Show Job Controls
Bid Cobra

HILL FM 66 (0596-01-021)

Items: 81

County: HILL
Length: N/A
Highway: FM 66
District: WACO
Control Number: 0596-01-021
DBE Goal: N/A
Project: STP 1902(017)HRR
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $854,447.00
Date: 08/06/2019 (6 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$854,447.00
$849,409.10
Over/Under Est: -0.59% -$5,037.90
Over/Under Est: 20.02% $171,040.00
Amt Left: 20.73% $176,077.90
Over/Under Est: 22.02% $188,164.50
Amt Left: 22.75% $193,202.40
Delta: -1.67% -$17,124.50
Over/Under Est: 26.75% $228,598.69
Amt Left: 27.51% $233,636.59
Delta: -3.88% -$40,434.19
$1,166,884.00
Over/Under Est: 36.57% $312,437.00
Amt Left: 37.38% $317,474.90
Delta: -7.74% -$83,838.31
Over/Under Est: 75.29% $643,311.95
Amt Left: 76.33% $648,349.85
Delta: -28.36% -$330,874.95

Bid Items & Bid Tabulations

81 Total 0 of 81
HILL  |  FM 66  |  WACO  |  0596-01-021  |  08/06/2019  |  $854,447.00  |  STP 1902(017)HRR  |  SAFETY TREAT FIXED OBJECTS  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BEAR CREEK CONTRACTING, LLC
CROSS PLUS CONSTRUCTION, LLC
TALBRAN ENTERPRISES LLC
PROJECT ALLIED RESOURCES, LLC
SJ&J CONSTRUCTION, LLC
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 6.000 $5,000.000 $1,700.000 $1,234.000 $2,500.000 $3,000.000 $1,500.000 $6,300.000
REMOVING CONC (RIPRAP)
SY 751.000 $12.000 $10.000 $34.000 $10.000 $12.900 $30.000 $21.000
EXCAVATION (CHANNEL)
CY 143.000 $15.000 $6.000 $43.000 $50.000 $18.100 $25.000 $42.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 668.000 $12.000 $25.000 $54.000 $150.000 $35.700 $28.000 $42.000
BLOCK SODDING
SY 2,418.000 $4.500 $3.500 $6.000 $7.000 $6.800 $7.000 $10.000
BROADCAST SEED (TEMP) (WARM)
SY 1,209.000 $0.250 $1.000 $1.000 $1.000 $0.270 $0.500 $0.250
BROADCAST SEED (TEMP) (COOL)
SY 1,209.000 $0.250 $2.000 $1.000 $1.000 $0.290 $0.500 $0.250
VEGETATIVE WATERING
MG 37.000 $15.000 $26.000 $23.000 $50.000 $50.000 $20.000 $175.000
CEM STABIL BKFL
CY 177.000 $200.000 $146.000 $234.000 $500.000 $242.000 $230.000 $210.000
CUT & RESTORE ASPH PAVING
SY 14.000 $100.000 $181.000 $199.000 $150.000 $193.000 $110.000 $210.000
TRENCH EXCAVATION PROTECTION
LF 23.000 $50.000 $6.000 $56.000 $10.000 $28.200 $50.000 $52.500
TEMPORARY SPL SHORING
SF 454.000 $25.000 $20.000 $56.000 $15.000 $7.100 $25.000 $30.000
RIPRAP (CONC)(4 IN)
CY 24.000 $385.000 $500.000 $400.000 $500.000 $672.000 $800.000 $735.000
RIPRAP (CONC)(5 IN)
CY 20.100 $385.000 $500.000 $600.000 $500.000 $608.000 $750.000 $735.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 50.000 $150.000 $167.000 $300.000 $200.000 $144.000 $210.000 $262.500
RIPRAP (MOW STRIP)(4 IN)
CY 203.000 $385.000 $425.000 $389.000 $400.000 $597.000 $650.000 $735.000
RIPRAP (STONE COMMON)(GROUT)(18 IN)
CY 53.000 $400.000 $240.000 $432.000 $400.000 $362.000 $300.000 $315.000
CMP (GAL STL 12 IN)
LF 7.000 $40.000 $76.000 $50.000 $156.000 $242.000 $60.000 $212.000
CMP (GAL STL 18 IN)
LF 6.000 $55.000 $152.000 $56.000 $266.000 $318.000 $80.000 $266.000
CMP (GAL STL 48 IN)
LF 10.000 $120.000 $52.000 $123.000 $1,070.000 $402.000 $200.000 $425.000
CMP (GAL STL 15 IN)
LF 4.000 $50.000 $105.000 $234.000 $115.000 $273.000 $70.000 $239.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 3.700 $450.000 $1,428.000 $900.000 $350.000 $842.000 $600.000 $1,000.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 8.000 $475.000 $714.000 $1,200.000 $400.000 $752.000 $700.000 $1,025.000
