Show Job Controls
Bid Cobra

HIDALGO US 83 (0039-02-072)

Items: 14

County: HIDALGO
Length: N/A
Highway: US 83
District: PHARR
Control Number: 0039-02-072
DBE Goal: N/A
Project: STP 1902(312)HES
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $1,740,246.25
Date: 08/07/2019 (6 years ago)
Contract Number: N/A
Type: SFT - HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$1,740,246.25
$2,177,828.80
Over/Under Est: 25.14% $437,582.55
Over/Under Est: 32.61% $567,459.00
Amt Left: 5.96% $129,876.45

Bid Items & Bid Tabulations

14 Total 0 of 14
HIDALGO  |  US 83  |  PHARR  |  0039-02-072  |  08/07/2019  |  $1,740,246.25  |  STP 1902(312)HES  |  SFT - HAZARD ELIM & SAFETY  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CLORE EQUIPMENT LLC
SCR CIVIL CONSTRUCTION, LLC
BLADING
STA 306.000 $85.000 $150.320 $135.000
FURNISHING AND PLACING TOPSOIL (4")
SY 60,381.000 $2.000 $0.320 $2.200
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 60,381.000 $0.250 $0.380 $0.350
VEGETATIVE WATERING
MG 1,263.000 $12.500 $34.640 $74.000
RIPRAP (MOW STRIP)(4 IN)
CY 1,558.000 $420.000 $522.800 $712.000
MOBILIZATION
LS 1.000 $186,000.000 $206,893.730 $103,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,000.000 $10,825.000 $11,300.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 13,400.000 $5.000 $5.680 $5.300
BIODEG EROSN CONT LOGS (REMOVE)
LF 13,400.000 $1.500 $1.080 $1.250
CABLE BARRIER SYSTEM (TL-4)
LF 28,189.000 $14.000 $15.640 $12.300
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 70.000 $2,500.000 $4,713.940 $3,400.000
REMOVE CABLE BARRIER
LF 1,219.000 $4.500 $19.130 $9.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $12,990.000 $12,700.000
TMA (STATIONARY)
EA 1.000 $8,000.000 $48,712.500 $30,000.000
Totals: $1,740,246.250 $2,177,828.800 $2,307,705.250