HOOD SH 144 (0385-04-045)

Items: 64

County: HOOD
Length: N/A
Highway: SH 144
District: FORT WORTH
Control Number: 0385-04-045
DBE Goal: N/A
Project: ER 1602(591)
Guaranty: N/A
Time: 149 WORKING DAYS
Engineer's Estimate: $2,909,365.50
Date: 01/04/2017 (9 years ago)
Contract Number: N/A
Type: OFF SITE DRAINAGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,909,365.50
$2,899,083.65
Over/Under Est: -0.35% -$10,281.85
Over/Under Est: 10.61% $308,825.50
Amt Left: 11.01% $319,107.35
Over/Under Est: 22% $639,971.00
Amt Left: 22.43% $650,252.85
Delta: -10.29% -$331,145.50
$3,642,426.50
Over/Under Est: 25.2% $733,061.00
Amt Left: 25.64% $743,342.85
Delta: -2.62% -$93,090.00
$3,944,246.70
Over/Under Est: 35.57% $1,034,881.20
Amt Left: 36.05% $1,045,163.05
Delta: -8.29% -$301,820.20
Over/Under Est: 38.53% $1,121,015.65
Amt Left: 39.02% $1,131,297.50
Delta: -2.18% -$86,134.45
Over/Under Est: 44.9% $1,306,216.95
Amt Left: 45.41% $1,316,498.80
Delta: -4.60% -$185,201.30

Bid Items & Bid Tabulations

64 Total 0 of 64
HOOD  |  SH 144  |  FORT WORTH  |  0385-04-045  |  01/04/2017  |  $2,909,365.50  |  ER 1602(591)  |  OFF SITE DRAINAGE REPL  |  149 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BRETT CONSTRUCTION COMPANY
SEMA CONSTRUCTION, INC.
ED BELL CONSTRUCTION COMPANY
FNH CONSTRUCTION, LLC
EARTH BUILDERS, L.P.
JAY MILLS CONTRACTING, INCORPORATED
RAGLE CONSTRUCTION, INC.
PREPARING ROW
AC 0.400 $5,000.000 $30,000.000 $500,000.000 $150,000.000 $350,000.000 $180,000.000 $15,000.000 $500,000.000
REMOVING CONC (PAV)
SY 280.000 $7.000 $15.000 $20.000 $16.800 $20.000 $20.000 $10.000 $15.000
REMOVING CONC (RIPRAP)
SY 40.000 $20.000 $10.000 $40.000 $31.500 $20.000 $20.000 $15.000 $12.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 454.000 $8.000 $15.000 $10.000 $10.000 $12.000 $12.000 $12.000 $6.000
EXCAVATION (ROADWAY AND CHANNEL)
CY 1,870.000 $20.000 $20.000 $22.000 $17.850 $20.000 $25.000 $30.000 $23.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 620.000 $20.000 $32.000 $70.000 $50.000 $35.000 $65.000 $65.000 $40.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 5,580.000 $40.000 $32.000 $70.000 $50.000 $35.000 $65.000 $75.000 $40.000
GENERAL USE COMPOST (4")
SY 160.000 $5.000 $7.000 $9.000 $15.000 $3.000 $8.000 $10.000 $9.000
BLOCK SODDING
SY 160.000 $10.000 $7.000 $10.000 $22.000 $5.000 $13.000 $15.000 $13.000
VEGETATIVE WATERING
MG 7.000 $50.000 $100.000 $150.000 $700.000 $1,000.000 $500.000 $150.000 $100.000
LIME TRT (NEW BASE)(8")
SY 3,710.000 $10.000 $4.250 $5.000 $5.250 $3.500 $15.000 $10.000 $4.000
LIME (HYD, COM, OR QK(SLURRY))
TON 100.000 $250.000 $160.000 $140.000 $148.000 $171.000 $200.000 $170.000 $142.500
SALV, HAUL & STKPL RCL APH PV (2"-6")
SY 2,450.000 $7.500 $7.000 $6.000 $10.000 $20.000 $8.000 $8.000 $7.000
PRIME COAT (MULTI OPTION)
GAL 598.000 $7.000 $8.000 $7.250 $10.000 $8.000 $12.000 $10.000 $6.900
D-GR HMA(SQ) TY-B PG64-22
