HIDALGO FM 492 (0862-01-057)

Items: 79

County: HIDALGO
Length: N/A
Highway: FM 492
District: PHARR
Control Number: 0862-01-057
DBE Goal: N/A
Project: BR 2023(199)
Guaranty: N/A
Time: 159 WORKING DAYS
Engineer's Estimate: $2,066,856.82
Date: 11/03/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JESUS NORIEGA
ANDRES ESPINOZA
HECTOR SILLER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,066,856.82
$1,917,663.50
Over/Under Est: -7.22% -$149,193.32
Over/Under Est: 5.19% $107,336.93
Amt Left: 13.38% $256,530.25
$2,244,245.35
Over/Under Est: 8.58% $177,388.53
Amt Left: 17.03% $326,581.85
Delta: -3.22% -$70,051.60
$2,889,271.44
Over/Under Est: 39.79% $822,414.62
Amt Left: 50.67% $971,607.94
Delta: -28.74% -$645,026.09
Over/Under Est: 52.49% $1,084,842.18
Amt Left: 64.35% $1,234,035.50
Delta: -9.08% -$262,427.56

Bid Items & Bid Tabulations

79 Total 0 of 79
HIDALGO  |  FM 492  |  PHARR  |  0862-01-057  |  11/03/2022  |  $2,066,856.82  |  BR 2023(199)  |  BRIDGE REPL  |  159 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS CORDIA CONSTRUCTION, LLC
LUCANIA CONSTRUCTION LLC
FOREMOST PAVING, INC.
IOC COMPANY, LLC
ARANDA BROTHERS CONSTRUCTION CO., INC.
PREPARING ROW
STA 14.550 $2,000.000 $1,000.000 $900.000 $2,250.000 $8,500.000 $15,000.000
REMOVING CONC (RIPRAP)
SY 94.000 $20.000 $12.000 $36.000 $10.000 $50.000 $10.000
REMOVING STAB BASE & ASPH PAV (0-6")
SY 3,892.000 $3.970 $3.000 $12.000 $6.000 $10.000 $12.000
EXCAVATION (ROADWAY)
CY 1,320.000 $20.000 $6.000 $20.000 $13.600 $20.000 $20.000
EXCAVATION (CHANNEL)
CY 58.000 $40.000 $20.000 $100.000 $25.000 $150.000 $25.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,115.000 $20.000 $4.000 $35.000 $18.500 $20.000 $35.000
FURNISHING AND PLACING TOPSOIL (4")
SY 6,053.000 $1.290 $3.000 $5.000 $6.500 $3.000 $10.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,381.000 $0.500 $1.000 $0.750 $0.700 $0.650 $2.000
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 2,772.000 $0.210 $1.000 $0.750 $0.700 $0.650 $2.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 5,153.000 $0.410 $1.000 $0.750 $0.700 $0.650 $2.000
VEGETATIVE WATERING
MG 167.500 $32.000 $30.000 $80.000 $55.000 $95.000 $105.000
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 78.000 $1.400 $5.000 $5.000 $5.000 $5.000 $35.000
PROOF ROLLING
HR 8.000 $115.000 $74.000 $60.000 $100.000 $50.000 $90.000
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
CY 1,744.000 $40.000 $45.000 $60.000 $45.000 $75.000 $90.000
REWORK BS MTL (TY A) (6") (ORD COMP)
SY 2,200.000 $6.000 $2.000 $9.000 $5.000 $10.000 $15.000
LIME (HYDRATED LIME (SLURRY))
TON 90.000 $190.000 $290.000 $430.000 $300.000 $245.000 $450.000
LIME TRT (MIX EXST MATL&NEW BASE(12")
SY 5,521.000 $8.000 $2.000 $3.500 $8.000 $6.000 $7.000
CEMENT
TON 64.000 $193.000 $190.000 $270.000 $205.000 $200.000 $285.000
CEMENT TREAT (NEW BASE)(11")
SY 5,521.000 $6.000 $2.000 $3.500 $7.500 $6.000 $35.000
PRIME COAT (MC-30)
GAL 1,105.000 $7.000 $4.000 $15.000 $8.000 $10.000 $12.000
ASPH (TIER II)
GAL 2,486.000 $7.000 $4.000 $12.000 $14.000 $10.000 $15.000
AGGR (TY-D GR-4P)(SAC-B)
CY 45.000 $150.000 $146.000 $300.000 $72.000 $750.000 $185.000
CEM STABIL BKFL
CY 138.000 $135.000 $64.000 $190.000 $110.000 $150.000 $130.000
SHEET PILING (PZ - 27)
SF 3,081.000 $110.000 $64.000 $60.000 $80.000 $115.000 $70.000
DRILL SHAFT (24 IN)
LF 340.000 $181.000 $275.000 $370.000 $220.000 $236.680 $450.000
DRILL SHAFT (36 IN)
LF 360.000 $310.000 $344.000 $400.000 $470.000 $290.550 $475.000
CL C CONC (ABUT)
CY 84.300 $1,800.000 $831.000 $1,400.000 $1,400.000 $2,000.000 $1,300.000
REINF CONC SLAB
SF 3,220.000 $21.000 $35.000 $32.000 $26.000 $45.000 $28.000
REINF CONC SLAB (SLAB BEAM)
SF 1,610.000 $17.410 $37.000 $35.000 $23.000 $40.000 $23.000
PRESTR CONC SLAB BEAM (5SB12)
LF 310.500 $200.000 $298.000 $240.000 $185.000 $300.000 $290.000
PRESTR CONC GIRDER (TX28)
LF 416.890 $200.000 $400.000 $225.000 $195.000 $265.000 $250.000
RIPRAP (CONC)(5 IN)
CY 39.000 $355.000 $648.000 $650.000 $1,100.000 $1,250.000 $575.000
RIPRAP (CONC) (CL A )
CY 22.000 $600.000 $657.000 $630.000 $1,400.000 $1,250.000 $575.000
RIPRAP (MOW STRIP)(4 IN)
CY 33.000 $514.000 $724.000 $630.000 $1,200.000 $1,250.000 $750.000
STR STEEL (MISC NON - BRIDGE)
LB 275.900 $11.000 $28.000 $32.000 $25.000 $50.000 $25.000
RAIL (TY SSTR)
LF 266.000 $270.000 $172.000 $150.000 $120.000 $200.000 $150.000
