Show Job Controls
Bid Cobra

HIDALGO CS (0921-02-305)

Items: 84

County: HIDALGO
Length: N/A
Highway: CS
District: PHARR
Control Number: 0921-02-305
DBE Goal: N/A
Project: BR 2015(640)
Guaranty: N/A
Time: 227 WORKING DAYS
Engineer's Estimate: $1,368,414.00
Date: 07/10/2018 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE & RECONSTRUCT APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,368,414.00
$1,276,034.00
Over/Under Est: -6.75% -$92,380.00
$1,358,484.09
Over/Under Est: -0.73% -$9,929.91
Amt Left: 6.46% $82,450.09
Over/Under Est: 1.73% $23,719.39
Amt Left: 9.1% $116,099.39
Delta: -2.48% -$33,649.30
Over/Under Est: 2.23% $30,516.70
Amt Left: 9.63% $122,896.70
Delta: -0.49% -$6,797.31
$1,479,800.70
Over/Under Est: 8.14% $111,386.70
Amt Left: 15.97% $203,766.70
Delta: -5.78% -$80,870.00

Bid Items & Bid Tabulations

84 Total 0 of 84
HIDALGO  |  CS  |  PHARR  |  0921-02-305  |  07/10/2018  |  $1,368,414.00  |  BR 2015(640)  |  REPLACE BRIDGE & RECON APPROACHES  |  227 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS CORDIA CONSTRUCTION, LLC
IOC COMPANY, LLC
ARANDA BROTHERS CONSTRUCTION CO., INC.
VALLEY INFRASTRUCTURE, INC.
FOREMOST PAVING, INC.
PREPARING ROW
STA 7.120 $1,000.000 $1,250.000 $1,350.000 $18,700.000 $825.000 $4,100.000
REMOVING CONC (RIPRAP)
SY 86.000 $15.000 $26.000 $30.000 $5.000 $25.000 $10.000
REMOVING CONC (DRIVEWAYS)
SY 33.000 $15.000 $33.000 $30.000 $5.000 $30.000 $22.250
REMOVING CONC (CURB AND GUTTER)
LF 168.000 $10.000 $6.000 $10.000 $2.000 $10.000 $8.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 87.000 $15.000 $15.000 $15.000 $5.000 $20.000 $12.000
REMOVING CONC (FLUME)
SY 6.000 $30.000 $160.000 $50.000 $5.000 $30.000 $120.000
REMOVING STAB BASE AND ASPH PAV(1"-9")
SY 971.000 $7.000 $14.000 $8.000 $7.350 $8.500 $16.500
EXCAVATION (ROADWAY)
CY 2,435.000 $5.000 $10.000 $3.000 $6.000 $21.000 $4.270
EXCAVATION (CHANNEL)
CY 561.000 $20.000 $18.000 $13.000 $10.000 $10.000 $10.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,026.000 $20.000 $5.000 $14.440 $12.000 $12.500 $11.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,832.000 $2.000 $2.000 $6.000 $3.000 $14.000 $3.500
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,832.000 $1.250 $1.000 $0.500 $0.450 $0.500 $0.750
DRILL SEEDING (TEMP) (WARM)
SY 2,832.000 $1.250 $1.000 $0.200 $0.350 $0.500 $0.800
DRILL SEEDING (TEMP) (COOL)
SY 2,832.000 $0.750 $1.000 $0.200 $0.350 $0.500 $0.800
VEGETATIVE WATERING
MG 47.700 $50.000 $40.000 $30.000 $40.000 $40.000 $40.000
FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)
CY 547.000 $40.000 $26.000 $35.000 $35.000 $45.000 $62.000
CEMENT
TON 70.000 $180.000 $220.000 $150.000 $165.000 $150.000 $186.000
CEMENT TREAT (NEW BASE) (8")
SY 2,642.000 $6.000 $2.000 $4.000 $7.500 $5.500 $4.750
CEMENT TREAT (SUBGRADE)(12")
SY 2,473.000 $5.000 $3.000 $5.000 $6.000 $6.500 $12.000
PRIME COAT (MC-30)
GAL 459.000 $7.500 $7.000 $3.500 $5.000 $7.500 $7.000
D-GR HMA(SQ) TY-D PG64-22
TON 183.000 $125.000 $140.000 $110.000 $105.000 $135.000 $250.000