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 16.000 $500.000 $516.000 $2,345.000 $425.000 $658.000 $800.000 $1,050.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 23.000 $550.000 $566.000 $1,200.000 $600.000 $1,040.000 $900.000 $1,200.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 14.000 $600.000 $572.000 $1,900.000 $650.000 $1,080.000 $900.000 $1,400.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 21.000 $650.000 $613.000 $2,000.000 $842.000 $990.000 $1,000.000 $1,700.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 7.000 $750.000 $1,022.000 $2,345.000 $920.000 $1,900.000 $1,300.000 $2,000.000
CONC BOX CULV (5 FT X 6 FT) (EXTEND)
LF 14.000 $750.000 $592.000 $2,456.000 $920.000 $1,590.000 $1,300.000 $1,600.000
RC PIPE (CL III)(15 IN)
LF 12.000 $40.000 $81.000 $50.000 $86.000 $101.000 $80.000 $170.000
RC PIPE (CL III)(18 IN)
LF 28.000 $50.000 $93.000 $59.000 $88.000 $107.000 $100.000 $250.000
RC PIPE (CL III)(24 IN)
LF 4.000 $60.000 $137.000 $123.000 $121.000 $120.000 $120.000 $260.000
RC PIPE (CL III)(30 IN)
LF 32.000 $85.000 $172.000 $199.000 $166.000 $129.000 $180.000 $294.000
RC PIPE (CL III)(36 IN)
LF 64.000 $125.000 $233.000 $199.000 $240.000 $176.000 $250.000 $310.000
HEADWALL (CH - FW - 15) (DIA= 36 IN)
EA 1.000 $5,000.000 $6,740.000 $8,000.000 $10,000.000 $2,580.000 $5,000.000 $7,350.000
HEADWALL (CH - FW - 30) (DIA= 30 IN)
EA 1.000 $4,500.000 $6,716.000 $12,000.000 $12,500.000 $3,410.000 $6,000.000 $7,350.000
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 1.000 $5,000.000 $7,218.000 $12,000.000 $15,000.000 $3,740.000 $7,000.000 $13,650.000
WINGWALL (FW - 0) (HW=3 FT)
EA 1.000 $4,500.000 $6,568.000 $3,455.000 $5,000.000 $3,260.000 $8,000.000 $4,325.000
WINGWALL (FW - 0) (HW=4 FT)
EA 4.000 $6,000.000 $6,754.000 $3,455.000 $5,500.000 $4,520.000 $8,000.000 $7,800.000
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $7,500.000 $7,084.000 $4,555.000 $7,000.000 $5,760.000 $10,000.000 $9,500.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $8,500.000 $7,897.000 $4,555.000 $7,500.000 $7,650.000 $12,000.000 $12,600.000
WINGWALL (FW - 0) (HW=7 FT)
EA 1.000 $9,500.000 $8,512.000 $5,678.000 $8,000.000 $8,550.000 $15,000.000 $15,500.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $10,000.000 $8,044.000 $7,890.000 $8,500.000 $10,900.000 $20,000.000 $12,500.000
WINGWALL (FW - S) (HW=5 FT)
EA 2.000 $9,000.000 $7,393.000 $7,890.000 $7,000.000 $9,140.000 $10,000.000 $12,500.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 1.000 $5,000.000 $7,828.000 $3,500.000 $5,000.000 $5,560.000 $7,000.000 $7,350.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 1.000 $6,000.000 $8,228.000 $3,500.000 $7,000.000 $7,980.000 $8,000.000 $9,450.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 1.000 $6,000.000 $7,902.000 $4,567.000 $5,000.000 $6,200.000 $8,000.000 $8,400.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $7,500.000 $9,188.000 $5,678.000 $11,000.000 $12,500.000 $9,000.000 $14,700.000
SET (TY II) (12 IN) (CMP) (6: 1) (P)
EA 3.000 $650.000 $850.000 $1,900.000 $130.000 $1,270.000 $1,300.000 $630.000
SET (TY II) (15 IN) (CMP) (6: 1) (P)
