REMOVING CONC (DRIVEWAYS)
|
SY
|
441.000
|
$11.000
|
$18.000
|
$13.150
|
|
|
REMOVING STAB BASE & ASPH PAV (18")
|
SY
|
70,237.000
|
$5.000
|
$5.500
|
$4.600
|
|
|
OBLITERATING ABANDONED ROAD
|
SY
|
1,312.000
|
$3.900
|
$5.000
|
$2.650
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
962.000
|
$7.000
|
$20.000
|
$5.200
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
652.000
|
$8.000
|
$20.000
|
$4.350
|
|
|
BACKFILL (TY A)
|
STA
|
230.000
|
$120.000
|
$150.000
|
$174.000
|
|
|
FURNISHING AND PLACING TOPSOIL
|
CY
|
50.000
|
$32.000
|
$30.000
|
$30.500
|
|
|
CELL FBR MLCH SEED(PERM)(URBAN)(SANDY)
|
SY
|
34,991.000
|
$0.310
|
$0.250
|
$0.310
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
34,991.000
|
$0.250
|
$0.250
|
$0.300
|
|
|
VEGETATIVE WATERING
|
MG
|
1,000.000
|
$19.000
|
$25.000
|
$34.500
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
1,842.000
|
$13.000
|
$1.000
|
$1.250
|
|
|
PROOF ROLLING
|
HR
|
36.000
|
$100.000
|
$65.000
|
$87.000
|
|
|
FL BS (CMP IN PLC)(TY E GR 4)(8")
|
SY
|
70,237.000
|
$10.000
|
$4.750
|
$6.950
|
|
|
CEMENT
|
TON
|
25.000
|
$156.000
|
$165.000
|
$168.000
|
|
|
CEMENT TREAT (SUBGRADE)(12")
|
SY
|
2,500.000
|
$2.300
|
$5.250
|
$3.300
|
|
|
ASPHALT STAB BASE (GR 4)(PG 64)
|
TON
|
22,828.000
|
$60.000
|
$73.500
|
$76.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
15,453.000
|
$3.200
|
$4.000
|
$4.600
|
|
|
SUPERPAVE MIXTURES SP-B SAC-B PG64-22
|
TON
|
17,617.000
|
$77.000
|
$68.000
|
$91.000
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
12,192.000
|
$95.000
|
$97.000
|
$126.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
9,898.000
|
$1.400
|
$4.000
|
$1.250
|
|
|
PLANE ASPH CONC PAV (4")
|
SY
|
8,955.000
|
$2.300
|
$5.000
|
$3.450
|
|
|
CEM STABIL BKFL
|
CY
|
41.000
|
$60.000
|
$300.000
|
$54.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
4.000
|
$130.000
|
$500.000
|
$202.000
|
|
|
RIPRAP (CONC)(CL B)(5 IN)
|
CY
|
25.000
|
$390.000
|
$550.000
|
$389.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
20.000
|
$377.000
|
$675.000
|
$377.000
|
|
|
RC PIPE (CL III)(18 IN)(SPL)
|
LF
|
658.000
|
$39.000
|
$48.000
|
$39.000
|
|
|
RC PIPE (CL III)(24 IN)(SPL)
|
LF
|
82.000
|
$47.000
|
$65.000
|
$51.500
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
30.000
|
$874.000
|
$850.000
|
$783.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,152.000
|
$1,800.000
|
$1,376.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
1.000
|
$1,200.000
|
$2,800.000
|
$3,283.000
|
|
|
REMOV STR (SET)
|
EA
|
18.000
|
$320.000
|
$240.000
|
$282.000
|
|
|
REMOV STR (PIPE)
|
LF
|
761.000
|
$15.000
|
$11.000
|
$9.050
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$823,000.000
|
$700,000.000
|
$900,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$5,000.000
|
$3,500.000
|
$3,500.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 2)
|
SY
|
2,028.000
|
$20.000
|
$16.000
|
$40.500
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
2,028.000
|
$7.000
|
$7.000
|
$5.750
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
4,015.000
|
$2.300
|
$3.000
|
$2.900
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
4,015.000
|
$0.650
|
$1.000
|
$0.600
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
6,760.000
|
$3.700
|
$5.000
|
$3.250
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
6,760.000
|
$0.650
|
$1.000
|
$0.600
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
6,690.000
|
$28.000
|
$38.000
|
$42.500
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
40,560.000
|
$5.000
|
$5.000
|
$4.600
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
6,690.000
|
$5.000
|
$9.000
|
$7.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
407.000
|
$42.000
|
$35.000
|
$52.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
443.000
|
$69.000
|
$54.000
|
$49.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
4,714.000
|
$29.000
|
$30.000
|
$32.500
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
38,560.000
|
$0.300
|
$0.300
|
$0.350
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
450.000
|
$21.000
|
$29.000
|
$25.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,700.000
|
$2,300.000
|
$1,715.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,140.000
|
$1,900.000
|
$960.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
325.000
|
$8.900
|
$9.000
|
$2.300
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$230.000
|
$410.000
|
$173.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$320.000
|
$460.000
|
$202.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$2,900.000
|
$3,500.000
|
$2,910.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$1,000.000
|
$675.000
|
$377.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
50.000
|
$1,300.000
|
$3,000.000
|
$870.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
7.000
|
$860.000