TON 687.000 $120.000 $130.000 $97.000 $100.000 $140.000 $110.000 $105.000 $91.900
D-GR HMA TY D PG70-28(LATEX ADDITIVE)
TON 344.000 $150.000 $130.000 $110.000 $125.000 $140.000 $130.000 $135.000 $102.200
CONC PVMT (CONT REINF - CRCP) (7")
SY 627.000 $70.000 $100.000 $100.000 $63.000 $85.000 $85.000 $75.000 $80.000
CEM STABIL BKFL
CY 1,685.000 $60.000 $125.000 $165.000 $95.000 $140.000 $200.000 $115.000 $120.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 200.000 $70.000 $140.000 $200.000 $95.000 $140.000 $200.000 $130.000 $110.000
FLOWABLE BACKFILL
CY 280.000 $200.000 $165.000 $140.000 $175.000 $400.000 $200.000 $140.000 $130.000
TRENCH EXCAVATION PROTECTION
LF 437.000 $40.000 $10.000 $215.000 $10.000 $3.000 $50.000 $50.000 $50.000
TEMPORARY SPL SHORING
SF 5,930.000 $20.000 $40.000 $1.000 $50.000 $45.000 $15.000 $48.000 $28.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 1,750.000 $80.000 $20.000 $20.000 $63.000 $55.000 $30.000 $75.000 $40.000
SOIL NAIL ANCHORS
LF 4,672.000 $40.000 $25.000 $24.000 $28.000 $45.000 $50.000 $26.000 $34.000
DRILL SHAFT (30 IN)
LF 48.000 $200.000 $550.000 $460.000 $500.000 $500.000 $550.000 $500.000 $450.000
CL C CONC (RAIL FOUNDATION)(HPC)
CY 16.000 $420.000 $900.000 $500.000 $840.000 $1,500.000 $500.000 $1,000.000 $900.000
CL F CONC (MISC)
CY 53.000 $400.000 $1,000.000 $350.000 $630.000 $1,500.000 $1,000.000 $800.000 $400.000
RETAINING WALL (MSE) (WELDED WIRE FACE)
SF 1,832.000 $100.000 $14.000 $35.000 $30.500 $65.000 $60.000 $80.000 $30.000
RET. WALL (SOIL NAILED) (GUNNITE FACIA)
SF 5,508.000 $60.000 $32.000 $30.000 $55.000 $55.000 $75.000 $35.000 $35.000
RIPRAP (CONC)(5 IN)
CY 22.000 $400.000 $900.000 $325.000 $630.000 $650.000 $500.000 $475.000 $525.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 3.900 $400.000 $1,200.000 $350.000 $735.000 $650.000 $500.000 $1,000.000 $600.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 249.000 $115.000 $150.000 $65.000 $125.000 $185.000 $100.000 $100.000 $125.000
RIPRAP (MOW STRIP)(4 IN)
CY 1.000 $2,000.000 $1,700.000 $500.000 $945.000 $2,000.000 $500.000 $2,000.000 $800.000
RAIL (TY T223)
LF 131.000 $140.000 $155.000 $80.000 $200.000 $185.000 $100.000 $150.000 $125.000
GABION MATTRESSES (PVC)(12 IN)
SY 120.000 $150.000 $100.000 $65.000 $125.000 $250.000 $130.000 $120.000 $100.000
GABIONS (PVC)( 3FT X 3 FT)
CY 300.000 $325.000 $150.000 $120.000 $315.000 $450.000 $240.000 $425.000 $225.000
CONC BOX CULV (10 FT X 9 FT)
LF 426.000 $1,200.000 $1,395.000 $2,000.000 $1,785.000 $1,500.000 $2,000.000 $2,500.000 $2,910.000
JCT BOX (COMPL)(SPL1)
EA 2.000 $10,000.000 $20,000.000 $10,000.000 $15,000.000 $5,000.000 $18,000.000 $20,000.000 $35,000.000
JCT BOX (COMPL)(SPL2)
EA 1.000 $70,000.000 $258,000.000 $60,000.000 $132,000.000 $5,000.000 $150,000.000 $130,000.000 $190,000.000
WINGWALL (FW - 0) (HW=12 FT)
EA 1.000 $35,000.000 $36,000.000 $35,000.000 $52,500.000 $35,000.000 $50,000.000 $50,000.000 $60,000.000
