HENDERSON US0175 (6477-10-001)

Items: 5

County: HENDERSON
Length: 0.0100 MILES
Highway: US0175
District: TYLER
Control Number: 6477-10-001
DBE Goal: N/A
Project: RMC - A00212932
Guaranty: $19,000.00
Time: 122 WORKING DAYS
Engineer's Estimate: $943,586.98
Date: 02/11/2025 (1 year ago) Changed
Contract Number: 2251001
Type: MOWING HIGHWAY RIGHT OF WAY
Project ID: A00212932
Contract Type: Waived
Project Description: MOWING HIGHWAY ROW IN HENDERSON COUNTY
Mail/Deliver Bids To: N/A
DANNY HENDERSON
EDUARDO CASTANEDA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$943,586.98
$736,319.81
Over/Under Est: -21.97% -$207,267.17
Over/Under Est: -7.27% -$68,591.14
Amt Left: 18.83% $138,676.03
Over/Under Est: 4.02% $37,969.95
Amt Left: 33.31% $245,237.12
Delta: -12.18% -$106,561.09
$1,058,656.84
Over/Under Est: 12.19% $115,069.86
Amt Left: 43.78% $322,337.03
Delta: -7.85% -$77,099.91
$1,119,616.78
Over/Under Est: 18.66% $176,029.80
Amt Left: 52.06% $383,296.97
Delta: -5.76% -$60,959.94
$1,233,944.66
Over/Under Est: 30.77% $290,357.68
Amt Left: 67.58% $497,624.85
Delta: -10.21% -$114,327.88
Subcontractor Percentage Amount
RENEGADE SITE SOLUTIONS, LLC 28.08% $206,758.60
SERVIN MOWING 20.04% $147,558.49
CEHAND SERVICES LLC 0.00% $0.00
Total: 48.12% $354,317.09

Bid Items & Bid Tabulations

5 Total 0 of 5
HENDERSON  |  US0175  |  TYLER  |  6477-10-001  |  02/11/2025  |  $943,586.98  |  RMC - A00212932  |  MOW HWY RIGHT OF WAY  |  122 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
12TWELVE ROAD AND BRIDGE LLC
CROSS PLUS CONSTRUCTION, LLC
A M FABRICATION INC.
ABESCAPE GROUP LLC
HX FARMS, INC.
CEHAND SERVICES LLC
MOBILIZATION (CALLOUT)
EA 4.000 $2,500.000 $1,000.000 $1.000 $1,000.000 $1.000 $1,000.000 $2,000.000
STRIP MOWING
AC 100.000 $40.000 $20.000 $1.000 $30.000 $25.000 $41.000 $49.000
SPOT MOWING
AC 50.000 $40.000 $20.000 $1.000 $30.000 $25.000 $41.000 $49.000
FULL - WIDTH MOWING
AC 18,187.980 $36.000 $29.099 $34.100 $35.500 $40.000 $41.000 $49.000
LITTER REMOVAL
AC 18,187.980 $15.000 $11.000 $14.000 $18.000 $18.000 $20.000 $18.000
Totals: $943,586.980 $736,319.810 $874,995.838 $981,556.930 $1,058,656.840 $1,119,616.780 $1,233,944.660