PREPARING ROW
|
STA
|
114.000
|
$2,000.000
|
$4,300.000
|
$1,800.000
|
$2,500.000
|
$1,000.000
|
|
|
REMOVING STAB BASE & ASPH PAV (9")
|
SY
|
2,337.000
|
$10.000
|
$6.000
|
$7.000
|
$5.000
|
$7.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
9,195.000
|
$4.500
|
$10.000
|
$5.000
|
$3.000
|
$5.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
130.000
|
$10.250
|
$52.000
|
$25.000
|
$12.000
|
$19.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
4,023.000
|
$8.000
|
$8.000
|
$7.000
|
$2.000
|
$4.000
|
|
|
BACKFILL (TY A)
|
STA
|
107.000
|
$150.000
|
$150.000
|
$200.000
|
$300.000
|
$121.000
|
|
|
FURNISHING AND PLACING TOPSOIL
|
CY
|
50.000
|
$40.000
|
$35.000
|
$25.000
|
$35.000
|
$47.000
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
41,997.000
|
$0.400
|
$0.400
|
$0.700
|
$0.420
|
$0.450
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
41,997.000
|
$0.290
|
$0.400
|
$0.600
|
$0.380
|
$0.400
|
|
|
VEGETATIVE WATERING
|
MG
|
766.000
|
$30.000
|
$29.000
|
$20.000
|
$35.000
|
$19.000
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
456.000
|
$7.000
|
$1.000
|
$1.000
|
$1.000
|
$5.000
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
7,153.000
|
$28.000
|
$28.000
|
$40.000
|
$30.000
|
$41.000
|
|
|
RWRK BS MTL(TY B)(8")(DEN CNT)(ORG POS)
|
CY
|
11,730.000
|
$14.000
|
$7.200
|
$10.000
|
$10.000
|
$4.000
|
|
|
LIME TRT (EXST MATL) (12")
|
SY
|
58,010.000
|
$2.000
|
$2.600
|
$3.100
|
$2.250
|
$2.000
|
|
|
LIME (HYD, COM OR QK)(SLURRY)
|
TON
|
1,723.000
|
$170.000
|
$170.000
|
$225.000
|
$185.000
|
$260.000
|
|
|
CEMENT
|
TON
|
638.000
|
$180.000
|
$195.000
|
$180.000
|
$193.000
|
$175.000
|
|
|
CEMENT TREAT(MX EXST MTL & NW BS)(12")
|
SY
|
56,650.000
|
$2.000
|
$2.400
|
$2.500
|
$2.250
|
$1.000
|
|
|
SALV,HAUL & STKPL RCL APH PV (2" TO 3")
|
SY
|
45,810.000
|
$2.000
|
$1.950
|
$2.700
|
$2.970
|
$3.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
10,845.000
|
$4.500
|
$5.000
|
$5.500
|
$5.000
|
$6.000
|
|
|
ASPH (TIER II)
|
GAL
|
16,266.000
|
$5.000
|
$6.250
|
$4.500
|
$4.500
|
$6.000
|
|
|
AGGR (TY-B GR-4P SAC-B)
|
CY
|
458.000
|
$75.000
|
$65.000
|
$120.000
|
$100.000
|
$133.000
|
|
|
PLANE ASPH CONC PAV (1.5")
|
SY
|
1,629.000
|
$1.800
|
$15.000
|
$15.000
|
$1.000
|
$13.000
|
|
|
CEM STABIL BKFL
|
CY
|
295.400
|
$80.000
|
$85.000
|
$50.000
|
$68.650
|
$68.000
|
|
|
CUT & RESTORING PAV
|
SY
|
72.000
|
$90.000
|
$280.000
|
$100.000
|
$48.600
|
$127.000
|
|
|
STRUCT EXCAV (SPECIAL)
|
CY
|
169.000
|
$40.000
|
$40.000
|
$65.000
|
$83.890
|
$75.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
2,016.000
|
$2.950
|
$3.500
|
$1.000
|
$1.000
|
$4.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
152.000
|
$170.000
|
$160.000
|
$180.000
|
$160.000
|
$198.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
650.000
|
$225.000
|
$280.000
|
$280.000
|
$300.000
|
$281.000
|
|
|
CL C CONC (ABUT)
|
CY
|
62.600
|
$1,300.000
|
$1,680.000
|
$1,200.000
|
$1,300.000
|
$960.000
|
|
|
REINF CONC SLAB
|
SF
|
3,680.000
|
$23.000
|
$25.000
|
$25.000
|
$44.500
|
$32.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
476.890
|
$170.000
|
$270.000
|
$210.000
|
$220.000
|
$428.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
62.000
|
$500.000
|
$350.000
|
$650.000
|
$575.000
|
$455.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
131.000
|
$450.000
|
$365.000
|
$700.000
|
$600.000
|
$484.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
57.900
|
$123.000
|
$190.000
|
$350.000
|
$200.000
|
$173.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
47.000
|
$400.000
|
$400.000
|
$600.000
|
$590.000
|
$697.000
|
|
|
RAIL (TY SSTR)
|
LF
|
216.000
|
$42.000
|
$150.000
|
$180.000
|
$210.000
|
$212.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
94.100