CEM STABIL BKFL
CY 72.000 $120.000 $40.000 $75.000 $55.000 $90.000 $80.000
TRENCH EXCAVATION PROTECTION
LF 593.000 $6.000 $8.000 $1.000 $1.000 $3.000 $1.000
DRILL SHAFT (30 IN)
LF 360.000 $100.000 $250.000 $234.470 $200.000 $235.000 $250.000
CL C CONC (ABUT)
CY 50.200 $1,000.000 $590.000 $1,000.000 $1,000.000 $975.000 $1,000.000
REINF CONC SLAB (BOX BEAM)
SF 3,761.000 $17.500 $15.000 $17.000 $15.000 $18.000 $13.000
BRIDGE SIDEWALK
SF 910.000 $12.500 $12.000 $17.000 $9.000 $22.000 $10.000
SHEAR KEY
CY 22.400 $400.000 $500.000 $475.000 $300.000 $550.000 $170.000
PRESTR CONC BOX BEAM (4B20)
LF 516.000 $190.000 $260.000 $180.000 $200.000 $215.000 $180.000
PRESTR CONC BOX BEAM (5B20)
LF 322.500 $190.000 $260.000 $180.000 $220.000 $220.000 $180.000
RIPRAP (CONC)(5 IN)
CY 186.000 $400.000 $370.000 $425.000 $325.000 $600.000 $750.000
RIPRAP (MOW STRIP)(4 IN)
CY 8.000 $500.000 $490.000 $500.000 $350.000 $550.000 $750.000
STR STEEL (MISC NON - BRIDGE)
LB 308.000 $20.000 $21.000 $21.000 $13.780 $21.000 $14.000
RAIL (TY C221)
LF 220.000 $150.000 $113.000 $125.000 $125.000 $202.000 $200.000
CONC BOX CULV (8 FT X 8 FT)
LF 198.000 $810.000 $700.000 $750.000 $605.000 $860.000 $650.000
RC PIPE (CL III)(24 IN)
LF 472.000 $70.000 $50.000 $65.000 $65.000 $60.000 $70.000
RC PIPE (CL III)(30 IN)
LF 179.000 $105.000 $70.000 $72.000 $70.000 $80.000 $80.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $6,000.000 $3,120.000 $2,800.000 $2,650.000 $4,400.000 $4,000.000
JCTBOX(COMPL)(PJB)(4FTX4FT)
EA 1.000 $5,000.000 $2,921.000 $3,000.000 $2,700.000 $4,100.000 $4,000.000
INLET (COMPL)(PCU)(3FT)(BOTH)
EA 3.000 $4,000.000 $4,260.000 $3,200.000 $3,250.000 $5,500.000 $6,000.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 6.000 $2,500.000 $2,670.000 $3,800.000 $2,600.000 $3,700.000 $4,400.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 4.000 $3,800.000 $4,030.000 $3,500.000 $3,650.000 $5,300.000 $5,500.000
WINGWALL (SW - 0) (HW=11 FT)
EA 2.000 $38,000.000 $20,250.000 $25,000.000 $10,500.000 $21,500.000 $60,000.000
REMOV STR (HEADWALL)
EA 1.000 $1,500.000 $2,020.000 $2,500.000 $1,500.000 $1,500.000 $4,000.000
REMOV STR (PIPE)
LF 137.000 $10.000 $8.000 $10.000 $10.000 $15.000 $20.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $22,500.000 $25,000.000 $30,000.000 $64,000.000 $11,000.000 $16,000.000
REMOVE STR (BOLLARD)
EA 2.000 $150.000 $238.000 $500.000 $150.000 $400.000 $30.000
MOBILIZATION
LS 1.000 $120,000.000 $64,385.000 $150,000.000 $130,000.000 $96,000.000 $105,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000 $4,000.000 $2,000.000 $2,500.000 $1,450.000 $1,000.000 $1,600.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 52.000 $55.000 $77.000 $45.000 $35.000 $40.000 $65.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 52.000 $55.000 $114.000 $45.000 $35.000 $40.000 $65.000
ROCK FILTER DAMS (REMOVE)
LF 52.000 $13.000 $47.000 $10.000 $5.000 $20.000 $20.000
ROCK FILTER DAMS (REMOVE)
