,500.000 $1,000.000 $1,000.000 $2,200.000 $1,700.000 $1,194.640
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $5,000.000 $12,500.000 $50,000.000 $25,000.000 $14,000.000 $16,350.000
MOBILIZATION
LS 1.000 $140,000.000 $175,000.000 $125,000.000 $140,000.000 $120,000.000 $125,000.000 $276,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $2,000.000 $500.000 $2,500.000 $932.800 $4,250.000 $2,000.000 $2,180.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 160.000 $50.000 $30.000 $50.000 $48.400 $1.000 $52.000 $45.104
ROCK FILTER DAMS (REMOVE)
LF 160.000 $15.000 $1.000 $10.000 $22.000 $1.000 $24.000 $13.571
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $30.000 $30.000 $10.000 $46.200 $1.000 $50.000 $35.970
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $1.000 $1.000 $16.500 $1.000 $18.000 $15.652
CONSTRUCTION PERIMETER FENCE
LF 60.000 $10.000 $10.000 $9.000 $9.900 $1.000 $10.800 $10.093
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,529.000 $4.000 $5.000 $4.000 $4.950 $1.000 $5.000 $5.308
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,529.000 $1.000 $1.000 $1.500 $1.100 $1.000 $1.200 $1.406
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $80.000 $100.000 $150.000 $100.000 $150.000 $150.000 $102.188
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $40.000 $100.000 $150.000 $100.000 $100.000 $100.000 $50.413
DRIVEWAYS (BASE)
SY 221.000 $60.000 $75.000 $70.000 $50.000 $60.000 $55.000 $59.950
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $35.000 $40.000 $32.000 $45.470 $30.000 $34.000 $42.510
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,900.000 $1,825.000 $1,750.000 $1,457.500 $1,500.000 $1,600.000 $1,989.250
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,500.000 $1,765.000 $1,850.000 $1,567.500 $1,600.000 $1,700.000 $1,923.850
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,500.000 $4,000.000 $3,800.000 $3,520.000 $3,200.000 $3,800.000 $3,924.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
EA 4.000 $5,000.000 $23,000.000 $20,000.000 $20,350.000 $18,500.000 $20,500.000 $21,255.000
WIRE FENCE (TY C)
LF 100.000 $50.000 $25.000 $35.000 $40.000 $20.000 $19.000 $49.585
WIRE FENCE (TY D)
LF 326.000 $30.000 $25.000 $40.000 $40.000 $20.000 $36.000 $22.890
GATE (TY 1)
EA 6.000 $2,500.000 $250.000 $2,500.000 $500.000 $800.000 $1,000.000 $2,764.055
REMOVE SM RD SN SUP&AM
EA 2.000 $250.000 $1.000 $200.000 $250.000 $100.000 $150.000 $175.490
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 12.000 $40.000 $50.000 $50.000 $19.800 $20.000 $22.000 $32.569
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 5.000 $30.000 $65.000 $50.000 $27.500 $25.000 $30.000 $58.816
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 8.000 $125.000 $50.000 $100.000 $88.000 $500.000 $90.000 $190.750
Totals: $1,498,562.000 $1,408,211.500 $1,478,124.500 $1,479,745.500 $1,484,351.000 $1,527,374.200 $1,699,830.006
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $2,000.00