|
$105.000
|
$170.000
|
$180.000
|
$170.000
|
$207.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,388.000
|
$60.000
|
$45.000
|
$60.000
|
$88.000
|
$55.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,082.000
|
$80.000
|
$56.000
|
$80.000
|
$86.000
|
$66.000
|
|
|
RC PIPE (CL IV) (24 IN) (SPL)
|
LF
|
260.000
|
$90.000
|
$68.000
|
$85.000
|
$90.000
|
$88.000
|
|
|
RC PIPE (CL IV) (18") (SPL)
|
LF
|
415.000
|
$60.000
|
$58.000
|
$70.000
|
$145.000
|
$70.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
6.000
|
$4,500.000
|
$4,000.000
|
$4,500.000
|
$4,000.000
|
$4,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,500.000
|
$1,050.000
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
43.000
|
$1,100.000
|
$1,150.000
|
$1,100.000
|
$1,300.000
|
$1,600.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$1,450.000
|
$1,455.000
|
$1,500.000
|
$1,600.000
|
$1,700.000
|
|
|
REMOV STR (SET)
|
EA
|
47.000
|
$400.000
|
$250.000
|
$200.000
|
$350.000
|
$600.000
|
|
|
REMOV STR (PIPE)
|
LF
|
2,795.000
|
$15.000
|
$5.000
|
$9.000
|
$10.000
|
$8.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$20,000.000
|
$60,000.000
|
$50,000.000
|
$25,000.000
|
$100,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$420,000.000
|
$425,000.000
|
$400,000.000
|
$500,000.000
|
$350,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
17.000
|
$4,500.000
|
$4,000.000
|
$7,600.000
|
$1,550.000
|
$6,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 2)
|
SY
|
546.000
|
$25.000
|
$24.000
|
$7.000
|
$15.000
|
$21.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
546.000
|
$10.000
|
$12.000
|
$4.000
|
$1.000
|
$11.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,120.000
|
$3.300
|
$4.000
|
$7.000
|
$4.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,120.000
|
$1.300
|
$1.500
|
$2.000
|
$1.350
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
2,700.000
|
$5.000
|
$5.500
|
$10.000
|
$5.250
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,700.000
|
$1.000
|
$1.500
|
$1.000
|
$1.350
|
$1.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
923.000
|
$39.000
|
$53.000
|
$40.000
|
$55.000
|
$39.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
500.000
|
$27.500
|
$29.000
|
$28.000
|
$40.350
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,300.000
|
$2,000.000
|
$2,200.000
|
$3,087.060
|
$2,200.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
600.000
|
$2.300
|
$3.000
|
$7.000
|
$10.000
|
$5.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,300.000
|
$3,000.000
|
$3,450.000
|
$2,500.000
|
$3,600.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$270.000
|
$500.000
|
$700.000
|
$100.000
|
$417.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
2.000
|
$255.000
|
$225.000
|
$400.000
|
$500.000
|
$300.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
86.000
|
$25.000
|
$65.000
|
$35.000
|
$32.000
|
$49.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
22.000
|
$880.000
|
$690.000
|
$850.000
|
$875.000
|
$825.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
11.000
|
$800.000
|
$750.000
|
$875.000
|
$950.000
|
$775.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$1,175.000
|
$990.000
|
$1,100.000
|
$950.000
|
$1,380.000
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
1.000
|
$240.000
|
$350.000
|
$400.000
|
$1,200.000
|
$625.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
27.000
|
$105.000
|
$80.000
|
$60.000
|
$55.000
|
$80.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
27.000
|
$75.000
|
$50.000
|
$25.000
|
$15.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
12.000
|
$26.000
|
$50.000
|
$40.000
|
$45.000
|
$35.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
12.000
|
$140.000
|
$75.000
|
$60.000
