Bid Cobra

HARRISON FM 450 (0843-06-019)

Items: 46

County: HARRISON
Length: N/A
Highway: FM 450
District: ATLANTA
Control Number: 0843-06-019
DBE Goal: N/A
Project: STP 2017(508)HESG
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $445,191.40
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: BASE, SURFACING & PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$445,191.40
$474,176.69
Over/Under Est: 6.51% $28,985.29
Over/Under Est: 8.86% $39,451.40
Amt Left: 2.21% $10,466.11
$530,530.18
Over/Under Est: 19.17% $85,338.78
Amt Left: 11.88% $56,353.49
Delta: -9.47% -$45,887.38
Over/Under Est: 28.12% $125,172.17
Amt Left: 20.29% $96,186.88
Delta: -7.51% -$39,833.39
Over/Under Est: 54.42% $242,290.90
Amt Left: 44.98% $213,305.61
Delta: -20.53% -$117,118.73
Over/Under Est: 56.37% $250,959.00
Amt Left: 46.81% $221,973.71
Delta: -1.26% -$8,668.10

Bid Items & Bid Tabulations

46 Total 0 of 46
HARRISON  |  FM 450  |  ATLANTA  |  0843-06-019  |  01/05/2017  |  $445,191.40  |  STP 2017(508)HESG  |  BASE, SURF & PAVMT MRK  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FRITCHER CONSTRUCTION SERVICES
L. S. EQUIPMENT CO., INC.
H. V. CAVER, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 12.000 $2,000.000 $2,000.000 $1,000.000 $2,000.000 $2,000.000 $2,300.000 $3,000.000
REMOVING CONC (RIPRAP)
SY 42.000 $13.000 $26.250 $15.000 $30.000 $75.000 $30.000 $25.000
REMOVING CONC (DRIVEWAYS)
SY 57.000 $15.500 $21.000 $15.000 $25.000 $55.000 $20.000 $25.000
SUBGRADE WIDENING (ORD COMP)
STA 75.000 $400.000 $175.000 $200.000 $250.000 $300.000 $450.000 $500.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 418.000 $15.000 $10.000 $20.000 $25.000 $25.000 $29.000 $15.000
BACKFILL (TY B)
STA 75.000 $150.000 $150.000 $200.000 $300.000 $325.000 $300.000 $300.000
BLADING
STA 75.000 $200.000 $75.000 $150.000 $150.000 $225.000 $225.000 $200.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 33,138.000 $1.000 $0.890 $1.000 $0.810 $0.940 $1.000 $1.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 8,285.000 $1.000 $0.860 $1.000 $0.800 $0.900 $1.000 $1.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 8,285.000 $1.000 $0.860 $1.000 $0.800 $0.900 $1.000 $1.000
VEGETATIVE WATERING
MG 530.000 $9.000 $20.000 $0.010 $15.000 $14.000 $22.000 $15.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 900.000 $1.550 $2.330 $2.500 $2.000 $2.450 $1.600 $2.500
FL BS (CMP IN PLC)(TY D GR 4)(10")
SY 4,971.000 $20.000 $20.000 $23.000 $19.150 $24.750 $38.000 $35.000
PRIME COAT & BLOTTER (MC-30)
GAL 1,243.000 $5.000 $5.000 $5.000 $8.750 $5.500 $8.300 $8.000
ASPH (TIER II)
GAL 2,651.000 $2.500 $6.200 $5.000 $8.000 $5.000 $4.400 $6.500
AGGR(TY-PB GR-3 SAC-B)
CY 60.000 $95.000 $217.350 $200.000 $130.000 $260.000 $340.000 $230.000
CEM STABIL BKFL
CY 21.000 $145.000 $183.750 $300.000 $210.000 $550.000 $210.000 $400.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 60.000 $160.000 $112.500 $250.000 $110.000 $220.000 $200.000 $175.000
RC PIPE (CL III)(15 IN)
LF 6.000 $60.000 $63.000 $40.000 $40.000 $110.000 $65.000 $60.000
RC PIPE (CL III)(18 IN)
LF 36.000 $60.000 $78.750 $55.000 $50.000 $145.000 $90.000 $60.000
RC PIPE (CL III)(24 IN)
LF 26.000 $65.000 $178.500 $75.000 $150.000 $300.000 $405.000 $75.000
RC PIPE (CL III)(36 IN)
LF 4.000 $135.000 $152.250 $150.000 $190.000 $350.000 $425.000 $300.000
RC PIPE (CL III)(42 IN)
LF 12.000 $175.000 $178.500 $250.000 $240.000 $280.000 $440.000 $500.000
SET (TY I) (36 IN) (4: 1) (C)
EA 2.000 $4,000.000 $3,675.000 $4,500.000 $5,000.000 $9,000.000 $11,000.000 $5,000.000
SET (TY I) (42 IN) (3: 1) (C)
EA 5.000 $6,000.000 $4,987.500 $4,500.000 $5,600.000 $5,500.000 $8,500.000 $7,500.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 6.000 $570.000 $939.750 $910.000 $750.000 $550.000 $550.000 $600.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 30.000 $700.000 $1,155.000 $1,100.000 $800.000 $650.000 $700.000 $600.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 8.000 $1,000.000 $1,575.000 $1,250.000 $1,400.000 $750.000 $800.000 $800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $900.000 $1,575.000 $1,500.000 $1,300.000 $1,000.000 $1,100.000 $900.000
MOBILIZATION
LS 1.000 $41,000.000 $65,000.000 $45,000.000 $84,900.000 $45,000.000 $68,000.000 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $815.000 $2,000.000 $4,000.000 $3,500.000 $2,100.000 $12,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 280.000 $27.000 $28.860 $30.000 $27.500 $38.000 $37.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 280.000 $6.750 $8.610 $10.000 $8.200 $13.000 $8.400 $8.200
TEMP SEDMT CONT FENCE (INSTALL)
LF 560.000 $2.500 $3.000 $3.000 $2.850 $3.250 $3.150 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 560.000 $0.750 $1.300 $0.500 $1.200 $1.250 $1.050 $1.240
DRIVEWAYS (CONC)
SY 45.000 $85.000 $99.750 $70.000 $100.000 $100.000 $120.000 $125.000
DRIVEWAYS (ACP)
SY 29.000 $40.000 $30.000 $70.000 $80.000 $80.000 $132.000 $60.000
DRIVEWAYS (SURF TREAT)
SY 216.000 $25.000 $21.000 $50.000 $40.000 $70.000 $50.000 $60.000
TURNOUTS (SURF TREAT)
SY 194.000 $25.000 $21.000 $50.000 $40.000 $75.000 $75.000 $60.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 3.000 $230.000 $265.780 $300.000 $250.000 $280.000 $280.000 $300.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 4.000 $250.000 $284.550 $300.000 $280.000 $300.000 $280.000 $325.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $475.000 $635.150 $700.000 $600.000 $665.000 $520.000 $700.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 3.000 $425.000 $553.600 $600.000 $540.000 $580.000 $670.000 $600.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 14.000 $55.000 $104.120 $100.000 $90.000 $110.000 $47.000 $110.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 14,470.000 $0.120 $0.410 $0.450 $0.350 $0.430 $0.400 $0.450
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 120.000 $12.000 $15.750 $20.000 $14.000 $16.500 $16.000 $20.000
Totals: $445,191.400 $474,176.690 $484,642.800 $530,530.180 $570,363.570 $687,482.300 $696,150.400