HOCKLEY US 385 (0227-06-024)

Items: 107

County: HOCKLEY
Length: N/A
Highway: US 385
District: LUBBOCK
Control Number: 0227-06-024
DBE Goal: N/A
Project: STP 2017(872)
Guaranty: N/A
Time: 259 WORKING DAYS
Engineer's Estimate: $6,848,581.53
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$6,848,581.53
$7,499,584.14
Over/Under Est: 9.51% $651,002.61
$8,382,785.01
Over/Under Est: 22.4% $1,534,203.48
Amt Left: 11.78% $883,200.87
$8,856,225.37
Over/Under Est: 29.31% $2,007,643.84
Amt Left: 18.09% $1,356,641.23
Delta: -5.65% -$473,440.36
$10,554,667.11
Over/Under Est: 54.11% $3,706,085.58
Amt Left: 40.74% $3,055,082.97
Delta: -19.18% -$1,698,441.74
Over/Under Est: 80.25% $5,495,680.29
Amt Left: 64.6% $4,844,677.68
Delta: -16.96% -$1,789,594.71

Bid Items & Bid Tabulations

107 Total 0 of 107
HOCKLEY  |  US 385  |  LUBBOCK  |  0227-06-024  |  04/03/2018  |  $6,848,581.53  |  STP 2017(872)  |  REHAB  |  259 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN BUTLER CONSTRUCTION, INC.
DUININCK, INC.
A. L. HELMCAMP, INC.
J. LEE MILLIGAN, INC.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
PREPARING ROW
STA 98.100 $2,000.000 $375.580 $1,000.000 $2,000.000 $6,600.000 $500.000
REMOVING CONC (DRIVEWAYS)
SY 1,155.000 $8.000 $7.450 $18.500 $22.000 $11.500 $15.000
REMOVING CONC (CURB AND GUTTER)
LF 228.000 $10.000 $7.060 $9.800 $30.000 $10.400 $10.000
REMOVING CONC (MISC)
SY 10.800 $15.000 $54.900 $18.500 $70.000 $105.000 $80.000
REMOVING CONC (WHEELCHAIR RAMP)
SY 19.000 $25.000 $31.180 $23.500 $40.000 $31.000 $34.000
EXCAVATION (ROADWAY)
CY 34,806.700 $8.000 $7.110 $16.500 $15.000 $14.300 $15.000
EXCAVATION (CHANNEL)
CY 192.390 $20.000 $26.590 $20.000 $18.000 $18.500 $40.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,627.700 $8.000 $8.360 $13.000 $11.000 $19.700 $9.000
BLOCK SODDING
SY 14,145.550 $2.000 $5.030 $4.350 $3.800 $5.550 $9.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 36,878.090 $0.200 $0.200 $0.270 $0.160 $0.130 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 36,878.090 $0.100 $0.180 $0.260 $0.160 $0.130 $1.000
VEGETATIVE WATERING
MG 1,717.000 $15.000 $39.310 $27.000 $20.000 $38.000 $85.000
SPRINKLING (HOT PAVMT)
MG 1,000.000 $10.000 $37.570 $27.000 $10.000 $59.000 $60.000
FL BS (CMP IN PLC) (TY D GR 4) (1")
SY 70,682.010 $1.500 $1.040 $2.200 $2.000 $1.950 $6.450
REWRK BS MATL (TY B)(10")(DENS CONT)
SY 43,758.000 $6.000 $2.220 $6.350 $2.700 $3.750 $3.000
CEMENT
TON 596.380 $150.000 $133.010 $165.000 $190.000 $137.000 $200.000
CEM TRT (MX EXST MTL & NW BS)(DC)(6")
SY 70,682.010 $2.000 $4.580 $2.650 $2.000 $2.450 $5.600
PRIME COAT (MC-30)
GAL 14,136.400 $4.000 $3.520 $4.000 $5.500 $3.750 $5.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 4,794.150 $3.000 $3.150 $3.500 $3.300 $3.350 $5.000
FOG SEAL (CSS-1H)
GAL 6,269.270 $3.000 $5.010 $3.300 $3.300 $3.200 $5.000
ASPH (AC-20-5TR)
GAL 41,822.570 $3.000 $2.900 $3.300 $3.300 $4.050 $5.000
AGGR(TY-PB GR-4 SAC-B)
CY 885.130 $150.000 $199.340 $135.000 $110.000 $135.550 $145.000
D-GR HMA TY-B PG70-28
TON 16,011.230 $85.000 $103.040 $90.000 $92.000 $143.650 $120.000
STONE-MTRX-ASPH SMA-D SAC-A PG70-28
TON 8,091.070 $115.000 $145.260 $138.000 $140.000 $174.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 213.500 $50.000 $57.050 $80.000 $150.000 $71.000 $85.000
CEM STABIL BKFL
CY 190.300 $200.000 $95.030 $235.000 $200.000 $232.000 $200.000
RIPRAP (CONC)(4 IN)
CY 0.800 $1,000.000 $1,732.940 $1,600.000 $3,200.000 $1,580.000 $3,000.000
RIPRAP (CONC)(5 IN)
CY 14.900 $450.000 $774.920 $480.000 $800.000 $475.000 $3,000.000
RIPRAP (CONC)(6 IN)
CY 466.900 $450.000 $305.120 $455.000 $500.000 $445.000 $1,500.000
CONC BOX CULV (5 FT X 2 FT)
LF 312.000 $250.000 $292.020 $425.000 $400.000 $422.000 $625.310
RC PIPE (CL III)(24 IN)
LF 666.000 $80.000 $120.910 $85.500 $80.000 $84.000 $125.060
