HENDERSON SH 31 (0163-03-053)

Items: 77

County: HENDERSON
Length: 1.0000 MILES
Highway: SH 31
District: TYLER
Control Number: 0163-03-053
DBE Goal: 0.0%
Project: F 2026(130)
Guaranty: $100,000.00
Time: 170 WORKING DAYS
Engineer's Estimate: $19,578,202.80
Date: 12/02/2025 (6 months ago)
Contract Number: 12253008
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00197754
Contract Type: Federal
Project Description: FY 2026 SEAL COAT
Mail/Deliver Bids To: N/A
LANCE POMYKAL
MANUEL Y ENRIQUEZ
JUANITA DANIELSWEST
STEVEN SWINDELL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$19,578,202.80
$19,658,258.22
Over/Under Est: 0.41% $80,055.42
Over/Under Est: 6.68% $1,307,548.53
Amt Left: 6.24% $1,227,493.11
$21,889,996.49
Over/Under Est: 11.81% $2,311,793.69
Amt Left: 11.35% $2,231,738.27
Delta: -4.81% -$1,004,245.16
$22,353,987.16
Over/Under Est: 14.18% $2,775,784.36
Amt Left: 13.71% $2,695,728.94
Delta: -2.12% -$463,990.67

Bid Items & Bid Tabulations

77 Total 0 of 77
HENDERSON  |  SH 31  |  TYLER  |  0163-03-053  |  12/02/2025  |  $19,578,202.80  |  F 2026(130)  |  HAZARD ELIM & SAFETY  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
D. I. J. CONSTRUCTION, INC.
CDM HOLDINGS
CK NEWBERRY, LLC
ASPH (AC-20-5TR OR AC-20XP)
TON 8,476.250 $570.000 $542.070 $600.000 $579.500 $690.000
AGGR (TY-PD, GR-3)(SAC-A)
CY 17,241.000 $155.000 $165.060 $211.000 $185.000 $225.000
AGGR (TY-PD, GR-4)(SAC-A)
CY 8,756.000 $156.000 $161.650 $206.000 $185.000 $225.000
AGGR (TY-PD OR PL, GR-3)
CY 13,434.000 $142.000 $127.770 $180.000 $150.000 $200.000
MOBILIZATION
LS 1.000 $2,420,855.700 $3,407,689.000 $2,000,000.000 $3,500,000.000 $1,200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $40,000.000 $40,000.000 $35,000.000 $100,000.000 $150,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 73.000 $100.000 $0.010 $300.000 $1,000.000 $1.000
TMA (STATIONARY)
DAY 99.000 $0.010 $0.010 $100.000 $500.000 $1.000
TMA (MOBILE OPERATION)
DAY 125.000 $0.010 $0.010 $1,940.000 $500.000 $1.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 87,789.000 $0.100 $0.300 $0.320 $0.300 $0.320
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 142,153.000 $0.300 $0.300 $0.380 $0.300 $0.380
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 40,951.000 $0.010 $0.010 $0.010 $1.000 $0.550
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 127,202.000 $0.010 $0.010 $0.010 $1.000 $0.580
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,279.000 $1.000 $0.200 $3.000 $0.650 $1.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 408.000 $1.000 $0.200 $3.000 $1.750 $2.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 36,139.000 $0.800 $0.800 $0.850 $0.850 $0.850
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
LF 853.000 $5.000 $5.000 $6.250 $6.250 $5.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 8,609.000 $2.000 $4.000 $8.000 $8.000 $6.000
RE PM TY II (W) 6" (BRK)
LF 51,599.000 $0.170 $0.140 $0.170 $0.170 $0.180
RE PM TY II (W) 6" (DOT)
LF 152.000 $0.200 $0.140 $3.000 $0.500 $1.000
RE PM TY II (W) 6" (SLD)
LF 2,092,543.000 $0.170 $0.130 $0.150 $0.150 $0.160
RE PM TY II (W) 8" (DOT)
LF 858.000 $0.300 $0.300 $3.000 $0.350 $1.000
RE PM TY II (W) 8" (SLD)
LF 29,959.000 $0.250 $0.300 $0.350 $0.350 $0.300
RE PM TY II (W) 18" (SLD)
LF 859.000 $5.000 $5.000 $6.000 $6.000 $2.500
RE PM TY II (W) 24" (SLD)
LF 14,393.000 $2.000 $4.000 $6.000 $6.000 $3.000
RE PM TY II (W) (ARROW)
EA 312.000 $120.000 $100.000 $135.000 $135.000 $75.000
RE PM TY II (W) (DBL ARROW)
EA 17.000 $150.000 $120.000 $175.000 $175.000 $120.000
RE PM TY II (W) (LN REDUCT ARW)
EA 4.000 $250.000 $200.000 $250.000 $250.000 $200.000
RE PM TY II (W) (WORD)
EA 136.000 $130.000 $100.000 $135.000 $135.000 $110.000
RE PM TY II (W) (RR XING)
EA 13.000 $400.000 $400.000 $300.000 $300.000 $350.000
RE PM TY II (W) 18" (YLD TRI)
EA 19.000 $52.950 $15.000 $30.000 $30.000 $20.000
RE PM TY II (W) 36" (YLD TRI)
