Show Job Controls
Bid Cobra

HOPKINS IH 30 (0009-09-115)

Items: 61

County: HOPKINS
Length: 0.1940 MILES
Highway: IH 30
District: PARIS
Control Number: 0009-09-115
DBE Goal: 0.0%
Project: BR 2026(233)
Guaranty: $114,000.00
Time: 286 WORKING DAYS
Engineer's Estimate: $2,874,515.70
Date: 01/07/2026 (5 months ago)
Contract Number: 1263215
Type: BRIDGE MAINTENANCE
Project ID: A00209704
Contract Type: Federal
Project Description: IH 30 EB/WB/S FR/N FR AT CLENDELING CREEK
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$2,874,515.70
$2,279,664.82
Over/Under Est: -20.69% -$594,850.88
Over/Under Est: -7.96% -$228,839.70
Amt Left: 16.06% $366,011.18
Over/Under Est: 7.31% $210,085.70
Amt Left: 35.31% $804,936.58
Delta: -16.59% -$438,925.40
Over/Under Est: 13.47% $387,121.72
Amt Left: 43.08% $981,972.60
Delta: -5.74% -$177,036.02
Over/Under Est: 45.28% $1,301,677.90
Amt Left: 83.19% $1,896,528.78
Delta: -28.04% -$914,556.18
Over/Under Est: 60.03% $1,725,548.80
Amt Left: 101.79% $2,320,399.68
Delta: -10.15% -$423,870.90
Subcontractor Percentage Amount
HYDRO TECHNOLOGIES, INC. 6.29% $143,390.92
MORRIS COUNTY CONTRACTORS, L.L.C. 4.11% $93,694.22
STRIPING TECHNOLOGY, L.P. 2.53% $57,675.52
S & S BRIDGE PAINTING, INC. 2.18% $49,696.69
TEX OP CONSTRUCTION, LP 1.90% $43,313.63
DIAMOND ELITE BARRICADES, LLC 0.92% $20,972.92
EMERY SAPP & SON'S INC. 0.40% $9,118.66
Total: 18.33% $417,862.56

