HOPKINS CR (0901-28-097)

Items: 36

County: HOPKINS
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-28-097
DBE Goal: N/A
Project: BR 2022(357)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $958,568.40
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$958,568.40
$842,684.36
Over/Under Est: -12.09% -$115,884.04
Over/Under Est: -1.06% -$10,138.00
Amt Left: 12.55% $105,746.04
Over/Under Est: 4.28% $41,059.50
Amt Left: 18.62% $156,943.54
Delta: -5.40% -$51,197.50

Bid Items & Bid Tabulations

36 Total 0 of 36
HOPKINS  |  CR  |  PARIS  |  0901-28-097  |  05/05/2023  |  $958,568.40  |  BR 2022(357)  |  BRIDGE REPL  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
HIGHWAY 19 CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 7.260 $2,000.000 $1,500.000 $2,500.000 $4,200.000
EXCAVATION (ROADWAY)
CY 200.000 $25.000 $18.000 $25.000 $25.000
EXCAVATION (CHANNEL)
CY 1,732.000 $30.000 $15.000 $25.000 $15.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 732.000 $30.000 $18.000 $30.000 $30.000
BROADCAST SEED (TEMP) (WARM)
SY 818.000 $0.300 $0.010 $1.000 $2.000
BROADCAST SEED (TEMP) (COOL)
SY 818.000 $0.300 $0.010 $1.000 $2.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,636.000 $2.000 $4.410 $2.000 $3.000
VEGETATIVE WATERING
MG 20.000 $20.000 $20.000 $100.000 $1.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 808.000 $32.000 $40.000 $27.000 $50.000
REWORK BS MTL (TY B) (9-18") (ORD COMP)
SY 472.000 $20.000 $40.000 $11.000 $12.000
CEM STABIL BKFL
CY 79.000 $200.000 $250.000 $250.000 $250.000
DRILL SHAFT (24 IN)
LF 276.000 $175.000 $156.000 $157.000 $135.000
DRILL SHAFT (36 IN)
LF 276.000 $250.000 $202.000 $164.000 $180.000
CL C CONC (ABUT)
CY 56.800 $1,200.000 $1,000.000 $1,194.000 $1,500.000
REINF CONC SLAB
SF 1,950.000 $30.000 $25.000 $31.000 $35.000
REINF CONC SLAB (SLAB BEAM)
SF 1,170.000 $25.000 $20.000 $25.000 $26.000
PRESTR CONC SLAB BEAM (5SB15)
LF 222.110 $260.000 $297.150 $320.000 $290.000
PRESTR CONC GIRDER (TX28)
LF 298.000 $250.000 $262.570 $301.000 $330.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 896.000 $200.000 $164.000 $180.000 $205.000
RAIL (TY T631LS)
LF 300.000 $75.000 $78.750 $66.000 $80.000
RC PIPE (CL III)(15 IN)
LF 20.000 $95.000 $90.000 $50.000 $200.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 2.000 $790.000 $1,000.000 $1,000.000 $4,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $13,000.000 $5,000.000 $10,000.000 $10,000.000
REMOV STR (PIPE)
EA 1.000 $350.000 $200.000 $500.000 $500.000
MOBILIZATION
LS 1.000 $87,143.000 $70,000.000 $100,000.000 $85,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $2,000.000 $1,134.000 $1,925.000 $1,200.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 82.000 $35.000 $40.000 $35.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 82.000 $10.000 $1.000 $10.000 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 178.000 $20.000 $1.000 $1.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 178.000 $6.000 $1.000 $1.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,300.000 $5.000 $3.500 $3.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,300.000 $2.000 $1.000 $1.000 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $30.000 $2.400 $27.000 $30.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,100.000 $3,071.250 $3,000.000 $3,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $30.000 $31.500 $35.000 $30.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 160.000 $130.000 $246.490 $250.000 $250.000
Totals: $958,568.400 $842,684.366 $948,430.400 $999,627.900