Bid Cobra

HIDALGO FM 494 (0864-01-069)

Items: 173

County: HIDALGO
Length: 1.9900 MILES
Highway: FM 494
District: PHARR
Control Number: 0864-01-069
DBE Goal: 4.0%
Project: F 2025(673)
Guaranty: $100,000.00
Time: 432 WORKING DAYS
Engineer's Estimate: $16,823,452.87
Date: 04/03/2025 (1 year ago)
Contract Number: 4253005
Type: WIDEN ROAD - ADD LANES
Project ID: A00096030
Contract Type: Federal
Project Description: WIDEN TO 4 LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HECTOR SILLER
JESUS NORIEGA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$16,823,452.87
$15,739,166.30
Over/Under Est: -6.45% -$1,084,286.57
Over/Under Est: -4.07% -$685,296.87
Amt Left: 2.54% $398,989.70
$19,596,885.17
Over/Under Est: 16.49% $2,773,432.30
Amt Left: 24.51% $3,857,718.87
Delta: -21.43% -$3,458,729.17
Subcontractor Percentage Amount
FLOVERA CONSTRUCTION SERVICES, LLC 6.71% $1,056,098.06
*AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 2.49% $391,905.24
HIGHWAY BARRICADES AND SERVICES, LLC 1.26% $198,313.50
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 0.39% $61,382.75
TEXAS ICON CONSTRUCTION, LLC 0.14% $22,034.83
Total: 10.99% $1,729,734.38

Bid Items & Bid Tabulations

173 Total 0 of 173
HIDALGO  |  FM 494  |  PHARR  |  0864-01-069  |  04/03/2025  |  $16,823,452.87  |  F 2025(673)  |  WIDEN ROAD - ADD LANES  |  432 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REIM CONSTRUCTION, INC.
TEXAS CORDIA CONSTRUCTION, LLC
FOREMOST PAVING, INC.
PREPARING ROW
STA 111.000 $3,000.000 $2,700.000 $2,500.000 $5,000.000
REMOV CONC (PAV)
SY 113.000 $7.700 $6.350 $20.000 $25.000
REMOV CONC (RIPRAP)
SY 469.000 $17.730 $7.850 $5.000 $10.000
REMOV CONC (DRIVEWAYS)
SY 1,992.000 $17.250 $9.750 $5.000 $20.500
REMOV CONC (CURB & GUTTER)
LF 520.000 $7.500 $3.300 $3.000 $8.500
RMV (10") TRT/UNTRT BASE & ASPH PAV
CY 1,000.000 $15.360 $11.900 $20.000 $8.000
EXCAV (ROADWAY)
CY 44,651.000 $7.500 $5.300 $7.000 $7.500
EMBANK (FNL)(DC)(TY C)
CY 6,878.000 $20.000 $5.400 $3.000 $10.000
BACKFILL (TY A)
STA 20.000 $122.370 $232.000 $200.000 $455.000
FURN & PLACE TOPSOIL (VEH)
CY 100.000 $40.500 $38.250 $40.000 $16.000
HYDRO MULCH SEED (PERM_URBAN_SANDY)
SY 23,259.000 $0.650 $0.690 $0.500 $0.700
HYDRO MULCH SEED (TEMP_WARM)
SY 23,259.000 $0.450 $0.350 $0.500 $0.330
VEGETATIVE WATERING
TGL 395.000 $21.500 $29.250 $30.000 $65.000
SPRINKLING (DUST CONTROL)
TGL 444.000 $13.290 $29.250 $20.000 $1.000
PROOF ROLLING
HR 200.000 $117.740 $40.250 $60.000 $80.000
FL BS (RDWY DEL)(TY E GR 4)(FNL POS)
CY 14,422.000 $35.980 $34.500 $38.000 $32.000
GEOGRID BASE REINFORCEMENT (TYPE 2)
SY 106,046.000 $1.350 $1.100 $2.000 $1.400
REWORK BS MTL (TY B)(5")(DC)(ORG POS)
CY 14,422.000 $22.000 $4.100 $4.000 $8.500
CEMENT
TON 2,548.000 $226.450 $216.000 $210.000 $190.000
CEMENT TRT (EXIST MATL & NEW BASE)(10")
SY 103,824.000 $3.000 $1.750 $2.000 $2.200
CEMENT TRT (SUBGRADE)(12")
SY 106,046.000 $2.000 $1.900 $2.000 $2.600
SALV,HAUL & STKPL RCL ASPH PV(3"TO 6")
SY 46,835.000 $2.500 $3.250 $3.000 $3.650
PRIME COAT (MC-30)
