HARRISON FM 1997 (1919-02-037)

Items: 47

County: HARRISON
Length: N/A
Highway: FM 1997
District: ATLANTA
Control Number: 1919-02-037
DBE Goal: N/A
Project: STP 1702(400)
Guaranty: N/A
Time: 114 WORKING DAYS
Engineer's Estimate: $859,169.65
Date: 06/07/2017 (9 years ago)
Contract Number: N/A
Type: SIDEWALKS, CURB RAMPS AND RET WALL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$859,169.65
Over/Under Est: -4.16% -$35,733.00
Over/Under Est: 10.15% $87,225.58
Amt Left: 14.93% $122,958.58
Over/Under Est: 13.44% $115,487.00
Amt Left: 18.36% $151,220.00
Delta: -2.99% -$28,261.42
Over/Under Est: 16.31% $140,148.20
Amt Left: 21.36% $175,881.20
Delta: -2.53% -$24,661.20
$1,193,244.25
Over/Under Est: 38.88% $334,074.60
Amt Left: 44.91% $369,807.60
Delta: -19.41% -$193,926.40

Bid Items & Bid Tabulations

47 Total 0 of 47
HARRISON  |  FM 1997  |  ATLANTA  |  1919-02-037  |  06/07/2017  |  $859,169.65  |  STP 1702(400)  |  SIDEWALKS, CURB RAMPS AND RET WALL  |  114 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 6.940 $2,500.000 $1,500.000 $1,500.000 $5,000.000 $5,000.000 $5,000.000
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 2.000 $2,000.000 $3,000.000 $7,000.000 $1,500.000 $1,000.000 $1,500.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 10.000 $500.000 $250.000 $1,600.000 $800.000 $500.000 $1,000.000
REMOVING CONC (MEDIANS)
SY 158.000 $22.000 $28.000 $40.000 $20.000 $25.000 $20.000
REMOVING CONC (SIDEWALKS)
SY 220.000 $15.000 $30.000 $30.000 $15.000 $25.000 $20.000
REMOVING CONC (CURB)
LF 365.000 $10.000 $17.000 $9.000 $5.000 $10.000 $20.000
REMOVING CONC (CURB AND GUTTER)
LF 675.000 $15.000 $15.000 $14.000 $8.000 $10.000 $12.500
REMOVING CONC (RETAINING WALLS)
SY 7.000 $30.000 $150.000 $225.000 $125.000 $100.000 $100.000
EXCAVATION (ROADWAY)
CY 599.000 $7.000 $10.500 $15.000 $20.000 $25.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 455.000 $15.000 $15.000 $20.000 $25.000 $30.000 $35.000
BACKFILL (TY A)
STA 28.000 $350.000 $400.000 $325.000 $300.000 $300.000 $450.000
BLOCK SODDING
SY 436.000 $5.000 $9.500 $6.500 $6.000 $6.000 $5.500
VEGETATIVE WATERING
MG 7.000 $10.000 $8.000 $15.000 $30.000 $100.000 $1,000.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 2,643.000 $110.000 $125.000 $114.000 $127.000 $130.000 $120.000
FLEX PAVE STRUCTURE REPAIR (8"-10")
SY 626.000 $95.000 $100.000 $95.000 $90.000 $75.000 $85.000
PLANE ASPH CONC PAV (1.5")
SY 23,215.000 $3.000 $4.000 $2.500 $3.000 $3.000 $4.250
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 600.000 $8.000 $4.000 $5.250 $8.000 $3.000 $10.000
CUT & RESTORING PAV
SY 157.000 $50.000 $68.500 $135.000 $85.000 $200.000 $200.000
RIPRAP (CONC)(FLUME)
CY 9.400 $434.000 $580.000 $2,000.000 $650.000 $500.000 $650.000
MOBILIZATION
LS 1.000 $78,000.000 $73,500.000 $75,000.000 $85,000.000 $100,000.000 $119,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,500.000 $1,850.000 $3,500.000 $5,000.000 $2,000.000 $12,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $25.000 $61.750 $50.000 $30.000 $35.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 80.000 $5.000 $25.000 $16.500 $10.000 $10.000 $15.000
EXCAV (EROSN & SEDMT CONT, IN VEH)
CY 190.000 $16.000 $12.000 $35.000 $25.000 $30.000 $30.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 190.000 $30.000 $12.000 $35.000 $25.000 $30.000 $30.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 26.000 $10.000 $10.000 $28.000 $20.000 $10.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 26.000 $1.000 $4.000 $12.000 $5.000 $5.000 $8.000
CONC CURB & GUTTER (TY II)
LF 667.000 $40.000 $26.000 $34.000 $50.000 $25.000 $35.000
CONCRETE RAMP WITH WALL
CY 16.000 $1,900.000 $395.000 $1,100.000 $1,200.000 $2,500.000 $1,500.000
CONCRETE SIDEWALK WITH WALL
CY 171.000 $900.000 $485.000 $1,100.000 $1,000.000 $700.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 5.000 $300.000 $500.000 $450.000 $450.000 $500.000 $650.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $300.000 $500.000 $360.000 $375.000 $500.000 $650.000
REMOVE SM RD SN SUP&AM
EA 8.000 $60.000 $150.000 $185.000 $100.000 $200.000 $100.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 1,190.000 $1.500 $1.500 $1.650 $1.650 $1.500 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,946.000 $1.500 $1.500 $1.400 $1.400 $1.250 $1.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 2,196.000 $0.100 $0.250 $0.280 $0.300 $25.000 $1.000
PREFAB PAV MRK TY C (W) (8") (SLD)
LF 300.000 $5.000 $4.000 $4.400 $4.400 $4.000 $2.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 530.000 $15.000 $11.750 $13.000 $13.000 $12.000 $10.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $350.000 $185.000 $205.000 $205.000 $4.000 $200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 1.000 $350.000 $245.000 $270.000 $270.000 $250.000 $200.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 135.000 $14.500 $11.750 $13.000 $13.000 $12.000 $10.000
REFL PAV MRKR TY I-C
EA 30.000 $3.000 $4.000 $4.500 $4.400 $4.000 $15.000
REFL PAV MRKR TY II-A-A
EA 372.000 $3.250 $4.000 $4.400 $4.400 $4.000 $15.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,386.000 $0.750 $0.350 $0.400 $0.400 $0.350 $1.000
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 16,174.000 $0.300 $0.450 $0.500 $0.500 $0.500 $0.500
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 12,735.000 $0.300 $0.450 $0.500 $0.500 $0.500 $0.500
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
LF 965.000 $0.350 $0.750 $0.850 $0.850 $0.750 $0.500
Totals: $859,169.650 $823,436.650 $946,395.230 $974,656.650 $999,317.850 $1,193,244.250