HIDALGO IH0002 (6366-11-001)

Items: 27

County: HIDALGO
Length: N/A
Highway: IH0002
District: PHARR
Control Number: 6366-11-001
DBE Goal: N/A
Project: RMC - 636611001
Guaranty: N/A
Time: 180 W
Engineer's Estimate: $626,715.60
Date: 03/05/2021 (5 years ago)
Contract Number: N/A
Type: ITS CCTV_CAMERAS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$626,715.60
$571,618.89
Over/Under Est: -8.79% -$55,096.71
Over/Under Est: -2.16% -$13,517.85
Amt Left: 7.27% $41,578.86
$639,052.35
Over/Under Est: 1.97% $12,336.75
Amt Left: 11.8% $67,433.46
Delta: -4.22% -$25,854.60
Over/Under Est: 27.87% $174,655.01
Amt Left: 40.19% $229,751.72
Delta: -25.40% -$162,318.26

Bid Items & Bid Tabulations

27 Total 0 of 27
HIDALGO  |  IH0002  |  PHARR  |  6366-11-001  |  03/05/2021  |  $626,715.60  |  RMC - 636611001  |  ITS CCTV_CAMERAS  |  180 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE LEVY COMPANY, INC.
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
TRAF-TEX, INC.
AMERICAN LIGHTING AND SIGNALIZATION, LLC
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 105.000 $600.000 $645.420 $510.000 $710.870 $884.020
RIPRAP (CONC) (CL B) (4")
CY 7.680 $345.000 $562.260 $750.000 $2,990.370 $909.530
MOBILIZATION
LS 1.000 $57,000.000 $51,050.460 $32,500.000 $22,718.780 $84,891.520
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $6,600.000 $1,521.570 $3,500.000 $4,805.380 $9,244.230
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $7.000 $5.900 $12.000 $9.450 $3.180
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $1.300 $3.000 $2.500 $3.300 $1.350
HI MST IL POLE (125 FT)(100 MPH)
EA 3.000 $26,500.000 $32,213.030 $34,950.000 $39,501.350 $38,393.970
CONDT (PVC) (SCH 40) (2")
LF 450.000 $15.000 $11.960 $9.000 $13.250 $17.770
CONDT (PVC) (SCH 80) (2") (BORE)
LF 920.000 $25.000 $26.970 $25.000 $14.740 $29.020
CONDT (RM) (2")
LF 440.000 $29.000 $23.910 $28.000 $22.660 $35.260
ELEC CONDR (NO.6) BARE
LF 965.000 $1.800 $1.480 $1.650 $1.110 $1.650
ELEC CONDR (NO.6) INSULATED
LF 1,930.000 $1.900 $1.440 $1.700 $1.250 $2.270
ELEC CONDR (NO.4) BARE
LF 405.000 $1.850 $1.910 $2.500 $1.380 $2.920
ELEC CONDR (NO.4) INSULATED
LF 810.000 $1.950 $1.900 $2.600 $1.520 $3.390
GROUND BOX TY A (122311)W/APRON
EA 16.000 $750.000 $608.110 $785.000 $724.250 $1,834.300
GROUND BOX TY D (162922)W/APRON
EA 11.000 $950.000 $829.570 $900.000 $769.250 $2,205.680
ELC SRV TY D 120/240 060(NS)SS(N)TP(O)
EA 11.000 $3,500.000 $3,734.010 $2,156.000 $2,537.300 $3,951.260
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $71.000 $94.870 $275.000 $730.170 $104.460
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $10,000.000 $12,888.000 $6,500.000 $3,835.280 $6,059.200
ITS COM CBL (ETHERNET)
LF 605.000 $3.050 $1.980 $10.000 $2.720 $3.060
CCTV FIELD EQUIP (ANALOG) (INSTL ONLY)
EA 8.000 $1,405.000 $1,557.100 $3,200.000 $708.280 $1,167.040
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
EA 6.000 $1,235.000 $1,532.940 $3,200.000 $578.480 $934.080
SYSTEM INTEGRATION
LS 1.000 $10,000.000 $12,580.490 $6,500.000 $16,066.690 $12,308.800
ITS POLE (8 FT)(COSS/OSB)
EA 8.000 $3,925.000 $3,328.210 $5,600.000 $7,806.270 $6,593.130
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 8.000 $6,620.000 $4,087.680 $5,400.000 $5,476.850 $5,892.260
TMA (STATIONARY)
DAY 180.000 $135.000 $195.890 $200.000 $163.510 $136.500
CCTV ON HIGH MAST ILLUMINATION ASSEMBLY
EA 3.000 $34,000.000 $28,176.520 $31,500.000 $28,715.000 $32,704.810
Totals: $626,715.600 $571,618.897 $613,197.750 $639,052.352 $801,370.610