GAL 21,209.000 $5.920 $4.400 $5.000 $4.500
SP MIXES SP-B SAC-B PG76-22
TON 19,263.000 $130.000 $112.000 $120.000 $108.000
SP MIXES SP-C SAC-A PG76-22
TON 11,007.000 $107.980 $115.000 $120.000 $110.000
STRUCT EXCAV (SPECIAL)
CY 2,983.000 $77.960 $73.500 $100.000 $75.000
CUT & RESTORING PAV
SY 608.000 $90.000 $61.500 $85.000 $100.000
CEM STABIL BKFL
CY 7,186.000 $78.640 $97.500 $60.000 $120.000
TRENCH EXCAVATION PROTECTION
LF 11,753.000 $2.910 $1.800 $3.000 $1.000
TEMPORARY SPL SHORING
SF 3,906.000 $28.000 $20.750 $30.000 $28.000
DRILL SHAFT (TRF SIG POLE) (24 IN)
LF 36.000 $203.040 $155.000 $150.000 $140.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 84.000 $311.740 $426.000 $420.000 $385.000
CL C CONC (COLLAR)
EA 14.000 $1,600.000 $898.000 $5,340.000 $6,000.000
RETAINING WALL (MSE)
SF 17,033.000 $44.000 $72.500 $100.000 $105.000
RIPRAP (CONC)(4 IN)
CY 53.000 $651.440 $437.000 $630.000 $450.000
RAIL (TY T551)
LF 2,047.000 $131.410 $211.000 $50.000 $95.000
RAIL (TY PR11)
LF 865.000 $232.400 $122.000 $120.000 $100.000
RC PIPE (CL III)(18 IN)
LF 2,223.000 $70.120 $77.000 $80.000 $150.000
RC PIPE (CL III)(24 IN)
LF 1,351.000 $94.190 $89.000 $90.000 $152.000
RC PIPE (CL III)(30 IN)
LF 1,441.000 $120.000 $119.000 $118.000 $158.000
RC PIPE (CL III)(36 IN)
LF 371.000 $156.000 $175.000 $175.000 $175.000
RC PIPE (CL III)(42 IN)
LF 1,855.000 $180.000 $232.000 $230.000 $210.000
RC PIPE (CL III)(48 IN)
LF 2,524.000 $200.000 $273.000 $270.000 $260.000
RC PIPE (CL III)(54 IN)
LF 1,991.000 $215.000 $308.000 $310.000 $337.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 5.000 $5,500.000 $4,700.000 $5,000.000 $6,600.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 18.000 $5,200.000 $4,930.000 $5,270.000 $6,600.000
INLET (COMPL)(PCO)(3FT)(BOTH)
EA 4.000 $6,000.000 $5,640.000 $5,970.000 $7,300.000
INLET (COMPL)(PCO)(4FT)(LEFT)
EA 2.000 $5,800.000 $6,040.000 $6,600.000 $8,400.000
INLET (COMPL)(PCO)(4FT)(RIGHT)
EA 4.000 $10,604.410 $5,720.000 $6,200.000 $8,600.000
INLET (COMPL)(PCO)(4FT)(BOTH)
EA 1.000 $8,863.420 $6,060.000 $6,400.000 $7,600.000
INLET (COMPL)(PCO)(5FT)(NONE)
EA 1.000 $5,548.000 $6,080.000 $6,800.000 $10,500.000
INLET (COMPL)(PCO)(5FT)(LEFT)
EA 5.000 $12,838.350 $6,110.000 $6,400.000 $9,000.000
INLET (COMPL)(PCO)(5FT)(BOTH)
EA 1.000 $12,269.390 $6,970.000 $7,000.000 $9,400.000
INLET (COMPL)(PCO)(6FT)(LEFT)
EA 8.000 $12,542.000 $7,330.000 $8,900.000 $12,200.000
INLET (COMPL)(PCO)(6FT)(BOTH)
EA 5.000 $8,223.890 $7,850.000 $9,500.000 $11,300.000
INLET (COMPL)(PCU)(3FT)(NONE)
EA 4.000 $5,328.000 $3,750.000 $4,300.000 $5,900.000
INLET (COMPL)(PSL)(RC)(6FTX6FT)
EA 5.000 $8,731.000 $7,380.000 $11,600.000 $10,000.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 5.000 $4,600.000 $3,620.000 $4,780.000 $8,300.000
REMOV STR (INLET)
EA 2.000 $1,506.670 $652.000 $700.000 $600.000
REMOV STR (SET)
EA 16.000 $620.920 $294.000 $300.000 $600.000
REMOV STR (PIPE)
LF 302.000 $12.910 $11.000 $10.000 $50.000
MOBILIZATION
