HILL FM 66 (0596-01-019)

Items: 66

County: HILL
Length: N/A
Highway: FM 66
District: WACO
Control Number: 0596-01-019
DBE Goal: 600.0%
Project: BR 2024(986)
Guaranty: N/A
Time: 150 WORKING DAYS
Engineer's Estimate: $2,951,502.65
Date: 05/03/2024 (2 years ago)
Contract Number: N/A
Type: REPL BR & APPRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,951,502.65
$2,469,349.43
Over/Under Est: -16.34% -$482,153.22
$2,747,848.31
Over/Under Est: -6.9% -$203,654.34
Amt Left: 11.28% $278,498.88
Over/Under Est: -5.29% -$156,048.55
Amt Left: 13.21% $326,104.67
Delta: -1.73% -$47,605.79
$3,233,846.20
Over/Under Est: 9.57% $282,343.55
Amt Left: 30.96% $764,496.77
Delta: -15.68% -$438,392.10
Over/Under Est: 33.48% $988,147.63
Amt Left: 59.54% $1,470,300.85
Delta: -21.83% -$705,804.08
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 5.56% $137,420.01
DIIBS SPECIALISTS, LLC 2.35% $58,082.20
LINDAMOOD, INC. 1.80% $44,488.49
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.98% $24,221.51
STRIPING TECHNOLOGY, L.P. 0.91% $22,491.40
CEN-TREE SOLUTIONS LLC 0.82% $20,266.98
MURRAY CONSTRUCTION 0.77% $19,031.19
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.72% $17,795.40
PRIMATE CONSTRUCTION, LP 0.46% $11,369.28
SOUTHERN CROSS CONTRACTORS, LLC 0.40% $9,886.33
LS SERVICES LLC 0.38% $9,392.01
PROFESSIONAL TRAFFIC CONTROL LLC 0.32% $7,909.07
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 15.47% $382,353.87

