HENDERSON SH0019 (6485-92-001)

Items: 48

County: HENDERSON
Length: 0.0100 MILES
Highway: SH0019
District: TYLER
Control Number: 6485-92-001
DBE Goal: N/A
Project: RMC - A00216167
Guaranty: $14,000.00
Time: 730 CALENDAR DAYS
Engineer's Estimate: $683,580.00
Date: 07/08/2025 (11 months ago)
Contract Number: 7251001
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00216167
Project Description: FOR THE PURPOSE OF REPAIRING GUARDRAIL ELEMENTS IN HENDERSON AND ANDERSON COUNTIES.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
2709 W FRONT ST, TYLER, TX 75702
DANNY HENDERSON
EDUARDO CASTANEDA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$683,580.00
$573,272.00
Over/Under Est: -16.14% -$110,308.00
$617,810.00
Over/Under Est: -9.62% -$65,770.00
Amt Left: 7.77% $44,538.00
$805,980.00
Over/Under Est: 17.91% $122,400.00
Amt Left: 40.59% $232,708.00
Delta: -30.46% -$188,170.00

Bid Items & Bid Tabulations

48 Total 0 of 48
HENDERSON  |  SH0019  |  TYLER  |  6485-92-001  |  07/08/2025  |  $683,580.00  |  RMC - A00216167  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BK FIELD OPERATIONS LLC
RHINO EQUITY, LLC
CATOCON, INC.
REMOV CONC (RIPRAP)
SY 30.000 $150.000 $80.000 $15.000 $50.000
CONC STR REPAIR (STANDARD)
SF 15.000 $250.000 $200.000 $300.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $600.000 $300.000 $100.000 $500.000
MOBILIZATION (CALLOUT)
EA 30.000 $200.000 $1.000 $1.000 $500.000
TMA (STATIONARY)
DAY 100.000 $300.000 $1.000 $700.000 $300.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $35.000 $34.000 $23.000 $50.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 25.000 $50.000 $100.000 $40.000 $100.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,000.000 $2,000.000 $1,700.000 $500.000
MTL BEAM GD FEN TRANS (T101)
EA 1.000 $800.000 $1,200.000 $1,500.000 $1,500.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 2,000.000 $10.000 $4.000 $1.000 $4.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 25.000 $20.000 $30.000 $50.000 $1.000
TRANSITION ADJUSTMENT
EA 1.000 $10.000 $2,000.000 $1,500.000 $1.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,500.000 $1,250.000 $1,200.000 $2,100.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 150.000 $80.000 $67.000 $60.000 $40.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 25.000 $100.000 $300.000 $800.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $3.000 $1.000 $2.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $250.000 $100.000 $100.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,000.000 $3,000.000 $3,000.000 $2,500.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 2.000 $500.000 $1,000.000 $1,000.000 $1.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 1.000 $2,000.000 $1,000.000 $1,000.000 $2,500.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 7,000.000 $26.000 $14.000 $12.000 $37.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 25.000 $45.000 $250.000 $100.000 $100.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 15.000 $50.000 $250.000 $610.000 $50.000
REPLACE TIMBER POST W/O CONC FND
EA 350.000 $75.000 $100.000 $40.000 $49.000
REPLACE TIMBER POST W/ CONC FND
EA 50.000 $100.000 $250.000 $100.000 $60.000
REPLACE STEEL POST W/ CONC FND
EA 50.000 $100.000 $250.000 $60.000 $90.000
REALIGN POSTS
EA 400.000 $22.000 $1.000 $5.000 $25.000
REPLACE TERMINAL ANCHOR POSTS
EA 2.000 $100.000 $1.000 $100.000 $50.000
REM OBSOLETE GET & REPL W/ SGT
EA 60.000 $3,600.000 $3,900.000 $4,000.000 $4,500.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 12.000 $1,000.000 $1,550.000 $1,285.000 $1,100.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 800.000 $35.000 $20.000 $36.000 $40.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 20.000 $100.000 $750.000 $250.000 $500.000
REPLACE BLOCKOUT
EA 250.000 $40.000 $6.000 $20.000 $20.000
REPAIR STEEL POST WITH BASE PLATE
EA 2.000 $150.000 $100.000 $800.000 $300.000
RESET SGT IMPACT HEAD
EA 20.000 $200.000 $200.000 $500.000 $100.000
REPLACE SGT OBJECT MARKER
EA 10.000 $30.000 $1.000 $275.000 $100.000
REPLACE SGT CABLE ANCHOR
EA 8.000 $90.000 $100.000 $120.000 $200.000
REPLACE SGT CABLE ASSEMBLY
EA 6.000 $100.000 $300.000 $200.000 $300.000
REPLACE SGT STRUT
EA 2.000 $75.000 $500.000 $150.000 $300.000
REPLACE HINGED TOP SGT POST (STEEL)
EA 50.000 $150.000 $100.000 $175.000 $200.000
REALIGN HINGED TOP SGT POST ((STEEL)
EA 50.000 $300.000 $1.000 $25.000 $200.000
REPLACE (NARROW QUAD)
EA 1.000 $25,000.000 $26,000.000 $26,000.000 $25,000.000
REPAIR (NARROW QUAD NOSE)
EA 10.000 $1,500.000 $1,000.000 $500.000 $1,500.000
REPAIR (NARROW QUAD BAY)
EA 2.000 $1,500.000 $2,000.000 $2,500.000 $5,000.000
REPAIR (T101)
LF 175.000 $50.000 $40.000 $40.000 $30.000
REPAIR (T6)
LF 5.000 $200.000 $90.000 $200.000 $700.000
REPAIR (STEEL POST W/CHANNEL IRON RAIL)
LF 25.000 $50.000 $200.000 $100.000 $100.000
MAINTENANCE SPEED LIMIT SIGNING
EA 5.000 $200.000 $1.000 $1,000.000 $500.000
Totals: $683,580.000 $573,272.000 $617,810.000 $805,980.000