LS 1.000 $1,530,768.440 $1,300,000.000 $834,900.000 $1,750,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $7,580.328 $2,380.000 $500.000 $8,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $106.680 $56.000 $30.000 $65.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $3,277.760 $2,810.000 $300.000 $13,000.000
TMA (STATIONARY)
DAY 720.000 $72.620 $28.000 $15.000 $40.000
TMA (MOBILE OPERATION)
DAY 480.000 $115.180 $56.000 $25.000 $0.010
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 480.000 $25.610 $9.850 $10.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 480.000 $7.730 $8.250 $8.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $3.770 $4.500 $6.000 $9.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $1.150 $1.950 $3.000 $3.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 930.000 $3.810 $2.450 $5.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 930.000 $1.100 $1.000 $1.000 $2.000
CONSTRUCTING DETOURS
SY 6,943.000 $42.040 $41.500 $38.000 $50.000
PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1
LF 3,720.000 $51.940 $8.650 $30.000 $30.000
PCTB (MOVE)(F-SHAPE OR SNGL SLP)TY1
LF 3,720.000 $6.460 $6.750 $6.000 $11.000
PCTB (REMOVE)(F-SHAPE OR SNGL SLP)TY1
LF 3,720.000 $10.500 $4.250 $10.000 $9.000
CONCRETE C&G (VALLEY GUTTER)
LF 456.000 $58.950 $41.500 $78.000 $52.000
CONC CURB (TY F3)
LF 865.000 $221.890 $163.000 $210.000 $420.000
CONC CURB & GUTTER (TY B) (MOUNTABLE)
LF 16,907.000 $15.630 $15.000 $19.000 $15.000
DRIVEWAYS (CONC)
SY 1,166.000 $78.970 $61.000 $90.000 $64.200
DRIVEWAYS (ACP)
SY 2,466.000 $39.440 $36.250 $30.000 $48.000
CONC SIDEWALKS (4")
SY 12,433.000 $47.250 $41.000 $50.000 $57.000
CURB RAMPS (TY 1)
EA 12.000 $1,800.000 $1,570.000 $1,760.000 $2,100.000
CURB RAMPS (TY 10)
EA 10.000 $1,634.910 $1,780.000 $1,775.000 $2,100.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $26.000 $28.500 $30.000 $25.850
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,200.000 $2,350.000 $2,800.000 $2,125.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,600.000 $1,320.000 $3,000.000 $1,190.000
REMOVE METAL BEAM GUARD FENCE
LF 2,175.000 $3.560 $2.900 $8.000 $2.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 6.000 $201.930 $453.000 $380.000 $225.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,300.000 $3,210.000 $4,000.000 $2,900.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $1,511.670 $1,650.000 $3,000.000 $1,490.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,035.390 $534.000 $1,550.000 $800.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $25,000.000 $8,770.000 $5,600.000 $7,800.000
MAILBOX INSTALL-S (TWG-POST) TY 4
EA 23.000 $412.970 $249.000 $460.000 $225.000
CONDT (PVC) (SCH 40) (1")
LF 160.000 $19.920 $24.250 $20.000 $22.000
CONDT (PVC) (SCH 40) (2")
LF 1,870.000 $12.640 $15.500 $19.000 $14.000
CONDT (PVC) (SCH 40) (4")
LF 205.000 $28.790 $31.000 $30.000 $28.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 480.000 $36.580 $44.250 $40.000 $40.000
ELEC CONDR (NO.8) BARE
LF 1,050.000 $1.550 $2.100 $2.000 $1.900
ELEC CONDR (NO.6) BARE
