HOUSTON COUNTY ROAD 4700 (0911-28-061)
Items: 48
County: HOUSTON
Length: 0.0000 MILES
Highway: COUNTY ROAD 4700
District: LUFKIN
Control Number: 0911-28-061
DBE Goal: 4.0%
Project: BR 2B23(196)
Guaranty: $31,000.00
Time: 208 WORKING DAYS
Engineer's Estimate: $1,498,562.00
Date: 07/02/2025 (11 months ago)
Contract Number: 7253230
Type: BRIDGE REPLACEMENT
Project ID: A00140933
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESSE SISCO
HOUSTON COUNTY ROAD 4700 (0911-28-061)
Project Name: N/A
Project: BR 2B23(196)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT LEE CREEK
Limits To: .
Project Description: REPLACE BRIDGE AND APPROACHES
HOUSTON CEDAR SPRINGS (0911-28-065)
Project Name: CR 4050 AT HARTTS CREEK TRIB - HBP
Project: BR 2024(003)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: CR 4050 AT HARTTS CREEK TRIBUTARY
Limits To: .
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,498,562.00 | |||
| $1,408,211.50 |
-6.03%
-$90,350.50
|
|||
| $1,478,124.50 |
-1.36%
-$20,437.50
|
4.96%
$69,913.00
|
||
| $1,479,745.50 |
-1.26%
-$18,816.50
|
5.08%
$71,534.00
|
-0.11%
-$1,621.00
|
|
| $1,484,351.00 |
-0.95%
-$14,211.00
|
5.41%
$76,139.50
|
-0.31%
-$4,605.50
|
|
| $1,527,374.20 |
1.92%
$28,812.20
|
8.46%
$119,162.70
|
-2.90%
-$43,023.20
|
|
| $1,699,830.01 |
13.43%
$201,268.01
|
20.71%
$291,618.51
|
-11.29%
-$172,455.81
|
E
Engineer's Estimate
$1,498,562.00
1
Awarded
$1,408,211.50
Over/Under Est:
-6.03%
-$90,350.50
$1,478,124.50
Over/Under Est:
-1.36%
-$20,437.50
Amt Left:
4.96%
$69,913.00
$1,479,745.50
Over/Under Est:
-1.26%
-$18,816.50
Amt Left:
5.08%
$71,534.00
Delta:
-0.11%
-$1,621.00
$1,484,351.00
Over/Under Est:
-0.95%
-$14,211.00
Amt Left:
5.41%
$76,139.50
Delta:
-0.31%
-$4,605.50
$1,527,374.20
Over/Under Est:
1.92%
$28,812.20
Amt Left:
8.46%
$119,162.70
Delta:
-2.90%
-$43,023.20
$1,699,830.01
Over/Under Est:
13.43%
$201,268.01
Amt Left:
20.71%
$291,618.51
Delta:
-11.29%
-$172,455.81
| Subcontractor | Percentage | Amount |
|---|---|---|
| HODGES AND SON CONSTRUCTION COMPANY, INC. | 9.22% | $129,837.10 |
| ODUM SERVICES, LLC | 6.92% | $97,448.24 |
| DIAMOND ELITE BARRICADES, LLC | 1.56% | $21,968.10 |
| TORO BRAVO CONSTRUCTION, LLC | 1.46% | $20,559.89 |
| TORO BRAVO CONSTRUCTION, LLC | 0.49% | $6,900.24 |
| Total: | 19.65% | $276,713.57 |
Bid Items & Bid Tabulations
48
Total
0 of 48
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $2,000.00 |