EA 159.000 $20.000 $20.000 $30.000 $30.000 $25.000
RE PM TY II (Y) 6" (BRK)
LF 147,600.000 $0.170 $0.140 $0.170 $0.170 $0.180
RE PM TY II (Y) 6" (SLD)
LF 1,911,651.000 $0.170 $0.130 $0.160 $0.160 $0.160
RE PM TY II (W)(ACC PRK)(SYMBOL ONLY)
EA 1.000 $250.000 $500.000 $150.000 $150.000 $350.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 1,773,500.000 $0.750 $0.640 $0.640 $0.640 $0.570
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 47,957.000 $0.750 $0.640 $1.050 $1.050 $0.570
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 922,622.000 $0.750 $0.640 $0.150 $0.150 $0.570
PAVEMENT SLER 6"
LF 102,699.000 $1.000 $0.300 $0.200 $0.200 $0.150
PAVEMENT SLER 8"
LF 6,610.000 $1.000 $1.000 $0.300 $0.300 $0.300
PAVEMENT SLER 24"
LF 1,148.000 $3.000 $2.000 $2.000 $2.000 $2.500
PAVEMENT SLER (ARROW)
EA 25.000 $70.000 $50.000 $50.000 $50.000 $75.000
PAVEMENT SLER (WORD)
EA 16.000 $80.000 $50.000 $50.000 $50.000 $100.000
PAVEMENT SLER (DBL ARROW)
EA 1.000 $35.000 $200.000 $50.000 $50.000 $200.000
PAVEMENT SLER (YLD TRI)
EA 56.000 $30.000 $25.000 $15.000 $15.000 $20.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 125,052.000 $0.500 $0.440 $0.550 $0.620 $0.550
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 864,913.000 $0.500 $0.440 $0.540 $0.600 $0.500
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 152,468.000 $0.500 $0.440 $0.550 $0.620 $0.550
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 2,243,545.000 $0.500 $0.440 $0.540 $0.600 $0.550
PREFAB PM TY C (W)(ARROW)
EA 409.000 $220.000 $200.000 $210.000 $210.000 $210.000
PREFAB PM TY C (W)(DBL ARROW)
EA 3.000 $250.000 $220.000 $345.000 $345.000 $275.000
PREFAB PM TY C (W)(LN REDUCT ARROW)
EA 9.000 $350.000 $350.000 $450.000 $450.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 225.000 $250.000 $220.000 $240.000 $240.000 $238.000
PREFAB PM TY C (W)(RR XING)
EA 13.000 $400.000 $400.000 $550.000 $550.000 $555.000
PREFAB PM TY C (W)(18")(YLD TRI)
EA 6.000 $30.000 $9.000 $30.000 $30.000 $35.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 465.000 $35.000 $30.000 $45.000 $45.000 $40.000
PREFAB PM TY C (W)(BIKE ARROW)
EA 2.000 $300.000 $200.000 $250.000 $250.000 $100.000
PREFAB PM TY C (W)(BIKE SYMBOL)
EA 2.000 $300.000 $200.000 $300.000 $300.000 $200.000
REFL PAV MRKR TY I-C
EA 9,567.000 $4.500 $4.000 $4.000 $4.000 $4.000
REFL PAV MRKR TY II-A-A
EA 80,205.000 $4.500 $4.000 $3.500 $4.000 $3.500
ELIM EXT PM & MRKS (6")
LF 97,139.000 $0.700 $0.500 $0.400 $0.600 $0.550
ELIM EXT PM & MRKS (8")
LF 14,193.000 $1.500 $0.800 $0.650 $0.650 $0.700
ELIM EXT PM & MRKS (12")
LF 268.000 $5.000 $1.000 $2.000 $2.000 $2.000
ELIM EXT PM & MRKS (24")
LF 1,148.000 $7.000 $2.000 $4.000 $4.000 $2.000
ELIM EXT PM & MRKS (ARROW)
EA 25.000 $120.000 $80.000 $70.000 $70.000 $50.000
ELIM EXT PM & MRKS (DBL ARROW)
EA 1.000 $75.600 $80.000 $100.000 $100.000 $100.000
ELIM EXT PM & MRKS (WORD)
EA 16.000 $120.000 $100.000 $70.000 $70.000 $75.000
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 56.000 $30.000 $10.000 $20.000 $20.000 $15.000
ELIM EXT PM & MRKS (RUMBLE STRIP)
LF 895,182.000 $0.200 $0.200 $0.140 $0.140 $0.180
PAV SURF PREP FOR MRK (6")
LF 102,159.000 $0.010 $0.020 $0.010 $0.010 $0.020
PAV SURF PREP FOR MRK (8")
LF 6,332.000 $0.010 $0.020 $0.010 $0.010 $0.050
PAV SURF PREP FOR MRK (24")
LF 1,128.000 $0.010 $1.000 $0.250 $0.250 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 25.000 $0.010 $20.000 $20.000 $20.000 $15.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $21.530 $20.000 $20.000 $20.000 $25.000
PAV SURF PREP FOR MRK (WORD)
EA 16.000 $0.010 $20.000 $20.000 $20.000 $15.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 56.000 $0.010 $20.000 $5.000 $2.000 $15.000
FRICTIONAL ASPH SURF PRESERV TRTMT
SY 319,416.000 $1.480 $1.780 $1.780 $1.780 $2.150
Totals: $19,578,202.800 $19,658,258.218 $20,885,751.330 $21,889,996.485 $22,353,987.160