REMOV STR (PIPE)
LF 210.000 $50.000 $15.000 $50.000 $30.000 $30.000 $100.000 $20.000 $20.000
REMOV STR (DRAINAGE FLUME)
EA 2.000 $1,000.000 $1,500.000 $2,000.000 $1,500.000 $1,500.000 $3,000.000 $2,200.000 $1,500.000
MOBILIZATION
LS 1.000 $280,000.000 $250,000.000 $312,000.000 $349,000.000 $375,000.000 $350,000.000 $390,000.000 $415,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,000.000 $3,500.000 $2,000.000 $18,900.000 $8,500.000 $2,200.000 $8,500.000 $51,530.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 48.000 $55.000 $25.000 $40.000 $50.000 $30.000 $45.000 $30.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 48.000 $10.000 $10.000 $10.000 $12.000 $15.000 $10.000 $12.000 $10.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 10.000 $60.000 $100.000 $250.000 $50.000 $30.000 $25.000 $100.000 $40.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 195.000 $3.000 $5.000 $6.500 $4.000 $4.000 $7.000 $12.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 195.000 $1.000 $1.000 $2.300 $1.500 $2.000 $3.500 $3.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 120.000 $6.000 $10.000 $6.500 $7.000 $12.000 $8.000 $15.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $1.000 $1.000 $2.300 $1.500 $8.000 $3.250 $3.000 $2.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 330.000 $25.000 $15.500 $20.000 $15.750 $25.000 $30.000 $20.000 $14.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 690.000 $10.000 $5.000 $2.000 $6.300 $15.000 $15.000 $10.000 $8.500
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 570.000 $10.000 $15.500 $6.000 $15.750 $15.000 $30.000 $20.000 $9.000
CONC CURB & GUTTER (TY II)
LF 442.000 $30.000 $58.000 $15.000 $50.000 $35.000 $30.000 $40.000 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 12.500 $60.000 $50.000 $200.000 $75.000 $25.000 $40.000 $220.000 $200.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $2,000.000 $4,000.000 $3,000.000 $2,000.000 $1,850.000 $1,500.000 $3,500.000 $3,000.000
REMOVE METAL BEAM GUARD FENCE
LF 58.000 $10.000 $5.000 $20.000 $10.000 $3.000 $5.000 $15.000 $20.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $1,000.000 $500.000 $1,500.000 $800.000 $650.000 $350.000 $750.000 $1,500.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 15.000 $10.000 $15.000 $15.000 $20.000 $10.000 $20.000 $16.500 $10.000
REFL PAV MRK TY II (Y) 12" (SLD)
LF 372.000 $8.000 $5.000 $5.000 $8.000 $10.000 $10.000 $5.500 $2.900
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 971.000 $1.500 $2.900 $1.500 $2.000 $2.000 $1.200 $1.650 $2.600
REFL PAV MRK TY II (R&W)6"(FIRE LANE)
LF 595.000 $5.000 $4.750 $1.000 $3.000 $2.000 $3.000 $1.100 $4.250
PREFAB PAV MRK TY C (W) (ARROW)
EA 5.000 $300.000 $300.000 $250.000 $300.000 $150.000 $300.000 $275.000 $215.000
Totals: $2,909,365.500 $2,899,083.650 $3,218,191.000 $3,549,336.500 $3,642,426.500 $3,944,246.700 $4,030,381.150 $4,215,582.450