HIDALGO IH0002 (6443-44-001)

Items: 32

County: HIDALGO
Length: N/A
Highway: IH0002
District: PHARR
Control Number: 6443-44-001
DBE Goal: 0.0%
Project: BPM - 644344001
Guaranty: N/A
Time: 120 W
Engineer's Estimate: $606,850.00
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
JUAN SUSTAITA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$606,850.00
$555,555.00
Over/Under Est: -8.45% -$51,295.00
Over/Under Est: 58.5% $355,021.00
Amt Left: 73.14% $406,316.00

Bid Items & Bid Tabulations

32 Total 0 of 32
HIDALGO  |  IH0002  |  PHARR  |  6443-44-001  |  06/05/2024  |  $606,850.00  |  BPM - 644344001  |  BRIDGE PREVENT MAINT  |  120 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
LUCANIA CONTRACTORS LLC
ICOS MANAGEMENT, LLC
REMOVING CONC (RIPRAP)
SY 16.000 $50.000 $500.000 $550.000
REMOVING CONC (MISC)
SY 17.000 $100.000 $400.000 $550.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 158.000 $250.000 $80.000 $110.000
CL C CONC (PILE ENCASEMENT)
CY 8.000 $2,500.000 $7,000.000 $6,600.000
CL C CONC (COLLAR)
EA 1.000 $2,000.000 $6,000.000 $8,800.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 14.000 $500.000 $200.000 $440.000
RIPRAP (CONC)(4 IN)
CY 15.000 $500.000 $550.000 $1,100.000
RIPRAP (MOW STRIP)(4 IN)
CY 61.000 $750.000 $550.000 $880.000
RETROFIT RAIL (TY SSTR)
LF 570.000 $300.000 $200.000 $715.000
REMOV & RE - LAY PIPE (24 IN)
LF 8.000 $100.000 $250.000 $715.000
REMOVE STR (CONC)
EA 1.000 $2,500.000 $3,500.000 $5,500.000
MOBILIZATION
LS 1.000 $50,000.000 $55,000.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $2,000.000 $1.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 2)
LF 270.000 $50.000 $40.000 $88.000
PORT CTB (MOVE)(SGL SLP)(TY 2)
LF 810.000 $50.000 $15.000 $55.000
PORT CTB (STKPL)(SGL SLP)(TY 2)
LF 270.000 $50.000 $40.000 $55.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,125.000 $30.000 $40.000 $44.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,500.000 $3,500.000 $4,400.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,800.000 $5,500.000 $2,750.000
REMOVE METAL BEAM GUARD FENCE
LF 1,275.000 $6.000 $6.000 $5.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $500.000 $700.000 $880.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 4.000 $3,500.000 $4,500.000 $4,400.000
CRASH CUSH ATTEN (DES SOURCE)
EA 1.000 $4,000.000 $4,000.000 $11,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $2,500.000 $2,000.000 $8,800.000
CRASH CUSH ATTEN (STKPL)
EA 1.000 $1,000.000 $4,000.000 $5,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $75.000 $40.000 $55.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $75.000 $40.000 $55.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $50.000 $40.000 $55.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 29.000 $250.000 $150.000 $220.000
REP STL BRDG MEMB (WELD REPAIR)
EA 14.000 $2,000.000 $1,400.000 $2,750.000
REPAIR STEEL (CORROSION MITIGATION)
EA 41.000 $750.000 $500.000 $550.000
BRIDGE SUBSTRUCTURE CLEANING (BENT)
EA 5.000 $1,000.000 $2,961.000 $4,400.000
Totals: $606,850.000 $555,555.000 $961,871.000