EA 2.000 $700.000 $890.000 $1,900.000 $200.000 $1,310.000 $1,400.000 $735.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 6.000 $800.000 $850.000 $1,900.000 $500.000 $1,220.000 $1,500.000 $630.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 4.000 $850.000 $950.000 $1,900.000 $240.000 $1,510.000 $1,600.000 $735.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 11.000 $850.000 $900.000 $1,900.000 $900.000 $1,150.000 $1,600.000 $735.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,000.000 $1,054.000 $2,341.000 $1,175.000 $1,740.000 $1,800.000 $840.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 1.000 $2,000.000 $1,277.000 $3,341.000 $1,688.000 $3,090.000 $2,500.000 $945.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $2,500.000 $1,414.000 $3,566.000 $2,010.000 $2,100.000 $2,700.000 $1,050.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $2,010.000 $3,566.000 $3,046.000 $3,180.000 $2,900.000 $1,785.000
SET (TY II) (48 IN) (CMP) (6: 1) (P)
EA 2.000 $6,000.000 $5,000.000 $5,466.000 $1,700.000 $8,530.000 $4,500.000 $7,350.000
CLEAN EXIST CULVERTS
EA 28.000 $1,200.000 $650.000 $500.000 $1,000.000 $1,170.000 $1,200.000 $2,100.000
REMOV STR (PIPE)
LF 42.000 $20.000 $9.000 $56.000 $10.000 $50.000 $60.000 $21.000
MOBILIZATION
LS 1.000 $51,000.000 $71,000.000 $75,000.000 $100,000.000 $76,000.000 $150,000.000 $282,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $5,200.000 $5,000.000 $4,000.000 $2,430.000 $5,000.000 $15,750.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 950.000 $50.000 $30.000 $23.000 $35.000 $73.000 $40.000 $33.000
ROCK FILTER DAMS (REMOVE)
LF 950.000 $10.000 $5.000 $23.000 $10.000 $11.800 $20.000 $16.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,300.000 $3.000 $6.000 $2.000 $6.500 $3.690 $3.000 $1.650
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,300.000 $0.750 $2.000 $2.000 $4.000 $1.110 $1.000 $0.220
MTL W-BEAM GD FEN (STEEL POST)
LF 2,137.500 $26.000 $31.000 $24.000 $25.000 $23.100 $31.000 $23.100
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,775.000 $1,800.000 $2,000.000 $1,950.000 $1,600.000 $1,952.500
MTL BEAM GD FEN TRANS (T6)
EA 4.000 $1,500.000 $982.000 $1,500.000 $1,500.000 $583.000 $3,000.000 $583.000
REMOVE METAL BEAM GUARD FENCE
LF 915.000 $3.000 $3.000 $3.000 $5.000 $2.480 $3.500 $2.480
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $2,750.000 $3,411.000 $2,500.000 $2,750.000 $2,810.000 $3,000.000 $2,805.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $300.000 $241.000 $345.000 $220.000 $275.000 $700.000 $275.000
WIRE FENCE (TY C)
LF 94.000 $18.000 $14.000 $8.000 $12.000 $12.200 $25.000 $27.500
WIRE FENCE (TY D)
LF 100.000 $13.000 $14.000 $8.000 $25.000 $26.200 $25.000 $38.500
GATE (TY 2)
EA 1.000 $1,300.000 $1,255.000 $500.000 $1,000.000 $1,200.000 $1,050.000 $2,200.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $20.000 $34.000 $30.000 $19.800 $60.000 $19.800
INSTL OM ASSM (OM-2Y)(WC)GND
EA 26.000 $70.000 $112.000 $34.000 $30.000 $49.500 $60.000 $49.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 37.000 $24.000 $41.000 $34.000 $30.000 $39.600 $60.000 $39.600
FULL - WIDTH MOWING
CYC 1.000 $20,000.000 $5,000.000 $7,899.000 $5,500.000 $24,100.000 $300.000 $8,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $3,258.000 $23.000 $250.000 $9,120.000 $6,000.000 $10,500.000
TMA (STATIONARY)
DAY 90.000 $235.000 $303.000 $123.000 $350.000 $839.000 $200.000 $525.000
Totals: $854,447.000 $849,409.100 $1,025,487.000 $1,042,611.500 $1,083,045.690 $1,166,884.000 $1,497,758.950