HOPKINS IH 30 (0009-09-103)

Items: 24

County: HOPKINS
Length: N/A
Highway: IH 30
District: PARIS
Control Number: 0009-09-103
DBE Goal: N/A
Project: BR 2B20(252)
Guaranty: N/A
Time: 70 WORKING DAYS
Engineer's Estimate: $287,402.63
Date: 09/04/2020 (5 years ago)
Contract Number: N/A
Type: REMOVE/REPLACE BRIDGE RAIL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$287,402.63
$397,137.50
Over/Under Est: 38.18% $109,734.87
Over/Under Est: 40.59% $116,664.87
Amt Left: 1.74% $6,930.00
$423,318.50
Over/Under Est: 47.29% $135,915.87
Amt Left: 6.59% $26,181.00
Delta: -4.76% -$19,251.00
$447,139.75
Over/Under Est: 55.58% $159,737.12
Amt Left: 12.59% $50,002.25
Delta: -5.63% -$23,821.25
Over/Under Est: 61.42% $176,517.37
Amt Left: 16.82% $66,782.50
Delta: -3.75% -$16,780.25
Over/Under Est: 65.66% $188,707.87
Amt Left: 19.89% $78,973.00
Delta: -2.63% -$12,190.50
$482,835.00
Over/Under Est: 68% $195,432.37
Amt Left: 21.58% $85,697.50
Delta: -1.41% -$6,724.50
Over/Under Est: 79.14% $227,462.37
Amt Left: 29.64% $117,727.50
Delta: -6.63% -$32,030.00
Over/Under Est: 90.22% $259,297.37
Amt Left: 37.66% $149,562.50
Delta: -6.18% -$31,835.00
$557,660.50
Over/Under Est: 94.03% $270,257.87
Amt Left: 40.42% $160,523.00
Delta: -2.00% -$10,960.50

Bid Items & Bid Tabulations

24 Total 0 of 24
HOPKINS  |  IH 30  |  PARIS  |  0009-09-103  |  09/04/2020  |  $287,402.63  |  BR 2B20(252)  |  REMOVE/REPLACE BRIDGE RAIL  |  70 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
HIGHWAY 19 CONSTRUCTION LLC
3LW CIVIL LLC
VANN/ELLI, INC.
TALBRAN ENTERPRISES LLC
SJ&J CONSTRUCTION, LLC
ODUM SERVICES, LLC
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
CATOCON, INC.
REMOVING CONC (RIPRAP)
SY 5.700 $45.000 $125.000 $50.000 $5.000 $120.000 $100.000 $15.000 $25.000 $100.000 $50.000 $265.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 300.000 $20.000 $35.000 $30.000 $32.000 $40.000 $100.000 $25.000 $35.000 $40.000 $50.000 $30.000
BLOCK SODDING
SY 475.000 $5.500 $13.000 $5.000 $1.000 $6.850 $10.000 $5.000 $10.000 $8.000 $8.000 $25.000
VEGETATIVE WATERING
MG 5.000 $16.000 $200.000 $100.000 $3.000 $400.000 $35.000 $10.000 $20.000 $50.000 $1,000.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 358.500 $4.250 $400.000 $500.000 $300.000 $480.000 $450.000 $500.000 $600.000 $500.000 $500.000 $550.000
MOBILIZATION
LS 1.000 $26,400.000 $30,000.000 $30,000.000 $25,000.000 $30,000.000 $50,000.000 $25,000.000 $40,000.000 $40,000.000 $50,000.000 $60,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $6,000.000 $2,000.000 $1,500.000 $29,000.000 $4,000.000 $1,000.000 $4,000.000 $5,000.000 $15,000.000 $8,500.000 $5,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 600.000 $3.500 $7.000 $1.000 $1.000 $4.000 $5.000 $3.500 $15.000 $7.000 $18.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 600.000 $1.000 $1.000 $1.000 $1.000 $0.500 $3.000 $1.000 $5.000 $1.000 $9.000 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 3,625.000 $22.000 $26.000 $18.500 $20.000 $25.200 $30.000 $30.000 $24.100 $21.000 $25.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,050.000 $1,800.000 $1,525.000 $1,900.000 $2,650.000 $1,700.000 $1,700.000 $2,000.000 $1,800.000 $1,850.000 $2,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 9.000 $1,150.000 $1,300.000 $930.000 $1,350.000 $1,175.000 $1,050.000 $1,500.000 $1,350.000 $1,000.000 $1,850.000 $1,000.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 200.000 $25.000 $35.000 $24.000 $60.000 $25.000 $35.000 $50.000 $26.000 $26.000 $50.000 $22.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 150.000 $70.000 $60.000 $58.000 $64.000 $58.600 $65.000 $60.000 $91.000 $65.000 $50.000 $60.000
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $3.000 $5.000 $10.000 $1.500 $2.000 $3.000 $4.000 $5.000 $12.000 $3.000 $20.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $300.000 $200.000 $400.000 $150.000 $200.000 $225.000 $500.000 $150.000 $500.000 $650.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 19.000 $2,700.000 $2,500.000 $2,400.000 $2,400.000 $2,703.000 $2,550.000 $2,600.000 $2,400.000 $2,600.000 $2,500.000 $2,800.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 1.000 $1,600.000 $1,000.000 $1,300.000 $750.000 $2,000.000 $2,550.000 $1,200.000 $1,100.000 $1,500.000 $1,500.000 $1,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $500.000 $500.000 $100.000 $300.000 $100.000 $225.000 $500.000 $250.000 $120.000 $850.000 $1,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 20.000 $88.000 $20.000 $75.000 $10.000 $15.000 $30.000 $40.000 $45.000 $35.000 $100.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 60.000 $28.000 $20.000 $75.000 $10.000 $15.000 $30.000 $40.000 $48.000 $35.000 $100.000 $20.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $13,000.000 $1,000.000 $5,000.000 $1,000.000 $6,000.000 $1,600.000 $10,000.000 $100.000 $10,000.000 $10,000.000 $500.000
TMA (STATIONARY)
DAY 28.000 $170.000 $400.000 $300.000 $100.000 $300.000 $300.000 $100.000 $100.000 $300.000 $550.000 $2,000.000
TMA (MOBILE OPERATION)
HR 24.000 $70.000 $75.000 $50.000 $25.000 $100.000 $100.000 $75.000 $200.000 $300.000 $85.000 $950.000
Totals: $287,402.625 $397,137.500 $404,067.500 $423,318.500 $447,139.750 $463,920.000 $476,110.500 $482,835.000 $514,865.000 $546,700.000 $557,660.500