HILL SH 81 (0014-07-103)

Items: 21

County: HILL
Length: N/A
Highway: SH 81
District: WACO
Control Number: 0014-07-103
DBE Goal: N/A
Project: STP 1902(129)HES
Guaranty: N/A
Time: 30 WORKING DAYS
Engineer's Estimate: $513,737.70
Date: 08/07/2019 (6 years ago)
Contract Number: N/A
Type: INSTALL CABLE MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$513,737.70
$482,159.20
Over/Under Est: -6.15% -$31,578.50
$603,662.50
Over/Under Est: 17.5% $89,924.80
Amt Left: 25.2% $121,503.30
$618,792.30
Over/Under Est: 20.45% $105,054.60
Amt Left: 28.34% $136,633.10
Delta: -2.51% -$15,129.80
Over/Under Est: 50.84% $261,169.30
Amt Left: 60.72% $292,747.80
Delta: -25.23% -$156,114.70

Bid Items & Bid Tabulations

21 Total 0 of 21
HILL  |  SH 81  |  WACO  |  0014-07-103  |  08/07/2019  |  $513,737.70  |  STP 1902(129)HES  |  INSTL CABLE MEDIAN BARRIER  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSS PLUS CONSTRUCTION, LLC
DBI SERVICES, LLC
VANN/ELLI, INC.
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 251.000 $16.000 $34.000 $85.000 $55.000 $65.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 30.000 $60.000 $56.000 $100.000 $52.500 $230.000
BLOCK SODDING
SY 8,076.000 $4.000 $2.000 $6.000 $6.250 $4.500
VEGETATIVE WATERING
MG 65.600 $22.000 $12.000 $65.000 $258.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 483.000 $450.000 $399.000 $400.000 $530.000 $795.000
MOBILIZATION
LS 1.000 $26,300.000 $50,000.000 $67,000.000 $50,000.000 $75,600.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,000.000 $4,000.000 $4,900.000 $8,000.000 $12,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 150.000 $3.500 $2.000 $5.000 $15.000 $21.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 150.000 $0.600 $2.000 $1.000 $10.000 $12.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,400.000 $26.000 $24.000 $26.000 $27.250 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,200.000 $444.000 $1,700.000 $3,500.000 $1,120.000
REMOVE METAL BEAM GUARD FENCE
LF 980.000 $5.000 $2.000 $5.000 $2.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $400.000 $199.000 $400.000 $100.000 $115.000
CABLE BARRIER SYSTEM (TL-4)
LF 8,135.000 $12.000 $14.000 $14.500 $10.500 $13.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 10.000 $4,000.000 $2,167.000 $3,000.000 $2,800.000 $2,565.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,000.000 $2,500.000 $3,800.000 $3,300.000 $2,765.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $260.000 $455.000 $200.000 $100.000 $225.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $39.500 $56.000 $50.000 $45.000 $30.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 7.000 $39.500 $67.000 $50.000 $45.000 $30.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $130.000 $45.000 $300.000 $150.000 $186.000
TMA (STATIONARY)
DAY 48.000 $200.000 $200.000 $400.000 $400.000 $400.000
Totals: $513,737.700 $482,159.200 $603,662.500 $618,792.300 $774,907.000