HASKELL US 380 (0360-04-033)
Items: 46
County: HASKELL
Length: N/A
Highway: US 380
District: ABILENE
Control Number: 0360-04-033
DBE Goal: 0.0%
Project: C 360-4-33
Guaranty: N/A
Time: 136 WORKING DAYS
Engineer's Estimate: $7,735,157.45
Date: 12/05/2023 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,735,157.45 | |||
| $7,148,853.18 |
-7.58%
-$586,304.27
|
|||
| $7,791,517.13 |
0.73%
$56,359.68
|
8.99%
$642,663.95
|
||
| $7,988,610.96 |
3.28%
$253,453.51
|
11.75%
$839,757.78
|
-2.53%
-$197,093.83
|
|
| $8,765,930.11 |
13.33%
$1,030,772.66
|
22.62%
$1,617,076.93
|
-9.73%
-$777,319.15
|
|
| $9,046,308.40 |
16.95%
$1,311,150.95
|
26.54%
$1,897,455.22
|
-3.20%
-$280,378.29
|
E
Engineer's Estimate
$7,735,157.45
1
Awarded
$7,148,853.18
Over/Under Est:
-7.58%
-$586,304.27
$7,791,517.13
Over/Under Est:
0.73%
$56,359.68
Amt Left:
8.99%
$642,663.95
$7,988,610.96
Over/Under Est:
3.28%
$253,453.51
Amt Left:
11.75%
$839,757.78
Delta:
-2.53%
-$197,093.83
$8,765,930.11
Over/Under Est:
13.33%
$1,030,772.66
Amt Left:
22.62%
$1,617,076.93
Delta:
-9.73%
-$777,319.15
$9,046,308.40
Over/Under Est:
16.95%
$1,311,150.95
Amt Left:
26.54%
$1,897,455.22
Delta:
-3.20%
-$280,378.29
| Subcontractor | Percentage | Amount |
|---|---|---|
| FLAT LINE, INC. | 4.02% | $287,383.90 |
| W. S. CONSTRUCTION COMPANY | 3.59% | $256,643.83 |
| DUSTIN ALLEN, INC. | 3.55% | $253,784.29 |
| SURFACE PREPARATION TECHNOLOGIES, LLC | 0.50% | $35,744.27 |
| CONTRACTORS SERVICE, LTD. | 0.44% | $31,454.95 |
| J. H. ODEN CONTRACTING COMPANY | 0.13% | $9,293.51 |
| Total: | 12.23% | $874,304.75 |