HILL SH0022 (6473-42-001)

Items: 22

County: HILL
Length: 0.0100 MILES
Highway: SH0022
District: WACO
Control Number: 6473-42-001
DBE Goal: N/A
Project: RMC - 647342001
Guaranty: $32,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,580,805.60
Date: 12/04/2024 (1 year ago)
Contract Number: 12244206
Type: BASE FAILURE PAVEMENT REPAIR
Project ID: A00212214
Project Description: BASE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,580,805.60
$1,448,925.00
Over/Under Est: -8.34% -$131,880.60
Over/Under Est: 18.01% $284,765.40
Amt Left: 28.76% $416,646.00
Over/Under Est: 173.95% $2,749,859.40
Amt Left: 198.89% $2,881,740.00
Delta: -132.14% -$2,465,094.00

Bid Items & Bid Tabulations

22 Total 0 of 22
HILL  |  SH0022  |  WACO  |  6473-42-001  |  12/04/2024  |  $1,580,805.60  |  RMC - 647342001  |  BASE FAILURE PAVMT REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
D-GR HMA TY-C PG70-22
TON 1,050.000 $150.480 $137.000 $204.000 $370.000
D-GR HMA TY-D SAC-B PG64-22
TON 4,200.000 $110.000 $130.000 $170.500 $371.300
TACK COAT
GAL 3,000.000 $6.470 $4.000 $3.200 $8.850
SP MIXES SP-C SAC-B PG70-22
TON 3,000.000 $150.000 $137.000 $170.000 $383.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 2,700.000 $40.280 $40.000 $49.000 $91.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 600.000 $85.000 $80.000 $102.000 $232.000
PLANE ASPH CONC PAV(2")
SY 24,000.000 $5.000 $3.500 $3.700 $18.000
MOBILIZATION (CALLOUT)
EA 21.000 $4,467.300 $250.000 $1.000 $5,035.000
MOBILIZATION (EMERGENCY)
EA 9.000 $2,978.200 $500.000 $4,200.000 $5,045.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $109.450 $100.000 $25.000 $320.000
TMA (STATIONARY)
DAY 60.000 $275.640 $150.000 $270.000 $756.000
TMA (MOBILE OPERATION)
HR 60.000 $76.760 $100.000 $25.000 $110.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 450.000 $2.800 $1.500 $1.000 $1.100
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 450.000 $1.450 $1.500 $1.000 $1.100
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 150.000 $9.220 $12.000 $8.000 $15.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 3,000.000 $1.550 $1.500 $2.000 $1.750
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 3,000.000 $1.430 $1.500 $2.000 $1.750
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 3,000.000 $0.800 $1.500 $2.000 $1.750
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 3,000.000 $1.390 $1.500 $2.000 $1.750
REFL PAV MRKR TY I-C
EA 600.000 $6.670 $9.000 $6.000 $10.000
UNDERSEAL COURSE
GAL 5,100.000 $7.000 $5.250 $4.500 $10.150
MAINTENANCE SPEED LIMIT SIGNING
DAY 60.000 $80.000 $200.000 $395.000 $1,410.000
Totals: $1,580,805.600 $1,448,925.000 $1,865,571.000 $4,330,665.000