LF 115.000 $1.810 $2.500 $2.000 $2.250
ELEC CONDR (NO.6) INSULATED
LF 155.000 $2.570 $2.550 $2.000 $2.300
TRAY CABLE (4 CONDR) (12 AWG)
LF 785.000 $2.500 $2.750 $3.000 $2.500
GROUND BOX TY A (122311)W/APRON
EA 25.000 $1,100.000 $1,090.000 $1,070.000 $990.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $1,461.770 $1,270.000 $1,250.000 $1,150.000
REMOVE GROUND BOX
EA 8.000 $293.160 $404.000 $400.000 $365.000
ZINC-COAT STL WIRE STRAND (3/8")
LF 1,850.000 $2.760 $3.100 $3.000 $2.800
REMOVE ELECTRICAL SERVICES
EA 3.000 $665.790 $608.000 $600.000 $560.000
ELC SRV TY T 120/240 000(NS)GS(L)TS(O)
EA 3.000 $2,524.450 $3,150.000 $3,090.000 $2,850.000
ALUMINUM SIGNS (TY A)
SF 92.000 $30.600 $25.250 $20.000 $75.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 22.000 $778.200 $796.070 $740.000 $720.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 6.000 $830.250 $995.000 $1,320.000 $900.000
RELOCATE SM RD SN SUP&AM TY S80
EA 2.000 $639.080 $254.000 $1,540.000 $700.000
REMOVE SM RD SN SUP&AM
EA 18.000 $90.000 $122.000 $270.000 $100.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 18,550.000 $0.540 $0.640 $0.500 $0.600
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 426.000 $9.250 $9.950 $9.000 $9.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 22,384.000 $0.540 $0.640 $0.500 $0.600
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,247.000 $3.000 $8.300 $8.000 $7.500
WK ZN PAV MRK REMOV (W)6"(DOT)
LF 159.000 $1.750 $3.300 $3.000 $3.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 21,620.000 $0.760 $0.460 $0.500 $0.500
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 100.000 $1.410 $3.300 $3.000 $3.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 33,417.000 $0.850 $0.460 $0.500 $0.500
WK ZN PAV MRK REMOV (Y)12"(SLD)
LF 398.000 $1.900 $3.300 $3.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,500.000 $1.280 $1.450 $2.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 3,000.000 $1.730 $1.050 $2.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,009.000 $1.180 $0.970 $1.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,171.000 $8.770 $9.950 $9.000 $9.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 10.000 $161.480 $221.000 $200.000 $200.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $200.230 $332.000 $300.000 $305.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 252.000 $4.870 $2.200 $2.000 $2.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 5,040.000 $0.750 $0.970 $1.000 $0.900
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 21,828.000 $0.730 $0.820 $0.500 $0.800
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 4,340.000 $0.750 $0.970 $1.000 $0.900
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 21,749.000 $0.670 $0.820 $0.500 $0.800
REFL PAV MRKR TY I-C
EA 310.000 $4.690 $8.300 $8.000 $7.500
REFL PAV MRKR TY II-A-A
EA 605.000 $3.850 $8.300 $8.000 $7.500
ELIM EXT PM & MRKS (4")
LF 15,440.000 $0.400 $0.550 $0.500 $0.500
ELIM EXT PM & MRKS (24")
LF 80.000 $3.000 $11.000 $10.000 $10.000