|
$2,100.000
|
$405.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
7.000
|
$16,000.000
|
$18,600.000
|
$10,200.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
19.000
|
$280.000
|
$260.000
|
$260.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
2.000
|
$280.000
|
$360.000
|
$295.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
3.000
|
$600.000
|
$450.000
|
$509.000
|
|
|
CONDT (PVC) (SCH 40) (1")
|
LF
|
90.000
|
$26.000
|
$15.000
|
$17.400
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
205.000
|
$28.000
|
$28.000
|
$32.500
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
48.000
|
$25.000
|
$95.000
|
$25.500
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
2.000
|
$540.000
|
$650.000
|
$690.000
|
|
|
IN SM RD SN SUP&AM (INST SIGN ONLY)
|
EA
|
48.000
|
$225.000
|
$385.000
|
$250.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
4.000
|
$105.000
|
$270.000
|
$85.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
48.000
|
$140.000
|
$125.000
|
$85.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
|
EA
|
26.000
|
$55.000
|
$150.000
|
$85.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 1(FLX)GND
|
EA
|
16.000
|
$86.000
|
$150.000
|
$105.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
16.000
|
$75.000
|
$150.000
|
$87.000
|
|
|
INSTL OM ASSM (OM-3L)(FLX)GND
|
EA
|
1.000
|
$200.000
|
$150.000
|
$240.000
|
|
|
INSTL OM ASSM (OM-3R)(FLX)GND
|
EA
|
1.000
|
$200.000
|
$150.000
|
$242.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
45.000
|
$20.000
|
$150.000
|
$63.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
5,360.000
|
$0.400
|
$0.450
|
$0.800
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
36.000
|
$3.990
|
$2.900
|
$5.800
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-C-R
|
EA
|
838.000
|
$3.450
|
$2.900
|
$4.650
|
|
|
WK ZN PAV MRK REMOV (W)4"(DOT)
|
LF
|
146.000
|
$1.350
|
$0.850
|
$0.820
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
78,130.000
|
$0.550
|
$0.600
|
$0.800
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
11,270.000
|
$1.300
|
$1.200
|
$1.750
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
40.000
|
$7.600
|
$8.800
|
$5.800
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
42.000
|
$200.000
|
$220.000
|
$110.000
|
|
|
WK ZN PAV MRK REMOV (W)(WORD)
|
EA
|
42.000
|
$229.000
|
$240.000
|
$145.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
98,223.000
|
$0.550
|
$0.600
|
$0.800
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,185.000
|
$1.400
|
$1.000
|
$1.150
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
140.000
|
$1.500
|
$1.000
|
$1.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
3,710.000
|
$1.500
|
$1.400
|
$1.200
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
555.000
|
$5.600
|
$8.800
|
$3.500
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
6,290.000
|
$0.350
|
$0.450
|
$0.550
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
26,292.000
|
$0.300
|
$0.450
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
210.000
|
$0.300
|
$0.600
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
25,066.000
|
$0.300
|
$0.450
|
$0.550
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
25.000
|
$200.000
|
$220.000
|
$203.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
25.000
|
$265.000
|
$260.000
|
$308.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
10.000
|
$4.000
|
$3.800
|
$5.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
56.000
|
$3.430
|
$3.800
|
$5.500
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
505.000
|
$4.000
|
$3.800
|
$5.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
41,151.000
|
$0.500
|
$0.600
|
$0.750
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
1,625.000
|
$0.600
|
$1.200
|
$1.750
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
11.000
|
$60.000
|
$60.000
|
$29.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
11.000
|
$60.000
|
$60.000
|
$41.000
|
|
|
TEMP TRAF SIGNALS
|
EA
|
1.000
|
$8,000.000
|
$3,250.000
|
$3,710.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
|
LF
|
750.000
|
$2.220
|
$2.200
|
$2.550
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
320.000
|
$2.520
|
$2.400
|
$2.750
|
|
|
VEH LP DETECT (SAWCUT)
|
LF
|
828.000
|
$16.000
|
$12.000
|
$14.000
|
|
|
POTHOLE REPAIR (STANDARD)
|
SY
|
200.000
|
$42.000
|
$140.000
|
$98.750
|
|
|
DITCH CLEANING AND RESHAPING (FOOT)
|
LF
|
24,757.000
|
$5.000
|
$2.870
|
$2.550
|
|
|
NO. OF WORKING DAYS
|
$/D
|
2,710.000
|
$231.000
|
$190.000
|
$215.000
|
|
|
BIRD EXCLUSION METHOD
|
SF
|
2,000.000
|
$4.200
|
$3.000
|
$1.150
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$13,500.000
|
$3,575.000
|
$3,190.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
64.000
|
$240.000
|
$75.000
|
$290.000
|
|
Totals: |
$8,135,943.680
|
$8,019,896.840
|
$9,001,396.630
|