HOPKINS FM 900 (0680-05-014)
Items: 80
County: HOPKINS
Length: N/A
Highway: FM 900
District: PARIS
Control Number: 0680-05-014
DBE Goal: N/A
Project: STP 2B23(053)HES
Guaranty: N/A
Time: 223 WORKING DAYS
Engineer's Estimate: $2,950,739.80
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,950,739.80 | |||
| $3,356,595.02 |
13.75%
$405,855.22
|
|||
| $3,661,613.46 |
24.09%
$710,873.66
|
9.09%
$305,018.44
|
||
| $4,447,520.19 |
50.73%
$1,496,780.39
|
32.5%
$1,090,925.17
|
-21.46%
-$785,906.73
|
E
Engineer's Estimate
$2,950,739.80
1
Awarded
$3,356,595.02
Over/Under Est:
13.75%
$405,855.22
$3,661,613.46
Over/Under Est:
24.09%
$710,873.66
Amt Left:
9.09%
$305,018.44
$4,447,520.19
Over/Under Est:
50.73%
$1,496,780.39
Amt Left:
32.5%
$1,090,925.17
Delta:
-21.46%
-$785,906.73
| Subcontractor | Percentage | Amount |
|---|---|---|
| BAHENA CONSTRUCTION CO., INC. | 15.31% | $508,669.45 |
| CATOCON, INC. | 6.02% | $200,012.42 |
| STRIPING TECHNOLOGY, L.P. | 5.18% | $172,103.71 |
| MURRAY CONSTRUCTION | 1.96% | $65,120.32 |
| DUSTIN ALLEN, INC. | 0.89% | $29,569.94 |
| PANOLA SIGN & BARRICADE, INC. | 0.76% | $25,250.74 |
| A-CORE CONCRETE CUTTING OF TEXAS, INC. | 0.49% | $16,280.08 |
| Total: | 30.61% | $1,017,006.66 |