Bid Items & Bid Tabulations

66 Total 0 of 66
HILL  |  FM 66  |  WACO  |  0596-01-019  |  05/03/2024  |  $2,951,502.65  |  BR 2024(986)  |  REPL BR & APPRS  |  150 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
TALBERT COMPANIES LLC
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
SKYLINE BRIDGE LLC
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 21.700 $3,200.000 $2,100.000 $2,200.000 $2,450.000 $4,000.000 $7,700.000
REMOVING CONC (RIPRAP)
CY 55.000 $500.000 $86.000 $357.500 $148.000 $75.000 $150.000
REMOV STAB BASE AND ASPH PAV (10"-18")
SY 5,241.000 $12.000 $11.000 $4.510 $7.350 $9.500 $15.000
REMOVING UNTREATED BASE (8")
SY 787.000 $10.000 $7.500 $22.000 $10.500 $15.000 $10.000
EXCAVATION (ROADWAY)
CY 1,742.000 $23.000 $17.000 $20.900 $25.200 $23.000 $20.000
EXCAVATION (CHANNEL)
CY 575.000 $35.000 $35.000 $47.400 $28.350 $20.000 $40.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 1,590.000 $25.000 $17.000 $24.830 $31.500 $32.000 $15.000
FURNISHING AND PLACING TOPSOIL (4")
SY 9,545.000 $2.500 $1.000 $8.470 $3.150 $3.500 $4.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 9,545.000 $1.200 $0.550 $0.610 $0.600 $1.250 $0.500
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 4,772.000 $1.000 $0.790 $0.830 $0.800 $1.500 $0.740
VEGETATIVE WATERING
MG 155.000 $37.000 $1.000 $82.500 $60.000 $1.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 200.000 $2.000 $4.000 $9.850 $9.400 $5.000 $7.500
FL BS(CMP IN PLC)(TY D GR 5)(FNAL POS)
CY 2,298.000 $99.000 $85.000 $110.000 $98.700 $125.000 $140.000
PRIME COAT(MC-30 OR AE-P)
GAL 1,442.000 $8.000 $7.500 $7.700 $5.900 $10.000 $7.730
ASPH (CRS-2)
GAL 2,523.000 $4.000 $5.500 $5.230 $4.200 $9.000 $4.400
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 53.400 $220.000 $300.000 $390.500 $488.000 $550.000 $511.500
CEM STABIL BKFL
CY 179.000 $285.000 $280.000 $275.000 $397.000 $325.000 $400.000
DRILL SHAFT (24 IN)
LF 664.000 $250.000 $185.000 $154.000 $180.500 $275.000 $175.000
DRILL SHAFT (30 IN)
LF 320.000 $385.000 $250.000 $187.000 $224.900 $275.000 $200.000
CL B CONC (FLUME)
CY 4.700 $1,000.000 $1,250.000 $770.000 $1,965.000 $1,800.000 $1,500.000
CL C CONC (ABUT)(HPC)
CY 46.600 $1,750.000 $1,650.000 $1,191.820 $1,460.000 $1,400.000 $3,000.000
CL C CONC (CAP)(HPC)
CY 18.000 $1,750.000 $1,750.000 $1,191.300 $2,135.000 $2,000.000 $2,500.000
CL C CONC (COLUMN)(HPC)
CY 11.200 $2,000.000 $2,000.000 $1,430.040 $2,255.000 $2,000.000 $3,000.000
REINF CONC SLAB (SLAB BEAM)
SF 5,419.000 $25.000 $25.000 $23.650 $29.050 $32.500 $40.000
APPROACH SLAB
CY 110.000 $675.000 $700.000 $684.130 $695.000 $900.000 $2,000.000
PRESTR CONC SLAB BEAM (5SB12)
LF 689.500 $230.000 $260.000 $192.500 $233.200 $275.000 $400.000
PRESTR CONC SLAB BEAM (5SB15)
LF 346.500 $230.000 $250.000 $192.500 $240.900 $350.000 $400.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,792.000 $195.000 $139.000 $214.500 $153.650 $200.000 $275.000
RIPRAP (MOW STRIP)(4 IN)
CY 76.000 $625.000 $650.000 $715.000 $816.000 $800.000 $1,000.000
RAIL (TY T223)
LF 348.000 $161.000 $145.000 $121.000 $190.000 $165.000 $200.000
ARMOR JOINT (SEALED)
LF 128.000 $165.000 $132.000 $165.000 $145.000 $150.000 $100.000
RC PIPE (CL III)(18 IN)
LF 36.000 $91.000 $100.000 $45.100 $126.000 $225.000 $200.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,500.000 $2,000.000 $1,048.300 $3,410.000 $2,500.000 $2,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $33,000.000 $40,000.000 $24,477.750 $54,400.000 $45,000.000 $55,000.000
REMOV STR (SMALL FENCE)
LF 80.000 $13.000 $10.000 $9.020 $10.000 $10.000 $15.000
MOBILIZATION
LS 1.000 $271,931.000 $245,000.000 $290,000.000 $276,000.000 $250,000.000 $375,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $7,500.000 $3,500.000 $4,620.000 $3,500.000 $3,500.000 $11,550.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 325.000 $36.000 $30.000 $59.950 $57.250 $50.000 $88.000
ROCK FILTER DAMS (REMOVE)
LF 325.000 $11.000 $5.000 $49.500 $47.000 $10.000 $44.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,434.000 $6.000 $4.500 $3.140 $3.000 $4.000 $3.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,434.000 $1.600 $0.750 $1.820 $1.700 $1.500 $1.650
INTERSECTIONS (ACP)
SY 421.000 $50.000 $50.000 $85.800 $53.550 $125.000 $80.000
DRIVEWAYS (ACP)
SY 156.000 $59.000 $50.000 $85.800 $78.750 $175.000 $80.000
RUMBLE STRIPS (SHOULDER)
LF 3,504.000 $0.300 $1.750 $0.970 $1.250 $2.000 $1.250
RUMBLE STRIPS (CENTERLINE)
LF 1,752.000 $0.500 $1.750 $1.940 $1.400 $2.250 $1.250
MTL W-BEAM GD FEN (STEEL POST)
LF 500.000 $35.000 $33.000 $31.350 $28.350 $33.000 $35.200
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,650.000 $3,100.000 $2,420.000 $2,992.000 $2,500.000 $3,594.520
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,350.000 $3,300.000 $3,162.500 $3,150.000 $3,600.000 $3,575.000
WIRE FENCE (TY C)
LF 66.000 $29.000 $95.000 $41.250 $92.400 $25.000 $50.000
WIRE FENCE (WATER GAP)
LF 28.000 $75.000 $165.000 $182.970 $157.500 $200.000 $250.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $350.000 $360.000 $324.500 $310.000 $500.000 $330.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 23.000 $705.000 $825.000 $544.500 $520.000 $950.000 $715.000
REMOVE SM RD SN SUP&AM
EA 13.000 $110.000 $100.000 $126.500 $135.000 $200.000 $110.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $30.000 $42.000 $20.900 $19.000 $50.000 $27.500
REMOVE DELIN & OBJECT MARKER ASSMS
EA 16.000 $23.000 $45.000 $16.500 $21.000 $15.000 $27.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $47.000 $42.000 $39.050 $47.250 $50.000 $44.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 33.000 $15.000 $11.000 $6.600 $6.300 $10.000 $11.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 4,437.000 $1.100 $2.220 $1.430 $1.400 $3.000 $2.200
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 1,261.000 $1.000 $2.220 $1.490 $1.450 $1.750 $2.200
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 2,917.000 $1.050 $2.220 $1.430 $1.400 $1.600 $2.200
REFL PAV MRKR TY II-A-A
EA 68.000 $11.000 $22.000 $8.800 $8.400 $20.000 $22.000
TACK COAT
GAL 708.000 $5.000 $3.750 $3.850 $3.200 $10.000 $3.360
SP MIXES SP-C SAC-B PG70-22 (EXEMPT)
TON 1,555.000 $200.000 $135.000 $163.350 $164.000 $195.000 $170.500
LEAD CONTAINING COATING MANAGEMENT
SF 120.000 $105.000 $75.000 $101.200 $100.000 $100.000 $85.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $11,000.000 $1,000.000 $12,082.770 $11,000.000 $15,000.000 $9,450.000
TMA (MOBILE OPERATION)
DAY 6.000 $390.000 $100.000 $426.200 $1,100.000 $300.000 $1,100.000
Totals: $2,951,502.650 $2,469,349.430 $2,747,848.320 $2,795,454.100 $3,233,846.200 $3,939,650.280