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 186.000 $120.000 $179.000 $170.000 $150.000 $175.000 $200.000
RC PIPE (CL III)(24 IN)
LF 172.000 $115.000 $76.000 $110.000 $120.000 $225.000 $120.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $5,560.000 $5,561.000 $7,800.000 $7,000.000 $7,500.000 $4,850.000
INL(CMP)(PAZD-CZ)(FG)(3FTX3FT-3FTX3FT)
EA 2.000 $6,800.000 $4,447.000 $4,800.000 $7,000.000 $7,000.000 $3,750.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $1,500.000 $1,617.000 $2,200.000 $1,600.000 $4,000.000 $1,850.000
REMOV STR (INLET)
EA 1.000 $738.000 $1,697.000 $1,500.000 $800.000 $1,500.000 $750.000
REMOV STR (PIPE)
LF 154.000 $20.000 $8.000 $20.000 $15.000 $25.000 $25.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $25,000.000 $38,633.000 $25,000.000 $45,000.000 $75,000.000 $45,850.000
MOBILIZATION
LS 1.000 $147,337.000 $131,650.000 $138,000.000 $192,000.000 $275,000.000 $295,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $3,500.000 $4,000.000 $4,750.000 $4,000.000 $550.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 72.000 $41.000 $65.000 $80.000 $65.000 $65.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 72.000 $24.000 $20.000 $20.000 $20.000 $20.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $26.000 $21.000 $20.000 $45.000 $43.400 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $8.000 $10.000 $6.000 $25.000 $26.600 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,528.000 $3.300 $4.000 $4.900 $5.000 $4.150 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,528.000 $1.300 $1.000 $1.500 $2.000 $1.250 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 96.000 $5.000 $10.000 $12.000 $10.000 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 96.000 $1.240 $3.000 $2.500 $3.000 $2.500 $2.000
DRIVEWAYS (ACP)
SY 505.000 $60.000 $36.000 $55.000 $98.000 $100.000 $65.000
MTL W-BEAM GD FEN (STEEL POST)
LF 350.000 $60.000 $35.000 $40.000 $45.000 $45.000 $50.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,360.000 $2,595.000 $800.000 $2,200.000 $2,170.490 $2,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,447.000 $1,510.000 $2,500.000 $1,950.000 $1,935.490 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 1,036.000 $2.380 $3.000 $3.000 $2.500 $3.000 $15.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,397.000 $3,555.000 $3,900.000 $3,500.000 $3,449.210 $3,750.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $279.000 $275.000 $325.000 $350.000 $349.210 $700.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
EA 4.000 $20,000.000 $15,191.000 $18,000.000 $15,700.000 $15,690.490 $27,500.000
WIRE FENCE (TY B)
LF 165.000 $16.000 $39.000 $45.000 $25.000 $24.490 $20.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $215.000 $280.000 $400.000 $330.000 $325.490 $400.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $750.000 $755.000 $800.000 $1,225.000 $1,221.490 $850.000
REMOVE SM RD SN SUP&AM
EA 1.000 $94.000 $85.000 $200.000 $325.000 $321.490 $650.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $55.000 $20.000 $7.000 $20.000 $19.490 $95.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $65.000 $27.000 $15.000 $30.000 $29.490 $35.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 6.000 $91.500 $59.000 $65.000 $60.000 $59.490 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $75.000 $68.000 $35.000 $80.000 $79.490 $85.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 485.000 $4.480 $5.000 $8.000 $5.000 $4.500 $4.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,910.000 $0.310 $1.000 $1.500 $1.000 $1.000 $4.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 160.000 $0.350 $3.000 $2.250 $3.000 $3.000 $5.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,640.000 $0.330 $2.000 $1.500 $1.500 $1.500 $4.000
REFL PAV MRKR TY II-A-A
EA 29.000 $3.260 $10.000 $11.500 $10.000 $10.000 $85.000
SP MIXES SP-D SAC-A PG76-22
TON 906.000 $180.000 $140.000 $145.000 $133.000 $200.000 $190.000
BONDING COURSE
GAL 1,105.000 $6.000 $6.000 $15.000 $5.000 $10.000 $13.500
GEOGRID BASE REINFORCEMENT (TY II)
SY 5,611.000 $2.500 $2.000 $2.500 $4.100 $4.000 $20.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 56.000 $80.000 $65.000 $50.000 $425.000 $100.000 $280.000
Totals: $2,066,856.820 $1,917,663.500 $2,174,193.750 $2,244,245.350 $2,889,271.440 $3,151,699.000