REMOVING CONCRETE(MOW STRIP)
|
LF
|
7,514.000
|
$6.080
|
$4.000
|
$7.000
|
|
|
BACKFILL (TY A)
|
STA
|
854.000
|
$115.000
|
$300.000
|
$200.000
|
|
|
FURNISHING AND PLACING TOPSOIL
|
CY
|
100.000
|
$28.180
|
$35.000
|
$40.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
13,433.000
|
$0.150
|
$0.230
|
$0.250
|
|
|
DRILL SEEDING (PERM) (URBAN) (SANDY)
|
SY
|
15,033.000
|
$0.270
|
$0.230
|
$0.250
|
|
|
VEGETATIVE WATERING
|
MG
|
2,000.000
|
$34.040
|
$15.000
|
$40.000
|
|
|
PLANE ASPH CONC PAV (1.5")
|
SY
|
535,934.000
|
$1.500
|
$1.000
|
$1.850
|
|
|
PLANE ASPH CONC PAV (1.5" TO 4")
|
SY
|
200.000
|
$1.650
|
$24.000
|
$15.000
|
|
|
PAV JT UNDERSEAL (24")
|
LF
|
2,524.000
|
$23.230
|
$30.000
|
$25.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
349.000
|
$395.060
|
$450.000
|
$475.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL7)
|
LF
|
2,524.000
|
$32.870
|
$35.000
|
$40.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,400,000.000
|
$725,000.000
|
$650,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
13.000
|
$4,500.000
|
$1,500.000
|
$5,150.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
5,520.000
|
$6.010
|
$2.000
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
5,520.000
|
$1.540
|
$0.500
|
$1.500
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
69,721.000
|
$0.210
|
$0.200
|
$0.500
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
12,440.000
|
$27.180
|
$25.490
|
$28.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$1,932.810
|
$2,235.490
|
$2,000.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
15.000
|
$1,479.520
|
$1,645.490
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
12,440.000
|
$2.380
|
$1.490
|
$1.900
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
15.000
|
$195.210
|
$195.490
|
$350.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$225.000
|
$195.490
|
$350.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
17.000
|
$3,312.190
|
$3,375.490
|
$2,900.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
17.000
|
$277.510
|
$195.490
|
$350.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
160.000
|
$36.110
|
$9.490
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
121.000
|
$18.000
|
$19.490
|
$25.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
27.000
|
$30.550
|
$19.490
|
$25.000
|
|
|
INSTL OM ASSM (OM-3L)(WFLX)GND)GND
|
EA
|
6.000
|
$66.760
|
$395.500
|
$400.000
|
|
|
INSTL OM ASSM (OM-3R)(WFLX)GND)GND
|
EA
|
10.000
|
$85.830
|
$395.490
|
$400.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
19,930.000
|
$3.000
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
20,497.000
|
$1.140
|
$1.400
|
$1.400
|
|
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
|
LF
|
3,684.000
|
$2.580
|
$2.800
|
$2.800
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
8,319.000
|
$4.140
|
$2.800
|
$3.000
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
51,951.000
|
$0.240
|
$0.380
|
$0.400
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
36,731.000
|
$0.580
|
$0.550
|
$0.600
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
104,321.000
|
$0.510
|
$0.480
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
98,060.000
|
$0.570
|
$0.480
|
$0.500
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)CNTST
|
LF
|
2,523.000
|
$14.810
|
$9.800
|
$10.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
8.000
|
$214.770
|
$290.000
|
$300.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
8.000
|
$250.000
|
$290.000
|
$300.000
|
|
PREFAB PAV MRK TY C (W) (EXIT GORE)
|
EA
|
12.000
|
$3,520.000
|
$220.000
|
$225.000
|
|
REFL PAV MRKR TY I-R
|
EA
|
169.000
|
$6.580
|
$9.800
|
$10.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
4,110.000
|
$4.500
|
$3.600
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
16,860.000
|
$0.380
|
$0.650
|
$0.910
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
244.000
|
$1.000
|
$1.250
|
$3.000
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
492.000
|
$1.360
|
$3.500
|
$3.200
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
1.000
|
$50.000
|
$175.000
|
$1,100.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
1.000
|
$60.000
|
$175.000
|
$1,100.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
16,860.000
|
$0.240
|
$0.100
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
244.000
|
$0.350
|
$0.200
|
$0.250
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
492.000
|
$0.600
|
$0.600
|
$0.650
|
|
|
STONE-MTRX-ASPH SMA-F SAC-A PG76-22
|
TON
|
45,822.000
|
$130.000
|
$137.000
|
$135.000
|
|
|
BONDING COURSE
|
GAL
|
37,515.000
|
$5.250
|
$3.500
|
$4.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$4,859.880
|
$3,500.000
|
$2,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
382.000
|
$19.950
|
$1.000
|
$30.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
382.000
|
$20.000
|
$2.000
|
$0.010
|
|
Totals: |
$9,897,571.670
|
$9,148,469.990
|
$9,606,464.020
|