HENDERSON SH0019 (6435-20-001)

Items: 55

County: HENDERSON
Length: N/A
Highway: SH0019
District: TYLER
Control Number: 6435-20-001
DBE Goal: N/A
Project: RMC - 643520001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $680,927.20
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$680,927.20
$674,323.00
Over/Under Est: -0.97% -$6,604.20
$757,625.00
Over/Under Est: 11.26% $76,697.80
Amt Left: 12.35% $83,302.00
$877,670.00
Over/Under Est: 28.89% $196,742.80
Amt Left: 30.16% $203,347.00
Delta: -15.84% -$120,045.00

Bid Items & Bid Tabulations

55 Total 0 of 55
HENDERSON  |  SH0019  |  TYLER  |  6435-20-001  |  06/01/2023  |  $680,927.20  |  RMC - 643520001  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JCW CONSTRUCTION, LLC
RHINO EQUITY, LLC
CATOCON, INC.
REMOVING CONC (RIPRAP)
SY 30.000 $30.000 $250.000 $300.000 $100.000
CONC STR REPAIR (STANDARD)
SF 15.000 $300.000 $275.000 $300.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $400.000 $100.000 $400.000 $500.000
MOBILIZATION (CALLOUT)
EA 30.000 $400.000 $1.000 $400.000 $300.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $40.000 $35.000 $40.000 $40.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 25.000 $30.000 $200.000 $30.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,100.000 $2,000.000 $1,100.000 $1,500.000
MTL BEAM GD FEN TRANS (T101)
EA 1.000 $800.000 $1,500.000 $800.000 $900.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 2,000.000 $20.000 $5.000 $20.000 $3.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 25.000 $10.000 $75.000 $10.000 $1.000
TRANSITION ADJUSTMENT
EA 1.000 $100.000 $500.000 $100.000 $1.000
SHORT RADIUS
LF 25.000 $68.000 $50.000 $25.000 $40.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,300.000 $1,350.000 $1,300.000 $1,500.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 150.000 $40.000 $50.000 $40.000 $30.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 25.000 $20.000 $150.000 $20.000 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $6.000 $3.000 $6.000 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $250.000 $100.000 $250.000 $1.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 1.000 $250.000 $1,500.000 $250.000 $1.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 2.000 $2,750.000 $1,000.000 $2,750.000 $2,500.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,000.000 $300.000 $1,000.000 $1.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 7,000.000 $25.000 $20.000 $25.000 $37.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 25.000 $40.000 $50.000 $40.000 $40.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 5.000 $50.000 $200.000 $50.000 $100.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 350.000 $55.000 $75.000 $200.000 $71.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 50.000 $100.000 $75.000 $100.000 $86.000
REPAIR STEEL POST WITH BASE PLATE
EA 2.000 $400.000 $500.000 $400.000 $650.000
REALIGN POSTS
EA 400.000 $20.000 $22.500 $20.000 $10.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 100.000 $20.000 $20.000 $20.000 $24.000
REMOVE & REPLACE BLOCKOUT
EA 250.000 $20.000 $20.000 $20.000 $40.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 800.000 $40.000 $30.000 $40.000 $50.000
REPLACE TERMINAL ANCHOR POSTS
EA 2.000 $300.000 $100.000 $300.000 $350.000
REPLACE HINGED TOP SGT STEEL POST
EA 50.000 $300.000 $200.000 $200.000 $200.000
RESET HINGED TOP SGT STL POST
EA 50.000 $80.000 $20.000 $200.000 $50.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 60.000 $3,750.000 $4,000.000 $3,750.000 $4,350.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 12.000 $1,000.000 $600.000 $1,000.000 $1,500.000
REM & RESET SGT IMPACT HEAD
EA 20.000 $200.000 $100.000 $200.000 $200.000
REPLACE SGT CABLE ASSEMBLY
EA 6.000 $100.000 $1.000 $100.000 $160.000
REPLACE SGT CABLE ANCHOR
EA 8.000 $100.000 $1.000 $100.000 $160.000
REPLACE SGT STRUT
EA 2.000 $100.000 $1.000 $100.000 $150.000
REPLACE SGT OBJECT MARKER
EA 10.000 $100.000 $300.000 $100.000 $25.000
REPLACE SINGLE GDRAIL TERM POST(WOOD)
EA 20.000 $56.000 $50.000 $200.000 $100.000
REPLACE SINGLE GDRAIL TERM POST(STEEL)
EA 20.000 $222.860 $200.000 $200.000 $225.000
REMOVE AND REPLACE (TRACC)
EA 2.000 $4,000.000 $20,000.000 $10,000.000 $25,000.000
REPAIR (TRACC)
EA 1.000 $2,500.000 $3,000.000 $2,500.000 $6,500.000
REPAIR (WIDE TRACC)
EA 2.000 $5,000.000 $7,500.000 $5,000.000 $5,500.000
REPAIR (NARROW QUAD)
EA 1.000 $500.000 $3,500.000 $500.000 $3,000.000
REPAIR (QUAD) (N) (BAY)
EA 2.000 $800.000 $3,500.000 $800.000 $1,000.000
REMOVE AND REPLACE (FASTRACC)
EA 2.000 $9,000.000 $1.000 $9,000.000 $29,500.000
REPAIR (FASTRACC) (BAY)
EA 6.000 $600.000 $1,500.000 $600.000 $900.000
QUAD(N)(BAY)NOSE ASSMBLY(REMOVE&REPLAC)
EA 10.000 $500.000 $500.000 $500.000 $500.000
REPAIR (STEEL POST W/ W-BEAM - T101)
LF 175.000 $30.000 $50.000 $30.000 $40.000
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 5.000 $100.000 $200.000 $100.000 $100.000
REPAIR(STEEL POST W/ CHANNEL IRON RAIL)
LF 25.000 $40.000 $50.000 $40.000 $100.000
TMA (STATIONARY)
DAY 75.000 $250.000 $500.000 $300.000 $250.000
INST/REMV WKZN SPEED REDUCTION SIGNS
EA 5.000 $350.000 $1,000.000 $300.000 $800.000
Totals: $680,927.200 $674,323.000 $757,625.000 $877,670.000