HIDALGO CS (0921-02-484)
Items: 43
County: HIDALGO
Length: N/A
Highway: CS
District: PHARR
Control Number: 0921-02-484
DBE Goal: N/A
Project: STP 2B23(007)HESG
Guaranty: N/A
Time: 147 WORKING DAYS
Engineer's Estimate: $260,635.90
Date: 06/28/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
HECTOR SILLER
JESUS NORIEGA
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$260,635.90 | |||
| $307,597.50 |
18.02%
$46,961.60
|
|||
| $318,567.12 |
22.23%
$57,931.22
|
3.57%
$10,969.62
|
||
| $357,304.78 |
37.09%
$96,668.88
|
16.16%
$49,707.28
|
-12.16%
-$38,737.66
|
|
| $421,234.68 |
61.62%
$160,598.78
|
36.94%
$113,637.18
|
-17.89%
-$63,929.90
|
E
Engineer's Estimate
$260,635.90
$307,597.50
Over/Under Est:
18.02%
$46,961.60
$318,567.12
Over/Under Est:
22.23%
$57,931.22
Amt Left:
3.57%
$10,969.62
$357,304.78
Over/Under Est:
37.09%
$96,668.88
Amt Left:
16.16%
$49,707.28
Delta:
-12.16%
-$38,737.66
$421,234.68
Over/Under Est:
61.62%
$160,598.78
Amt Left:
36.94%
$113,637.18
Delta:
-17.89%
-$63,929.90
| Subcontractor | Percentage | Amount |
|---|---|---|
| PAVEMENT MARKINGS INC. | 4.31% | $13,257.45 |
| Total: | 4.31% | $13,257.45 |
Bid Items & Bid Tabulations
43
Total
0 of 43