|
$60.000
|
$85.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
9,940.000
|
$0.500
|
$0.600
|
$0.620
|
$0.600
|
$0.500
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
9,940.000
|
$0.490
|
$0.600
|
$0.620
|
$0.600
|
$0.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
360.000
|
$0.650
|
$0.900
|
$0.920
|
$0.900
|
$1.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
360.000
|
$0.840
|
$0.900
|
$0.920
|
$0.900
|
$1.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,650.000
|
$1.500
|
$1.150
|
$1.100
|
$3.130
|
$3.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
338.000
|
$1.000
|
$1.500
|
$1.550
|
$1.500
|
$3.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
150.000
|
$6.500
|
$5.000
|
$5.100
|
$5.000
|
$11.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
4.000
|
$130.000
|
$60.000
|
$65.000
|
$60.000
|
$126.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
4.000
|
$150.000
|
$75.000
|
$80.000
|
$75.000
|
$126.000
|
|
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
|
LF
|
533.000
|
$3.500
|
$2.000
|
$2.100
|
$2.000
|
$6.000
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
2,350.000
|
$0.400
|
$0.450
|
$0.500
|
$0.450
|
$0.470
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
9,881.000
|
$0.400
|
$0.400
|
$0.450
|
$0.400
|
$0.470
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
21,266.000
|
$0.500
|
$0.850
|
$0.900
|
$0.850
|
$1.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
18.000
|
$4.500
|
$5.000
|
$5.100
|
$5.000
|
$6.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
506.000
|
$4.000
|
$3.750
|
$4.000
|
$3.750
|
$4.000
|
|
TRAFFIC BUTTON TY Y
|
EA
|
493.000
|
$3.000
|
$3.750
|
$4.000
|
$3.750
|
$2.000
|
|
TRAFFIC BUTTON TY B
|
EA
|
2,917.000
|
$1.800
|
$1.250
|
$1.350
|
$1.250
|
$2.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
5,510.000
|
$0.380
|
$0.650
|
$0.700
|
$0.650
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
328.000
|
$0.160
|
$3.000
|
$3.200
|
$3.000
|
$0.310
|
|
|
IRRIGATION VALVE (12")
|
EA
|
2.000
|
$3,500.000
|
$6,350.000
|
$6,300.000
|
$10,000.000
|
$2,780.000
|
|
|
PRSSR IRRIG PVC PIPE (18")
|
LF
|
202.000
|
$55.000
|
$135.000
|
$55.000
|
$70.000
|
$107.000
|
|
|
PRSSR IRRIG PVC PIPE (24")
|
LF
|
193.000
|
$70.000
|
$166.000
|
$100.000
|
$130.000
|
$205.000
|
|
|
PRSSR IRRIG PVC PIPE (12")
|
LF
|
89.000
|
$48.000
|
$120.000
|
$38.000
|
$55.000
|
$48.000
|
|
|
SP MIXES SP-D SAC-A PG76-22
|
TON
|
9,424.000
|
$120.000
|
$100.000
|
$125.000
|
$140.000
|
$172.000
|
|
|
BONDING COURSE
|
GAL
|
3,910.000
|
$5.000
|
$4.000
|
$4.500
|
$5.000
|
$7.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
56,650.000
|
$1.400
|
$1.470
|
$1.200
|
$2.000
|
$2.000
|
|
|
BIRD EXCLUSION METHOD
|
SF
|
2,713.000
|
$1.780
|
$6.000
|
$3.500
|
$6.000
|
$6.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$9,800.000
|
$5,000.000
|
$12,000.000
|
$100.000
|
$15,280.000
|
|
MULTIPOLYMER PAV MRK (W)(4")(SLD)
|
LF
|
164.000
|
$0.950
|
$90.000
|
$91.000
|
$90.000
|
$3.000
|
|
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
|
LF
|
164.000
|
$0.990
|
$90.000
|
$91.000
|
$90.000
|
$3.000
|
|
|
TMA (STATIONARY)
|
DAY
|
266.000
|
$25.000
|
$1.000
|
$30.000
|
$10.000
|
$25.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
30.000
|
$230.000
|
$1.000
|
$35.000
|
$100.000
|
$50.000
|
|
|
CASING (STEEL) (20 IN) (OPEN TRENCH)
|
LF
|
72.000
|
$160.000
|
$365.000
|
$130.000
|
$160.000
|
$274.000
|
|
|
CASING (STEEL) (24 IN) (OPEN TRENCH)
|
LF
|
140.000
|
$200.000
|
$385.000
|
$140.000
|
$135.000
|
$313.000
|
|
|
CASING (STEEL) (30 IN) (OPEN TRENCH)
|
LF
|
140.000
|
$250.000
|
$440.000
|
$220.000
|
$160.000
|
$401.000
|
|
Totals: |
$4,754,899.410
|
$5,127,397.900
|
$5,334,331.400
|
$5,430,834.660
|
$5,760,721.220
|