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 2.000 $3,000.000 $10,946.900 $3,200.000 $16,000.000 $3,160.000 $4,689.810
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 6.000 $4,000.000 $6,877.490 $4,800.000 $15,000.000 $4,750.000 $7,034.720
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 24.000 $1,500.000 $2,061.480 $1,300.000 $1,000.000 $1,265.000 $1,875.920
CLEAN EXIST CULVERTS
EA 10.000 $2,000.000 $1,585.860 $3,200.000 $2,700.000 $920.000 $234.490
REMOV STR (PIPE)
EA 2.000 $2,000.000 $11,143.480 $215.000 $1,000.000 $210.000 $2,762.630
MOBILIZATION
LS 1.000 $448,000.000 $663,928.720 $800,000.000 $870,000.000 $1,033,000.000 $840,800.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $8,000.000 $4,662.140 $13,000.000 $25,000.000 $21,980.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 70.000 $25.000 $32.430 $33.000 $40.000 $75.000 $200.750
ROCK FILTER DAMS (REMOVE)
LF 70.000 $8.000 $19.670 $13.000 $7.000 $25.000 $147.020
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 148.000 $20.000 $22.260 $44.500 $30.000 $37.000 $40.060
CONSTRUCTION EXITS (REMOVE)
SY 148.000 $10.000 $8.970 $11.500 $5.000 $15.000 $23.180
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,330.000 $3.000 $2.800 $3.150 $4.000 $5.300 $13.670
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,330.000 $1.000 $1.060 $0.640 $1.000 $2.550 $2.760
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,290.000 $8.000 $4.760 $4.100 $6.500 $11.000 $30.400
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,290.000 $3.000 $0.790 $0.840 $2.000 $1.750 $4.640
CONSTRUCTING DETOURS
SY 20,107.000 $35.000 $31.940 $27.500 $48.000 $39.200 $75.000
CONC CURB & GUTTER (TY II)
LF 189.400 $30.000 $45.780 $37.500 $35.000 $36.900 $120.000
INTERSECTIONS (CONC)
SY 607.840 $60.000 $98.760 $160.000 $150.000 $136.000 $300.000
DRIVEWAYS (CONC)
SY 9,055.480 $60.000 $68.510 $88.000 $100.000 $79.000 $130.000
TURNOUTS (ACP)
SY 139.380 $30.000 $62.650 $42.500 $70.000 $170.000 $100.000
CONC SIDEWALKS (6")
SY 3,428.240 $60.000 $54.190 $69.000 $40.000 $52.700 $95.000
CURB RAMPS (TY 1)
SY 49.490 $200.000 $171.570 $130.000 $60.000 $170.000 $700.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $300.000 $237.890 $240.000 $250.000 $260.000 $350.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $400.000 $290.750 $295.000 $300.000 $275.000 $420.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 10.000 $500.000 $650.220 $655.000 $650.000 $735.000 $950.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $500.000 $507.490 $510.000 $510.000 $600.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 22.000 $525.000 $560.360 $565.000 $560.000 $630.000 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $600.000 $755.950 $760.000 $760.000 $890.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,000.000 $1,030.850 $1,000.000 $1,100.000 $1,300.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-EXAL)
EA 2.000 $1,100.000 $930.400 $940.000 $930.000 $1,130.000 $1,300.000
REMOVE SM RD SN SUP&AM
EA 36.000 $80.000 $79.300 $80.000 $80.000 $150.000 $90.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 26.000 $80.000 $84.580 $96.000 $95.000 $185.000 $140.690
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 12,123.000 $0.400 $0.130 $0.130 $0.130 $0.130 $0.340
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 69,418.000 $0.400 $0.130 $0.130 $0.130 $0.130 $0.310
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,030.000 $1.000 $0.260 $0.270 $0.270 $0.260 $0.630
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 928.000 $3.000 $1.060 $1.050 $1.060 $1.050 $4.490
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 543.000 $4.000 $2.110 $2.150 $2.120 $2.110 $9.380
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 20.000 $100.000 $26.430 $26.500 $26.500 $26.350 $132.880
