HARRISON US0059 (6442-52-001)

Items: 12

County: HARRISON
Length: N/A
Highway: US0059
District: ATLANTA
Control Number: 6442-52-001
DBE Goal: N/A
Project: RMC - 644252001
Guaranty: N/A
Time: 75 W
Engineer's Estimate: $187,650.00
Date: 06/14/2023 (2 years ago)
Contract Number: N/A
Type: TREE REMOVAL
Mail/Deliver Bids To: N/A
JASON DUPREE
CHARLOTTE ASLIN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$187,650.00
$142,028.00
Over/Under Est: -24.31% -$45,622.00
$175,431.00
Over/Under Est: -6.51% -$12,219.00
Amt Left: 23.52% $33,403.00
$194,969.00
Over/Under Est: 3.9% $7,319.00
Amt Left: 37.28% $52,941.00
Delta: -11.14% -$19,538.00
Over/Under Est: 6.35% $11,920.00
Amt Left: 40.51% $57,542.00
Delta: -2.36% -$4,601.00
Over/Under Est: 28.69% $53,832.00
Amt Left: 70.02% $99,454.00
Delta: -21.00% -$41,912.00
Over/Under Est: 33.22% $62,335.00
Amt Left: 76.01% $107,957.00
Delta: -3.52% -$8,503.00
Over/Under Est: 79.85% $149,845.05
Amt Left: 137.63% $195,467.05
Delta: -35.01% -$87,510.05

Bid Items & Bid Tabulations

12 Total 0 of 12
HARRISON  |  US0059  |  ATLANTA  |  6442-52-001  |  06/14/2023  |  $187,650.00  |  RMC - 644252001  |  TREE RMVL  |  75 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CEHAND SERVICES LLC
RHINO EQUITY, LLC
H. V. CAVER, INC.
RDA VEGETATION MANAGEMENT LLC
CROSS PLUS CONSTRUCTION, LLC
BA NEWTON'S ENTERPRISES LLC
ROAD SOLUTIONS L.L.C.
MOBILIZATION (CALLOUT)
EA 1.000 $500.000 $5,000.000 $1.000 $1.000 $4,500.000 $10,000.000 $22,500.000 $29,500.000
TREE REMOVAL (4" - 12" DIA)
EA 833.000 $100.000 $70.000 $100.000 $121.000 $90.000 $75.000 $75.000 $95.000
TREE REMOVAL (12" - 18" DIA)
EA 333.000 $100.000 $85.000 $110.000 $121.000 $125.000 $123.000 $250.000 $185.000
TREE REMOVAL (18" - 24" DIA)
EA 200.000 $120.000 $105.000 $75.000 $121.000 $135.000 $234.000 $250.000 $245.000
TREE REMOVAL (24" - 30" DIA)
EA 83.000 $200.000 $200.000 $200.000 $121.000 $200.000 $456.000 $150.000 $375.000
TREE REMOVAL (30" - 36" DIA)
EA 33.000 $250.000 $250.000 $200.000 $121.000 $325.000 $600.000 $100.000 $850.000
TREE REMOVAL (36" - 42" DIA)
EA 8.000 $300.000 $250.000 $300.000 $121.000 $500.000 $600.000 $250.000 $2,000.000
TREE REMOVAL (42" - 48" DIA)
EA 7.000 $400.000 $250.000 $300.000 $121.000 $700.000 $600.000 $100.000 $2,500.000
TREE REMOVAL (48" - 60" DIA)
EA 3.000 $500.000 $250.000 $300.000 $121.000 $800.000 $600.000 $70.000 $3,000.000
TREE REMOVAL (60" - 72" DIA)
EA 3.000 $500.000 $1.000 $300.000 $121.000 $1,200.000 $600.000 $100.000 $455.250
STUMP REMOVAL
EA 10.000 $100.000 $1.000 $100.000 $60.500 $50.000 $100.000 $30.000 $108.880
TMA (STATIONARY)
DAY 50.000 $250.000 $1.000 $200.000 $250.000 $175.000 $200.000 $250.000 $282.510
Totals: $187,650.000 $142,028.000 $175,431.000 $194,969.000 $199,570.000 $241,482.000 $249,985.000 $337,495.050