Bid Items & Bid Tabulations

61 Total 0 of 61
HOPKINS  |  IH 30  |  PARIS  |  0009-09-115  |  01/07/2026  |  $2,874,515.70  |  BR 2026(233)  |  BRIDGE MAINT  |  286 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
HIGHWAY 19 CONSTRUCTION LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
GIBSON & ASSOCIATES, INC.
GRANITE CONSTRUCTION COMPANY
HODGES AND SON CONSTRUCTION COMPANY, INC.
REMOV CONC (RIPRAP)
CY 247.600 $225.000 $40.000 $25.000 $25.000 $55.000 $420.000 $185.000
D-GR HMA TY-D SAC-A PG64-22 (EXEMPT)
TON 72.000 $250.000 $225.000 $500.000 $300.000 $579.700 $180.000 $450.000
TACK COAT
GAL 132.000 $2.000 $20.000 $10.000 $30.000 $1.650 $10.000 $2.000
FLOWABLE BACKFILL
CY 2.000 $300.000 $1,500.000 $500.000 $400.000 $1,000.000 $1,250.000 $900.000
REINF CONC SLAB
SF 9,329.000 $40.000 $27.000 $40.000 $45.000 $42.900 $98.000 $48.000
APPROACH SLAB
CY 47.000 $875.000 $850.000 $750.000 $400.000 $1,320.000 $1,500.000 $900.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 540.000 $15.000 $15.000 $34.000 $25.000 $19.800 $20.000 $25.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 82.000 $225.000 $150.000 $140.000 $275.000 $66.000 $140.000 $200.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 1,535.000 $175.000 $150.000 $45.000 $304.000 $35.000 $50.000 $190.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 255.000 $200.000 $140.000 $165.000 $250.000 $176.000 $250.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 35.200 $500.000 $800.000 $550.000 $600.000 $770.000 $1,200.000 $700.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,504.600 $195.000 $190.000 $180.000 $225.000 $214.500 $235.000 $270.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 504.000 $60.000 $34.240 $35.000 $60.000 $13.200 $26.000 $35.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 772.000 $50.000 $47.080 $55.000 $60.000 $33.000 $33.000 $45.000
CONCRETE OVERLAY (2 IN)
SY 2,892.000 $90.000 $40.000 $90.000 $90.000 $130.000 $110.000 $200.000
CLEAN & PAINT EXIST STR (SPL PROT SYS)
LS 1.000 $125,000.000 $42,800.000 $70,000.000 $65,000.000 $44,000.000 $85,000.000 $60,000.000
RAIL (TY T221)
LF 580.000 $100.000 $170.000 $180.000 $115.000 $220.000 $200.000 $170.000
ARMOR JOINT (SEALED)
LF 90.000 $150.000 $150.000 $180.000 $175.000 $275.000 $250.000 $200.000
HYDRO-DEMOLITION (3/4 IN)
SY 116.000 $80.000 $70.000 $150.000 $70.000 $126.500 $200.000 $400.000
HYDRO-DEMOLITION (2 IN)
SY 2,892.000 $120.000 $102.000 $75.000 $125.000 $126.500 $125.000 $290.000
REMOV STR (BRIDGE SLAB)
EA 1.000 $100,000.000 $100,000.000 $160,000.000 $125,000.000 $342,000.000 $300,000.000 $300,000.000
REMOV STR (APPROACH SLAB)
EA 2.000 $18,000.000 $10,000.000 $5,000.000 $5,000.000 $7,500.000 $8,500.000 $10,000.000
MOBILIZATION
LS 1.000 $260,000.000 $200,000.000 $300,000.000 $156,000.000 $315,000.000 $400,000.000 $415,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $6,500.000 $4,126.780 $5,000.000 $5,000.000 $9,500.000 $26,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 266.000 $75.000 $50.000 $50.000 $65.000 $95.000 $75.000 $100.000
TMA (STATIONARY)
DAY 218.000 $250.000 $150.000 $200.000 $300.000 $350.000 $180.000 $300.000
TMA (MOBILE OPERATION)
DAY 49.000 $150.000 $300.000 $500.000 $300.000 $350.000 $1,050.000 $300.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,306.000 $4.000 $3.850 $4.000 $5.000 $3.960 $5.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,306.000 $1.500 $1.180 $1.000 $2.000 $1.210 $1.100 $1.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 344.000 $45.000 $25.000 $180.000 $15.000 $200.000 $75.000 $430.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 840.000 $50.000 $25.000 $97.000 $100.000 $36.000 $1.000 $80.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 840.000 $10.000 $15.000 $25.000 $15.000 $11.000 $20.000 $12.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 840.000 $15.000 $20.000 $25.000 $30.000 $15.000 $1.000 $45.000
MTL W-BEAM GD FEN (STEEL POST)
LF 600.000 $30.000 $26.750 $27.000 $32.000 $35.200 $26.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,059.750 $2,500.000 $2,700.000 $2,420.000 $1,880.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 800.000 $15.000 $2.140 $4.000 $4.000 $3.850 $2.000 $2.000
RM MTL BM GD FENCE TRANS (TL-2)
EA 4.000 $250.000 $160.500 $350.000 $400.000 $165.000 $200.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,103.000 $3,200.000 $4,000.000 $3,410.000 $2,840.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $275.000 $214.000 $290.000 $400.000 $302.500 $200.000 $500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 5.000 $2,500.000 $2,140.000 $2,000.000 $1,500.000 $1,831.500 $5,000.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 5.000 $1,000.000 $856.000 $1,000.000 $1,000.000 $891.000 $500.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(S)(W)(TL3)
EA 5.000 $10,000.000 $9,095.000 $5,000.000 $10,000.000 $8,728.500 $8,000.000 $9,000.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 132.000 $12.000 $30.000 $10.000 $25.000 $10.000 $13.000 $10.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 470.000 $2.000 $5.350 $5.000 $6.000 $5.500 $5.000 $10.000
RE PM TY II (W) 6" (BRK)
LF 470.000 $0.500 $5.350 $5.000 $6.000 $5.500 $5.000 $10.000
RE PM TY II (W) 6" (SLD)
LF 1,334.000 $0.500 $5.350 $5.000 $6.000 $5.500 $5.000 $5.000
RE PM TY II (Y) 6" (SLD)
LF 2,300.000 $0.500 $5.350 $5.000 $6.000 $5.500 $5.000 $4.000
PAVEMENT SLER 6"
LF 4,184.000 $0.300 $2.680 $2.500 $3.000 $2.750 $2.500 $0.750
REFL PAV MRKR TY I-A
EA 168.000 $5.000 $10.700 $10.000 $15.000 $11.000 $10.000 $15.000
REFL PAV MRKR TY I-C
EA 247.000 $4.000 $10.700 $10.000 $15.000 $11.000 $10.000 $10.000
REFL PAV MRKR TY II-A-A
EA 55.000 $7.000 $10.700 $10.000 $15.000 $11.000 $10.000 $15.000
REFL PAV MRKR TY II-C-R
EA 52.000 $5.000 $10.700 $10.000 $15.000 $11.000 $10.000 $15.000
TRAFFIC BUTTON TY W
EA 740.000 $2.500 $7.490 $7.000 $10.000 $7.700 $7.000 $10.000
TRAFFIC BUTTON TY Y
EA 669.000 $2.500 $7.490 $7.000 $10.000 $7.700 $7.000 $10.000
ELIM EXT PM & MRKS (6")
LF 2,064.000 $0.500 $2.680 $2.500 $3.000 $2.750 $2.500 $2.000
PAV SURF PREP FOR MRK (6")
LF 4,184.000 $0.500 $0.540 $1.000 $0.750 $0.550 $0.500 $0.500
PAV SURF PREP FOR MRK (RPM)
EA 1,931.000 $1.000 $1.070 $1.000 $1.400 $1.100 $1.000 $0.500
CRACK CLEANING AND SEALING (JCP)
LF 40.000 $35.000 $45.000 $100.000 $10.000 $93.500 $65.000 $50.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 8.000 $650.000 $1,500.000 $100.000 $300.000 $632.500 $500.000 $400.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 80.000 $50.000 $75.000 $100.000 $25.000 $55.000 $70.000 $300.000
CARBON FIBER REINF POLYMER PROTECTION
SF 80.000 $100.000 $150.000 $180.000 $100.000 $101.200 $130.000 $300.000
Totals: $2,874,515.700 $2,279,664.820 $2,645,676.000 $3,084,601.400 $3,261,637.420 $4,176,193.600 $4,600,064.500