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 20.000 $100.000 $37.000 $37.500 $37.100 $36.890 $132.880
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 6,960.000 $0.400 $0.130 $0.130 $0.130 $0.130 $0.340
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 112,610.000 $0.400 $0.130 $0.130 $0.130 $0.130 $0.310
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 1,000.000 $4.000 $2.110 $2.150 $2.120 $2.110 $9.680
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 3,220.000 $3.000 $3.170 $3.200 $3.180 $3.160 $6.640
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,638.000 $2.000 $1.040 $1.050 $1.000 $1.100 $5.320
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,721.000 $2.000 $1.040 $1.050 $1.000 $1.150 $5.220
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 515.000 $1.000 $0.850 $0.850 $0.850 $0.840 $2.340
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 23,527.000 $0.400 $0.420 $0.430 $0.420 $0.420 $0.520
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 6,003.000 $0.500 $0.630 $0.640 $0.640 $0.630 $0.750
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,604.000 $0.400 $0.420 $0.430 $0.420 $0.420 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 29,201.000 $0.400 $0.420 $0.430 $0.420 $0.420 $0.520
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 488.000 $7.000 $9.940 $10.000 $9.960 $9.910 $13.520
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 207.000 $12.000 $19.880 $20.000 $19.930 $19.820 $31.270
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $200.000 $317.180 $320.000 $318.000 $316.210 $351.740
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $300.000 $449.340 $455.000 $450.500 $447.970 $390.820
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 500.000 $10.000 $21.150 $21.500 $21.200 $21.080 $23.450
PREFAB PAV MRK TY C (Y) (MED NOSE)
EA 4.000 $300.000 $84.580 $85.500 $84.800 $84.320 $8,285.330
REFL PAV MRKR TY II-A-A
EA 719.000 $3.000 $3.170 $3.200 $3.180 $3.160 $6.640
REFL PAV MRKR TY II-C-R
EA 330.000 $3.000 $3.170 $3.200 $3.180 $3.160 $6.640
ELIM EXT PAV MRK & MRKS (4")
LF 154,661.000 $0.600 $0.010 $0.640 $0.530 $1.050 $0.750
ELIM EXT PAV MRK & MRKS (8")
LF 815.000 $1.000 $2.110 $1.050 $1.060 $2.100 $1.560
ELIM EXT PAV MRK & MRKS (12")
LF 754.000 $2.000 $3.170 $2.150 $2.120 $3.150 $3.130
ELIM EXT PAV MRK & MRKS (24")
LF 947.000 $4.000 $6.340 $4.250 $3.180 $6.350 $6.250
ELIM EXT PAV MRK & MRKS (ARROW)
EA 20.000 $100.000 $52.860 $105.000 $53.000 $53.000 $78.160
ELIM EXT PAV MRK & MRKS (WORD)
EA 20.000 $200.000 $63.440 $105.000 $53.000 $63.000 $78.160
PAV SURF PREP FOR MRK (12")
LF 488.000 $3.000 $2.110 $2.150 $2.120 $2.110 $1.560
PAV SURF PREP FOR MRK (24")
LF 707.000 $6.000 $4.230 $4.250 $4.240 $4.220 $3.130
PAV SURF PREP FOR MRK (ARROW)
EA 8.000 $16.000 $37.010 $37.500 $37.100 $36.890 $62.530
PAV SURF PREP FOR MRK (WORD)
EA 8.000 $16.000 $63.440 $64.000 $63.600 $63.240 $62.530
PAV SURF PREP FOR MRK (MED NOSE)
EA 4.000 $20.000 $19.030 $19.000 $19.080 $18.970 $468.980
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 1.000 $600.000 $792.960 $2,100.000 $1,100.000 $1,580.000 $598.060
FULL - WIDTH MOWING
CYC 3.000 $3,000.000 $1,447.480 $1,700.000 $2,100.000 $2,420.000 $2,990.300
LITTER REMOVAL
CYC 3.000 $2,000.000 $993.270 $3,400.000 $1,800.000 $1,655.000 $5,980.610
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $10,572.740 $10,500.000 $15,000.000 $23,500.000 $18,000.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $8,000.000 $9,728.240 $10,500.000 $12,000.000 $12,400.000 $20,000.000
TMA (STATIONARY)
EA 4.000 $10,000.000 $39,647.780 $53,500.000 $15,000.000 $63,300.000 $20,000.000
TMA (MOBILE OPERATION)
DAY 15.000 $250.000 $1,025.260 $1,100.000 $900.000 $950.000 $3,500.000
Totals: $6,848,581.532 $7,499,584.295 $8,382,785.036 $8,856,225.386 $10,554,667.169 $12,344,261.830