HIDALGO IH 69C (0255-07-153)
Items: 54
County: HIDALGO
Length: 0.0000 MILES
Highway: IH 69C
District: PHARR
Control Number: 0255-07-153
DBE Goal: 0.0%
Project: F 2026(410)
Guaranty: $100,000.00
Time: 96 WORKING DAYS
Engineer's Estimate: $8,135,339.33
Date: 04/07/2026 (2 months ago)
Contract Number: 4263009
Type: PREVENTIVE MAINTENANCE
Project ID: A00209575
Contract Type: Federal
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
HIDALGO IH 69C (0255-07-153)
Project Name: N/A
Project: F 2026(410)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 2812
Limits To: FM 490
Project Description: OVERLAY
HIDALGO FM 1924 (1802-01-048)
Project Name: FM 1924 OVERLAY FY 2026
Project: F 2026(425)
Length: 0.0000 MILES
Project Type: OVERLAY
Limits From: FM 494
Limits To: FM 1926
Project Description: OVERLAY
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$8,135,339.33 | |||
| $8,784,921.94 |
7.98%
$649,582.61
|
|||
| $10,925,824.30 |
34.3%
$2,790,484.97
|
24.37%
$2,140,902.36
|
||
| $11,130,205.75 |
36.81%
$2,994,866.42
|
26.7%
$2,345,283.81
|
-1.87%
-$204,381.45
|
E
Engineer's Estimate
$8,135,339.33
1
Awarded
$8,784,921.94
Over/Under Est:
7.98%
$649,582.61
$10,925,824.30
Over/Under Est:
34.3%
$2,790,484.97
Amt Left:
24.37%
$2,140,902.36
$11,130,205.75
Over/Under Est:
36.81%
$2,994,866.42
Amt Left:
26.7%
$2,345,283.81
Delta:
-1.87%
-$204,381.45
Bid Items & Bid Tabulations
54
Total
0 of 54
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $15,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| Total: | $40,000.00 |