HIDALGO FM 2221 (0669-03-029)
Items: 78
County: HIDALGO
Length: N/A
Highway: FM 2221
District: PHARR
Control Number: 0669-03-029
DBE Goal: N/A
Project: STP 2B23(014)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $777,963.12
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
HECTOR SILLER
JESUS NORIEGA
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$777,963.12 | |||
| $802,713.95 |
3.18%
$24,750.83
|
|||
| $823,689.12 |
5.88%
$45,726.00
|
2.61%
$20,975.17
|
||
| $913,254.97 |
17.39%
$135,291.85
|
13.77%
$110,541.02
|
-10.87%
-$89,565.85
|
|
| $958,139.32 |
23.16%
$180,176.20
|
19.36%
$155,425.37
|
-4.91%
-$44,884.35
|
E
Engineer's Estimate
$777,963.12
$802,713.95
Over/Under Est:
3.18%
$24,750.83
$823,689.12
Over/Under Est:
5.88%
$45,726.00
Amt Left:
2.61%
$20,975.17
$913,254.97
Over/Under Est:
17.39%
$135,291.85
Amt Left:
13.77%
$110,541.02
Delta:
-10.87%
-$89,565.85
$958,139.32
Over/Under Est:
23.16%
$180,176.20
Amt Left:
19.36%
$155,425.37
Delta:
-4.91%
-$44,884.35
| Subcontractor | Percentage | Amount |
|---|---|---|
| PAVEMENT MARKINGS INC. | 5.25% | $42,142.48 |
| G & E ESCOBEDO CONSTRUCTION, INC. | 5.00% | $40,135.70 |
| RIO GRANDE CONSTRUCTORS AND CONSTRUCTION MANAGEMENT LLC | 4.67% | $37,486.74 |
| MUNOZ FOUNDATION DRILLING, INC. | 2.28% | $18,301.88 |
| Total: | 17.20% | $138,066.80 |
Bid Items & Bid Tabulations
78
Total
0 of 78