LF 52.000 $13.000 $47.000 $10.000 $5.000 $20.000 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 166.000 $30.000 $25.000 $25.000 $30.000 $25.000 $41.000
CONSTRUCTION EXITS (REMOVE)
SY 166.000 $12.000 $12.000 $9.980 $10.000 $10.000 $24.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,067.000 $5.000 $3.000 $6.000 $3.000 $4.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,067.000 $2.000 $1.000 $2.000 $1.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 386.000 $5.000 $5.000 $6.000 $5.750 $6.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 386.000 $2.000 $2.000 $1.000 $1.000 $1.000 $1.000
CONC CURB & GUTTER (VALLEY GUTTER)
LF 274.000 $25.000 $37.000 $35.000 $17.000 $65.000 $28.000
CONC. CURB TY A (BARRIER)
LF 661.000 $30.000 $19.000 $24.000 $18.000 $15.000 $26.000
DRIVEWAYS (CONC)
SY 16.000 $80.000 $94.000 $80.000 $45.000 $70.000 $85.000
DRIVEWAYS (ACP)
SY 276.000 $35.000 $29.000 $26.000 $40.000 $32.000 $78.000
CONC SIDEWALKS (4")
SY 104.000 $50.000 $55.000 $50.000 $40.000 $36.000 $56.000
CURB RAMPS (TY 1)
EA 2.000 $1,600.000 $1,700.000 $1,500.000 $1,750.000 $1,100.000 $1,210.000
CURB RAMPS (TY 10)
EA 11.000 $2,000.000 $1,615.000 $1,500.000 $1,350.000 $1,100.000 $1,310.000
CURB RAMPS (TY 21)
EA 1.000 $2,000.000 $1,692.000 $1,500.000 $1,950.000 $1,100.000 $1,460.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $950.000 $1,780.000 $2,500.000 $1,550.000 $1,250.000 $1,070.000
SHORT RADIUS
LF 100.000 $30.000 $52.000 $55.000 $35.000 $37.000 $35.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 4.000 $760.000 $1,216.000 $1,500.000 $1,290.000 $900.000 $800.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $5.000 $8.000 $10.000 $5.000 $5.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $100.000 $315.000 $1,000.000 $275.000 $150.000 $180.000
CHAIN LINK FENCE(INSTALL)(6 )(BARB TOP)
LF 40.000 $50.000 $25.000 $45.000 $20.000 $15.000 $37.000
REMOVE AND INSTALL EXISTING GATE
EA 1.000 $2,500.000 $520.000 $2,000.000 $500.000 $250.000 $1,200.000
MAILBOX INSTALL-S (TIM-POST) TY 5
EA 1.000 $150.000 $281.000 $575.000 $300.000 $500.000 $265.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 6.000 $500.000 $438.000 $800.000 $650.000 $800.000 $620.000
REMOVE SM RD SN SUP&AM
EA 2.000 $130.000 $142.000 $100.000 $100.000 $50.000 $85.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 10.000 $70.000 $152.000 $69.530 $100.000 $75.000 $50.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 13.000 $65.000 $156.000 $75.090 $100.000 $75.000 $50.000
PAVEMENT SEALER 4"
LF 260.000 $1.000 $1.000 $1.250 $1.000 $0.880 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,424.000 $2.000 $1.000 $2.250 $4.000 $1.050 $1.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,424.000 $2.000 $1.000 $2.250 $4.000 $1.050 $1.600
REFL PAV MRKR TY II-A-A
EA 20.000 $20.000 $15.000 $10.000 $50.000 $11.000 $7.000
BIRD EXCLUSION METHOD
SF 5,784.000 $2.000 $7.000 $2.500 $3.000 $1.000 $3.000
Totals: $1,368,414.000 $1,276,034.000 $1,358,484.090 $1,392,133.390 $1,398,930.700 $1,479,800.700