HAYS CR (0914-33-064)

Items: 46

County: HAYS
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-33-064
DBE Goal: N/A
Project: BR 1502(645)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $1,614,622.00
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,614,622.00
$1,535,478.50
Over/Under Est: -4.9% -$79,143.50
$1,627,956.40
Over/Under Est: 0.83% $13,334.40
Amt Left: 6.02% $92,477.90
$1,715,257.00
Over/Under Est: 6.23% $100,635.00
Amt Left: 11.71% $179,778.50
Delta: -5.36% -$87,300.60
Over/Under Est: 38.86% $627,501.75
Amt Left: 46.02% $706,645.25
Delta: -30.72% -$526,866.75

Bid Items & Bid Tabulations

46 Total 0 of 46
HAYS  |  CR  |  AUSTIN  |  0914-33-064  |  01/07/2022  |  $1,614,622.00  |  BR 1502(645)  |  BRIDGE MAINT  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN UNDERGROUND INCORPORATED
DAN WILLIAMS COMPANY
J3 COMPANY, LLC
AUSTIN ENGINEERING CO., INC.
PREPARING ROW
STA 4.400 $2,400.000 $3,000.000 $10,000.000 $7,500.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 6.000 $20.000 $180.000 $20.000 $75.000 $590.000
REMOVING CONC (CURB)
LF 16.000 $10.000 $70.000 $7.000 $25.000 $125.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 841.000 $10.000 $16.000 $2.500 $8.000 $10.500
EXCAVATION (ROADWAY)
CY 278.000 $25.000 $50.000 $20.000 $15.000 $43.000
EXCAVATION (CHANNEL)
CY 703.000 $25.000 $36.000 $28.000 $25.000 $43.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 469.000 $25.000 $20.000 $15.000 $15.000 $17.250
FURNISHING AND PLACING TOPSOIL (4")
SY 374.000 $3.000 $7.500 $4.000 $10.000 $15.500
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 374.000 $2.000 $1.250 $1.350 $2.000 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 187.000 $2.000 $4.500 $2.700 $3.000 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 187.000 $2.000 $4.500 $2.700 $3.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 374.000 $2.000 $2.000 $1.300 $2.000 $2.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 265.000 $60.000 $95.000 $72.000 $75.000 $95.000
CEM STABIL BKFL
CY 45.000 $150.000 $190.000 $200.000 $210.000 $265.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 2,500.000 $120.000 $20.000 $12.000 $55.000 $50.000
CL A CONC (CHANNEL LINING)
CY 207.000 $355.000 $310.000 $220.000 $250.000 $683.000
RETAINING WALL (CAST - IN - PLACE)
SF 400.000 $75.000 $145.000 $93.000 $60.000 $115.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 799.000 $150.000 $82.000 $220.000 $100.000 $270.000
RAIL (TY T223)
LF 552.000 $150.000 $170.000 $105.000 $180.000 $285.000
CONC BOX CULV (10 FT X 10 FT)
LF 408.000 $1,250.000 $1,600.000 $1,400.000 $1,555.000 $1,120.000
WINGWALL (PW - 1) (HW=12 FT)
EA 2.000 $40,000.000 $103,000.000 $125,000.000 $95,000.000 $250,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $30,000.000 $15,000.000 $8,000.000 $50,500.000 $40,000.000
REMOV STR (SMALL FENCE)
LF 100.000 $2.500 $5.000 $2.250 $5.000 $5.500
MOBILIZATION
LS 1.000 $120,000.000 $70,000.000 $160,000.000 $120,000.000 $85,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,000.000 $1,100.000 $3,000.000 $5,000.000 $8,100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 72.000 $30.000 $50.000 $24.000 $24.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 72.000 $10.000 $10.000 $20.000 $20.000 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 314.000 $3.000 $5.000 $3.500 $3.500 $8.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 314.000 $1.000 $1.000 $1.000 $1.000 $1.000
REMOVE METAL BEAM GUARD FENCE
LF 175.000 $3.000 $6.000 $2.000 $5.000 $6.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $7,000.000 $8,800.000 $5,500.000 $12,000.000 $13,500.000
WIRE FENCE (TY C)
LF 100.000 $20.000 $13.000 $7.000 $18.000 $15.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $500.000 $750.000 $680.000 $700.000 $750.000
REMOVE SM RD SN SUP&AM
EA 16.000 $100.000 $190.000 $110.000 $110.000 $120.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 9.000 $20.000 $32.000 $16.000 $25.000 $11.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 9.000 $75.000 $32.000 $48.000 $75.000 $76.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 2.000 $75.000 $90.000 $52.000 $75.000 $80.000
REFL PAV MRKR TY I-C
EA 44.000 $5.000 $29.000 $12.000 $10.000 $10.000
REFL PAV MRKR TY II-A-A
EA 44.000 $5.000 $29.000 $12.000 $10.000 $10.000
TRAFFIC BUTTON TY W
EA 132.000 $5.000 $19.000 $8.000 $10.000 $10.000
TRAFFIC BUTTON TY Y
EA 132.000 $5.000 $19.000 $8.000 $10.000 $10.000
D-GR HMA TY-D PG 76-22 (EXEMPT)
TON 259.000 $105.000 $140.000 $258.000 $220.000 $330.000
TEMP CONSTRUCTION ACCESS
LS 1.000 $50,000.000 $5,000.000 $25,000.000 $48,200.000 $80,000.000
INSTALL FTB
LF 500.000 $27.000 $43.000 $33.000 $32.000 $37.000
REMOVE FTB
LF 500.000 $8.000 $3.000 $2.500 $8.000 $26.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $10,000.000 $4,200.000 $7,750.000 $4,500.000 $7,500.000
Totals: $1,614,622.000 $1,535,478.500 $1,627,956.400 $1,715,257.000 $2,242,123.750