HARRISON SH 154 (0402-03-042)

Items: 31

County: HARRISON
Length: N/A
Highway: SH 154
District: ATLANTA
Control Number: 0402-03-042
DBE Goal: N/A
Project: STP 2023(698)HES
Guaranty: N/A
Time: 197 WORKING DAYS
Engineer's Estimate: $4,104,966.05
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$4,104,966.05
$3,492,422.90
Over/Under Est: -14.92% -$612,543.15
$3,874,251.69
Over/Under Est: -5.62% -$230,714.36
Amt Left: 10.93% $381,828.79
Over/Under Est: -4.91% -$201,619.30
Amt Left: 11.77% $410,923.85
Delta: -0.75% -$29,095.06
$4,144,326.96
Over/Under Est: 0.96% $39,360.91
Amt Left: 18.67% $651,904.06
Delta: -6.17% -$240,980.21
Over/Under Est: 9.33% $382,846.58
Amt Left: 28.5% $995,389.73
Delta: -8.29% -$343,485.67

Bid Items & Bid Tabulations

31 Total 0 of 31
HARRISON  |  SH 154  |  ATLANTA  |  0402-03-042  |  05/05/2023  |  $4,104,966.05  |  STP 2023(698)HES  |  SAFETY TREAT FIXED OBJECTS  |  197 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
H. V. CAVER, INC.
CROSS PLUS CONSTRUCTION, LLC
A. L. HELMCAMP, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 706.000 $3,400.000 $2,200.000 $3,500.000 $1,489.000 $3,300.000 $2,500.000
REMOVING CONC (RIPRAP)
SY 83.000 $20.000 $25.000 $25.000 $65.000 $45.000 $50.000
REMOVING CONC (DRIVEWAYS)
SY 573.000 $20.000 $25.000 $17.000 $65.000 $30.000 $55.000
REMOVING CONC (CURB)
LF 30.000 $20.000 $15.000 $20.000 $25.000 $55.000 $55.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 167.750 $50.000 $50.000 $40.000 $55.000 $70.000 $65.000
BLADING
STA 109.750 $105.000 $300.000 $150.000 $250.000 $350.000 $1,500.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 221,526.000 $0.700 $0.580 $0.530 $0.500 $0.550 $0.720
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 221,526.000 $0.100 $0.120 $0.110 $0.500 $0.110 $0.160
VEGETATIVE WATERING
MG 6,580.400 $10.000 $8.000 $0.010 $20.000 $7.000 $35.000
CUT & RESTORE ASPH PAVING
SY 384.000 $150.000 $100.000 $90.000 $350.000 $130.000 $185.000
CL A CONC (COLLAR)
EA 58.000 $1,050.000 $1,700.000 $1,100.000 $1,600.000 $1,550.000 $1,250.000
RIPRAP (CONC)(4 IN)
CY 6.000 $750.000 $1,200.000 $500.000 $1,200.000 $1,350.000 $1,100.000
RC PIPE (CL III)(18 IN)
LF 2,512.000 $60.000 $62.000 $42.960 $135.000 $76.000 $75.000
RC PIPE (CL III)(24 IN)
LF 142.000 $80.000 $82.000 $67.880 $175.000 $105.000 $95.000
RC PIPE (CL III)(30 IN)
LF 12.000 $115.000 $130.000 $91.810 $289.000 $180.000 $120.000
RC PIPE (CL III)(36 IN)
LF 48.000 $180.000 $175.000 $131.980 $450.000 $210.000 $155.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 430.000 $750.000 $900.000 $720.000 $2,100.000 $970.000 $1,300.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 27.000 $1,250.000 $1,350.000 $410.000 $2,199.000 $1,550.000 $1,750.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $2,500.000 $2,130.000 $7,500.000 $3,100.000 $4,100.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 7.000 $4,050.000 $6,500.000 $5,945.150 $8,121.000 $7,200.000 $6,100.000
CLEAN EXIST CULVERTS
EA 96.000 $950.000 $1,625.000 $1,250.000 $400.000 $1,300.000 $3,500.000
REMOV STR (HEADWALL)
EA 4.000 $1,700.000 $1,700.000 $1,500.000 $1,500.000 $7,000.000 $3,000.000
REMOV STR (PIPE)
LF 2,626.000 $30.000 $16.000 $16.000 $22.000 $22.500 $22.000
MOBILIZATION
LS 1.000 $370,000.000 $350,000.000 $300,000.000 $375,000.000 $250,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $6,000.000 $15,000.000 $3,389.420 $5,000.000 $2,500.000 $7,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 250.000 $3.400 $6.000 $4.500 $5.000 $18.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 250.000 $1.000 $3.000 $2.000 $5.000 $6.000 $4.000
CONC CURB (TY II)
LF 30.000 $90.000 $40.000 $50.000 $56.000 $105.000 $200.000
DRIVEWAYS (CONC)(TYPE 1)
SY 263.000 $100.000 $115.000 $120.000 $195.000 $130.000 $140.000
DRIVEWAYS (CONC)(TYPE 2)
SY 334.000 $120.000 $135.000 $140.000 $195.000 $160.000 $165.000
TMA (STATIONARY)
DAY 197.000 $250.000 $250.000 $200.000 $500.000 $390.000 $350.000
Totals: $4,104,966.050 $3,492,422.900 $3,874,251.694 $3,903,346.750 $4,144,326.960 $4,487,812.630