Bid Cobra

HOPKINS SH 11 (0083-12-004)

Items: 54

County: HOPKINS
Length: 2.4700 MILES
Highway: SH 11
District: PARIS
Control Number: 0083-12-004
DBE Goal: 0.0%
Project: C 83-12-4
Guaranty: $47,000.00
Time: 46 WORKING DAYS
Engineer's Estimate: $1,952,070.08
Date: 03/05/2026 (3 months ago) Changed
Contract Number: 5253017
Type: PREVENTIVE MAINTENANCE
Project ID: A00138814
Project Description: FDR W/OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,952,070.08
1
$1,638,857.87
Over/Under Est: -16.05% -$313,212.21
Over/Under Est: -13.53% -$264,075.23
Amt Left: 3% $49,136.98
Over/Under Est: -4.83% -$94,373.93
Amt Left: 13.35% $218,838.28
Delta: -10.05% -$169,701.30
Over/Under Est: -0.44% -$8,572.61
Amt Left: 18.59% $304,639.60
Delta: -4.62% -$85,801.32

Bid Items & Bid Tabulations

54 Total 0 of 54
HOPKINS  |  SH 11  |  PARIS  |  0083-12-004  |  03/05/2026  |  $1,952,070.08  |  C 83-12-4  |  PREVENT MAINT  |  46 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
BAKER & COMPANY CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
BACKFILL (TY A)
STA 104.000 $200.000 $255.520 $217.000 $400.000 $480.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 6,891.000 $0.650 $0.490 $0.400 $0.360 $0.500
VEGETATIVE WATERING
TGL 62.000 $100.000 $220.860 $1.050 $30.000 $170.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 1,723.000 $4.000 $4.370 $5.250 $5.000 $4.850
D-GR HMA TY-C SAC-A PG64-22(EXEMPT)
TON 1.000 $400.000 $1,515.350 $525.000 $1,500.000 $140.000
SP MIXES SP-C PG64-22
TON 6,129.000 $150.000 $113.940 $128.100 $145.000 $120.900
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 4,000.000 $80.000 $76.910 $82.500 $65.000 $106.130
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 55,717.000 $2.500 $2.520 $0.950 $2.450 $2.500
CONC PVMT (CRCP) (9")
SY 13.000 $300.000 $787.500 $1,050.000 $400.000 $550.000
CUT & RESTORING PAV
SY 13.000 $250.000 $406.170 $578.000 $175.000 $580.000
RIPRAP (CONC)(4 IN)
CY 45.400 $550.000 $761.250 $893.000 $800.000 $640.000
CLEANING AND SEALING EXISTING JOINTS
LF 58.000 $50.000 $108.150 $108.000 $50.000 $85.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 950.000 $40.000 $49.350 $49.500 $50.000 $60.000
MOBILIZATION
LS 1.000 $177,461.000 $81,942.890 $60,000.000 $140,000.000 $98,025.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $10,000.000 $18,106.260 $18,510.000 $10,000.000 $32,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 90.000 $100.000 $73.980 $117.000 $125.000 $225.000
TMA (MOBILE OPERATION)
DAY 90.000 $320.000 $10.000 $335.000 $300.000 $200.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 200.000 $6.000 $4.250 $4.750 $11.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $6.000 $1.050 $1.050 $2.000 $1.500
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $38.000 $26.250 $27.000 $28.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,300.000 $2,440.370 $2,130.000 $2,150.000 $2,025.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,300.000 $3,255.000 $3,255.000 $3,300.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $325.000 $315.000 $315.000 $220.000 $300.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 287.000 $5.000 $4.000 $6.850 $6.500 $6.500
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 823.000 $4.000 $4.000 $6.850 $6.500 $6.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,536.000 $1.000 $1.610 $1.600 $1.500 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,054.000 $1.000 $1.610 $1.350 $1.500 $1.750
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,847.000 $1.250 $1.050 $1.050 $1.100 $1.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 84.000 $8.470 $8.400 $10.000 $8.800 $8.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 10.000 $206.500 $147.000 $205.000 $155.000 $140.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 8.000 $234.000 $173.250 $237.000 $185.000 $165.000
RE PM TY III (W)(6")(SLD)
LF 5,919.000 $1.000 $0.570 $1.000 $0.600 $0.540
RE PM TY III (W)(6")(BRK)
LF 3,800.000 $2.000 $0.590 $1.000 $0.600 $0.560
RE PM TY III (W)(8")(SLD)
LF 2,210.000 $1.750 $0.890 $1.100 $0.950 $0.850
RE PM TY III (W)(8")(DOT)
LF 918.000 $2.000 $1.050 $1.300 $1.100 $1.000
RE PM TY III (W)(24")(SLD)
LF 144.000 $8.470 $8.400 $11.000 $8.800 $8.000
RE PM TY III (Y)(6")(SLD)
LF 5,620.000 $1.000 $0.570 $1.000 $0.600 $0.540
RE PM TY III (Y)(6")(BRK)
LF 5,876.000 $1.500 $0.590 $1.000 $0.600 $0.560
RE PM TY III (Y)(24")(SLD)
LF 38.000 $20.000 $8.400 $11.000 $8.750 $8.000
RE PM TY III (W)(ARROW)
EA 8.000 $500.000 $315.000 $210.000 $330.000 $300.000
RE PM TY III (W)(WORD)
EA 8.000 $300.000 $341.250 $242.000 $355.000 $325.000
RE PM TY III (W)(36" YLD TRI)
EA 49.000 $100.000 $78.750 $58.000 $85.000 $75.000
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 72.000 $0.760 $2.100 $0.700 $2.200 $2.000
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 20,476.000 $0.550 $0.790 $0.700 $0.830 $0.750
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 982.000 $1.000 $1.050 $0.700 $1.100 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 26,825.000 $0.750 $0.790 $0.700 $0.830 $0.750
ELIM EXT PM & MRKS (4")
LF 4,671.000 $0.750 $0.260 $0.700 $0.270 $0.250
ELIM EXT PM & MRKS (6")
LF 19,683.000 $1.000 $0.370 $0.700 $0.380 $0.350
ELIM EXT PM & MRKS (8")
LF 2,581.000 $1.500 $0.680 $0.800 $0.700 $0.650
ELIM EXT PM & MRKS (24")
LF 170.000 $3.000 $3.150 $2.650 $3.300 $3.000
ELIM EXT PM & MRKS (ARROW)
EA 8.000 $70.000 $105.000 $84.000 $110.000 $100.000
ELIM EXT PM & MRKS (WORD)
EA 8.000 $75.000 $105.000 $84.000 $110.000 $100.000
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 49.000 $35.000 $21.000 $21.000 $22.000 $20.000
BONDING COURSE
GAL 13,930.000 $3.500 $4.510 $5.000 $5.500 $7.200
Totals: $1,952,070.080 $1,638,857.870 $1,687,994.850 $1,857,696.150 $1,943,497.470
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $17,746.10
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $35,492.20
Total: $53,238.30