INSTALL HWY TRF SIG (ISOLATED)
EA 2.000 $18,500.000 $20,500.000 $21,100.000 $18,500.000
REMOVING TRAFFIC SIGNALS
EA 2.000 $2,900.000 $3,040.000 $2,980.000 $2,750.000
TEMP TRAF SIGNALS
EA 3.000 $40,000.000 $11,300.000 $11,600.000 $10,250.000
VEH SIG SEC (12")LED(GRN)
EA 8.000 $275.550 $348.000 $340.000 $315.000
VEH SIG SEC (12")LED(GRN ARW)
EA 4.000 $280.150 $348.000 $340.000 $315.000
VEH SIG SEC (12")LED(YEL)
EA 12.000 $281.330 $348.000 $340.000 $315.000
VEH SIG SEC (12")LED(YEL ARW)
EA 8.000 $284.630 $348.000 $340.000 $315.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $280.740 $348.000 $340.000 $315.000
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $283.820 $348.000 $340.000 $315.000
PED SIG SEC (LED)(COUNTDOWN)
EA 12.000 $597.000 $691.000 $680.000 $625.000
BACK PLATE (12")(3 SECT)
EA 8.000 $85.950 $105.000 $100.000 $95.000
BACK PLATE (12")(4 SECT)
EA 4.000 $170.000 $127.000 $120.000 $115.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 2,375.000 $2.010 $1.950 $2.000 $1.750
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 4,000.000 $2.540 $2.450 $2.000 $2.200
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 2,705.000 $2.800 $2.750 $3.000 $2.500
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
LF 5,635.000 $1.860 $1.950 $2.000 $1.750
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $5,306.140 $6,360.000 $6,410.000 $5,750.000
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 3.000 $500.000 $1,220.000 $1,190.000 $1,100.000
INS TRF SIG PL AM (S)STR(TY B)
EA 3.000 $6,280.930 $9,180.000 $8,990.000 $5,300.000
INS TRF SIG PL AM (S)STR(TY B)LUM
EA 3.000 $7,357.850 $9,840.000 $9,640.000 $8,900.000
PED POLE ASSEMBLY
EA 6.000 $2,069.330 $1,310.000 $1,280.000 $1,185.000
PED DETECT PUSH BUTTON (APS)
EA 12.000 $846.420 $912.000 $890.000 $825.000
PED DETECTOR CONTROLLER UNIT
EA 2.000 $3,200.000 $4,020.000 $3,940.000 $3,640.000
VEH LP DETECT (SAWCUT)
LF 2,047.000 $12.430 $18.250 $20.000 $16.500
REMOVAL OF CONTROL CABINET(GRND MNT)
EA 1.000 $451.430 $332.000 $920.000 $850.000
TREE REMOVAL (4" - 12" DIA)
EA 329.000 $375.130 $70.000 $20.000 $400.000
TREE REMOVAL (12" - 18" DIA)
EA 177.000 $431.190 $129.000 $140.000 $725.000
TREE REMOVAL (18" - 24" DIA)
EA 5.000 $675.000 $226.000 $2,570.000 $1,925.000
PRSSR IRRIG PVC PIPE (18")
LF 380.000 $220.000 $93.000 $90.000 $160.000
PRSSR IRRIG PVC PIPE (24")
LF 573.000 $237.390 $142.000 $140.000 $180.000
IRRIGATION WELL (48")
EA 4.000 $12,000.000 $23,400.000 $21,300.000 $65,000.000
IRRIGATION WELL (60")
EA 9.000 $18,500.000 $24,800.000 $26,000.000 $81,000.000
BONDING COURSE
GAL 6,857.000 $4.750 $4.500 $1.000 $2.800
WELDED STL CASING PIPE (OPEN CUT)(24")
LF 316.000 $200.000 $173.000 $241.000 $500.000
WELDED STL CASING PIPE (OPEN CUT)(30")
LF 458.000 $200.000 $225.000 $296.000 $580.000
Totals: $16,823,452.870 $15,739,166.300 $16,138,156.000 $19,596,885.170
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $248,196.14
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $124,098.00
Total: $372,294.14