Show Job Controls
Bid Cobra

HOOD FM 3450 (2631-01-006)

Items: 64

County: HOOD
Length: N/A
Highway: FM 3450
District: FORT WORTH
Control Number: 2631-01-006
DBE Goal: N/A
Project: STP 2020(474)
Guaranty: N/A
Time: 208 WORKING DAYS
Engineer's Estimate: $5,641,929.31
Date: 01/09/2020 (6 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$5,641,929.31
$5,769,636.53
Over/Under Est: 2.26% $127,707.22
Over/Under Est: 12.83% $724,131.01
Amt Left: 10.34% $596,423.79
Over/Under Est: 19.32% $1,090,112.99
Amt Left: 16.68% $962,405.77
Delta: -5.75% -$365,981.98
Over/Under Est: 21.42% $1,208,420.05
Amt Left: 18.73% $1,080,712.83
Delta: -1.76% -$118,307.06

Bid Items & Bid Tabulations

64 Total 0 of 64
HOOD  |  FM 3450  |  FORT WORTH  |  2631-01-006  |  01/09/2020  |  $5,641,929.31  |  STP 2020(474)  |  RESURF ROADWAY  |  208 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
TEXAS MATERIALS GROUP, INC.
JAY MILLS CONTRACTING, INCORPORATED
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
PREPARING ROW
STA 214.576 $300.000 $275.000 $160.000 $450.000 $3,000.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 81,074.000 $6.000 $1.050 $7.800 $6.150 $4.000
EXCAVATION (ROADWAY)
CY 50.000 $8.000 $42.000 $145.000 $75.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 50.000 $10.000 $42.000 $96.000 $75.000 $28.000
BACKFILL (TY B)
STA 214.800 $165.000 $210.000 $390.000 $225.000 $250.000
BLADING
HR 219.000 $150.000 $210.000 $38.000 $150.000 $150.000
COMPOST MANUF TOPSOIL (4")
SY 24,732.400 $1.400 $1.210 $1.350 $1.350 $2.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
AC 5.110 $800.000 $1,150.000 $1,050.000 $1,500.000 $700.000
VEGETATIVE WATERING
MG 1,048.000 $20.000 $42.000 $0.010 $40.000 $10.000
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
CY 10,970.000 $48.000 $55.000 $53.850 $38.500 $75.000
LIME (HYD, COM OR QK)(SLURRY)
TON 937.000 $158.000 $200.000 $200.000 $183.000 $200.000
LIME TRT (SUBGRADE)(8")
SY 55,541.000 $4.200 $2.100 $2.900 $4.000 $5.000
CEMENT
TON 555.500 $150.000 $150.000 $230.000 $155.000 $200.000
CEMENT TREAT(EXIST MATL)(8")
SY 14,358.000 $3.000 $1.330 $4.700 $4.000 $5.000
CEMENT TREAT (NEW BASE)(6")(DC)
SY 69,899.000 $2.500 $1.850 $2.035 $3.500 $4.000
PRIME COAT (EC-30)
GAL 13,169.000 $3.300 $7.320 $5.250 $5.500 $5.000
D-GR HMA TY-B PG64-22
TON 17,822.000 $75.000 $89.320 $86.000 $99.000 $90.000
TACK COAT
GAL 10,117.000 $3.500 $3.300 $3.500 $3.150 $4.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
TON 8,238.000 $110.000 $111.430 $101.250 $118.000 $95.000
TACK COAT
GAL 10,117.000 $3.500 $3.300 $3.500 $3.150 $4.000
PLANE ASPH CONC PAV(2" TO 4")
SY 81,074.000 $2.000 $1.990 $2.800 $2.700 $3.000
RIPRAP (MOW STRIP)(4 IN)
CY 152.000 $500.000 $525.000 $650.000 $630.000 $400.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $2,500.000 $4,200.000 $2,250.000 $1,500.000 $1,285.000
REMOV STR (SET)
EA 2.000 $400.000 $1,050.000 $560.000 $1,000.000 $1,000.000
MOBILIZATION
LS 1.000 $480,000.000 $549,000.000 $560,000.000 $650,000.000 $605,785.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $10,500.000 $8,000.000 $12,000.000 $3,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 736.000 $28.000 $27.500 $34.500 $24.650 $30.000
ROCK FILTER DAMS (REMOVE)
LF 736.000 $7.500 $13.750 $12.250 $7.600 $9.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $25.000 $20.350 $32.750 $24.000 $22.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $10.000 $9.900 $13.000 $9.500 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 961.000 $2.200 $1.650 $7.250 $3.200 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 961.000 $0.500 $0.170 $1.700 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 736.000 $7.000 $4.130 $6.200 $5.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 736.000 $1.800 $1.100 $1.500 $1.000 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 13.000 $8,000.000 $6,300.000 $7,600.000 $8,000.000 $4,800.000
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 926.000 $45.000 $36.000 $75.000 $76.000 $46.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,135.000 $23.000 $21.180 $25.000 $24.250 $19.000
REMOVE METAL BEAM GUARD FENCE
LF 4,210.000 $3.500 $2.200 $3.350 $3.300 $2.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 9.000 $245.000 $110.000 $280.000 $275.000 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $2,500.000 $2,860.000 $2,750.000 $2,800.000 $2,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $300.000 $220.000 $280.000 $275.000 $200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 47.000 $524.000 $495.000 $525.000 $650.000 $482.000
INSTL OM ASSM (OM-3R)(TWT)GND
EA 14.000 $212.000 $187.000 $279.000 $290.000 $170.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 33.000 $40.000 $40.700 $50.250 $50.000 $37.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 178,109.000 $0.200 $0.500 $0.560 $0.450 $0.250
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 11,428.000 $0.200 $0.500 $0.560 $0.570 $0.220
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 177,030.000 $0.200 $0.500 $0.560 $0.660 $0.230
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,440.000 $4.000 $3.740 $3.800 $4.950 $4.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 4,800.000 $0.700 $1.100 $1.120 $1.100 $0.600
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 176.000 $7.500 $8.800 $8.900 $13.200 $8.500
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 2,400.000 $0.700 $1.100 $1.120 $1.650 $0.650
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 135.000 $7.000 $6.050 $6.150 $16.500 $6.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 43,995.000 $0.450 $0.510 $0.500 $0.430 $0.300
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 10,125.000 $0.400 $0.570 $0.580 $0.110 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 28,905.000 $0.350 $0.510 $0.510 $0.440 $0.300
REFL PAV MRKR TY II-A-A
EA 471.000 $3.000 $3.740 $3.800 $4.950 $3.000
TRAFFIC BUTTON TY W
EA 9,463.000 $4.000 $3.080 $3.150 $2.600 $1.800
TRAFFIC BUTTON TY B
EA 9,463.000 $5.000 $3.080 $3.120 $2.750 $1.650
ELIM EXT PAV MRK & MRKS (4")
LF 2,400.000 $0.400 $1.250 $1.120 $1.100 $0.400
PAV SURF PREP FOR MRK (4")
LF 83,025.000 $0.150 $0.060 $0.050 $0.060 $0.100
PAV SURF PREP FOR MRK (24")
LF 129.000 $1.400 $3.300 $3.350 $1.400 $1.100
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,750.000 $14,000.000 $15,000.000 $7,000.000
TMA (STATIONARY)
DAY 50.000 $200.000 $735.000 $225.000 $300.000 $200.000
TMA (MOBILE OPERATION)
HR 20.000 $60.000 $110.000 $115.000 $250.000 $45.000
Totals: $5,641,929.310 $5,769,636.534 $6,366,060.325 $6,732,042.300 $6,850,349.360