HOPKINS IH 30 (0009-09-106)

Items: 27

County: HOPKINS
Length: N/A
Highway: IH 30
District: PARIS
Control Number: 0009-09-106
DBE Goal: N/A
Project: STP 1902(034)HES
Guaranty: N/A
Time: 182 WORKING DAYS
Engineer's Estimate: $3,988,122.00
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: SAFETY IMPROVEMENT PROJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$3,988,122.00
$3,952,539.25
Over/Under Est: -0.89% -$35,582.75
Over/Under Est: 0.88% $34,966.00
Amt Left: 1.78% $70,548.75
$4,055,676.75
Over/Under Est: 1.69% $67,554.75
Amt Left: 2.61% $103,137.50
Delta: -0.81% -$32,588.75
Over/Under Est: 4.82% $192,040.50
Amt Left: 5.76% $227,623.25
Delta: -3.07% -$124,485.75
$4,676,763.75
Over/Under Est: 17.27% $688,641.75
Amt Left: 18.32% $724,224.50
Delta: -11.88% -$496,601.25
$4,730,023.00
Over/Under Est: 18.6% $741,901.00
Amt Left: 19.67% $777,483.75
Delta: -1.14% -$53,259.25

Bid Items & Bid Tabulations

27 Total 0 of 27
HOPKINS  |  IH 30  |  PARIS  |  0009-09-106  |  06/05/2019  |  $3,988,122.00  |  STP 1902(034)HES  |  SAFETY IMPRV PROJECTS  |  182 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
STATELINE CONSTRUCTION, LLC
3LW CIVIL LLC
EAST TEXAS BRIDGE, INC.
VANN/ELLI, INC.
SJ&J CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 53.000 $10.000 $40.000 $100.000 $13.000 $20.000 $30.000 $45.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 42.000 $20.000 $50.000 $50.000 $41.000 $40.000 $50.000 $19.000
BLOCK SODDING
SY 200.000 $5.250 $20.000 $9.000 $8.000 $10.000 $15.000 $6.000
VEGETATIVE WATERING
MG 2.000 $10.000 $200.000 $100.000 $50.000 $100.000 $2,000.000 $20.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 17,125.000 $1.500 $1.000 $1.100 $0.750 $1.100 $1.750 $3.000
RIPRAP (MOW STRIP)(4 IN)
CY 3,434.000 $400.000 $350.000 $422.000 $435.000 $420.000 $450.000 $550.000
MOBILIZATION
LS 1.000 $266,145.000 $440,000.000 $380,000.000 $350,000.000 $300,000.000 $450,000.000 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $5,500.000 $4,000.000 $11,295.000 $8,000.000 $10,000.000 $5,000.000 $5,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 800.000 $3.000 $8.000 $4.000 $7.000 $10.000 $7.000 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 800.000 $0.850 $2.000 $2.000 $2.000 $3.000 $1.500 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 41,175.000 $22.500 $19.750 $19.500 $20.000 $21.500 $25.560 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 130.000 $1,750.000 $2,250.000 $1,760.000 $1,700.000 $1,750.000 $2,400.000 $1,850.000
MTL BEAM GD FEN TRANS (T101)
EA 48.000 $1,100.000 $1,700.000 $1,110.000 $1,000.000 $1,200.000 $1,100.000 $1,750.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 53.000 $1,200.000 $1,100.000 $920.000 $1,216.000 $1,000.000 $1,020.000 $1,100.000
REMOVE METAL BEAM GUARD FENCE
LF 24,750.000 $3.000 $1.000 $2.000 $1.000 $2.250 $3.000 $3.500
REMOVE TERMINAL ANCHOR SECTION
EA 174.000 $250.000 $100.000 $200.000 $150.000 $220.000 $200.000 $300.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 111.000 $400.000 $300.000 $200.000 $250.000 $220.000 $150.000 $300.000
RM MTL BM GD FEN TRANS (T101)
EA 17.000 $200.000 $300.000 $150.000 $230.000 $175.000 $100.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 242.000 $2,300.000 $2,750.000 $2,400.000 $2,600.000 $2,600.000 $2,640.000 $2,635.000
GUARDRAIL END TREATMENT (REMOVE)
EA 22.000 $400.000 $150.000 $200.000 $300.000 $220.000 $200.000 $600.000
CRASH CUSH ATTEN (REMOVE)
EA 36.000 $800.000 $150.000 $1,100.000 $1,100.000 $1,200.000 $1,500.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 3.000 $24,000.000 $30,900.000 $23,950.000 $30,000.000 $27,500.000 $30,000.000 $24,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 268.000 $14.000 $18.000 $17.000 $12.000 $20.000 $16.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 388.000 $40.000 $22.000 $19.000 $12.000 $20.000 $16.000 $30.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 196.000 $10.000 $18.000 $17.000 $12.000 $20.000 $16.000 $25.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $9,000.000 $4,000.000 $6,500.000 $7,500.000 $20,000.000 $15,000.000 $12,000.000
TMA (STATIONARY)
DAY 211.000 $350.000 $450.000 $150.000 $150.000 $200.000 $400.000 $150.000
Totals: $3,988,122.000 $3,952,539.250 $4,023,088.000 $4,055,676.750 $4,180,162.500 $4,676,763.750 $4,730,023.000