HARRISON IH 20 (0495-08-140)
Items: 26
County: HARRISON
Length: 9.5460 MILES
Highway: IH 20
District: ATLANTA
Control Number: 0495-08-140
DBE Goal: 0.0%
Project: C 495-8-140
Guaranty: $71,000.00
Time: 49 WORKING DAYS
Engineer's Estimate: $3,360,682.00
Date: 07/02/2025 (11 months ago)
Contract Number: 7253214
Type: RESURFACE ROADWAY
Project ID: A00208034
Project Description: RESURFACE EXISTING WESTBOUND INTERSTATE HIGHWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JACOB VISE
RYAN GRIFFIN
HARRISON IH 20 (0495-08-140)
Project Name: N/A
Project: C 495-8-140
Length: 9.5460 MILES
Project Type: CONSTRUCTION
Limits From: FM 450
Limits To: 0.5 MI W OF SH 43
Project Description: RESURFACE EXISTING WESTBOUND INTERSTATE HIGHWAY
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,360,682.00 | |||
| $2,798,906.58 |
-16.72%
-$561,775.42
|
|||
| $3,385,990.85 |
0.75%
$25,308.85
|
20.98%
$587,084.27
|
||
| $3,752,984.30 |
11.67%
$392,302.30
|
34.09%
$954,077.72
|
-10.84%
-$366,993.45
|
E
Engineer's Estimate
$3,360,682.00
1
Awarded
$2,798,906.58
Over/Under Est:
-16.72%
-$561,775.42
$3,385,990.85
Over/Under Est:
0.75%
$25,308.85
Amt Left:
20.98%
$587,084.27
$3,752,984.30
Over/Under Est:
11.67%
$392,302.30
Amt Left:
34.09%
$954,077.72
Delta:
-10.84%
-$366,993.45
| Subcontractor | Percentage | Amount |
|---|---|---|
| COLD CREEK CONSTRUCTION, LTD | 8.03% | $242,587.83 |
| STRIPING TECHNOLOGY, L.P. | 6.12% | $184,886.37 |
| R & G CONSTRUCTION, LLC | 3.98% | $120,236.56 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 1.05% | $31,720.70 |
| CHEROKEE SERVICES | 0.69% | $20,845.03 |
| WEST TEXAS RUMBLE STRIP LLC | 0.46% | $13,896.69 |
| J. H. ODEN CONTRACTING COMPANY | 0.23% | $6,948.34 |
| PANOLA SIGN & BARRICADE, INC. | 0.20% | $6,042.04 |
| Total: | 20.76% | $627,163.56 |
Bid Items & Bid Tabulations
26
Total
0 of 26
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| Total: | $10,000.00 |