HARRISON US 80 (0096-07-054)
Items: 76
County: HARRISON
Length: N/A
Highway: US 80
District: ATLANTA
Control Number: 0096-07-054
DBE Goal: N/A
Project: F 2B23(018)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $7,554,019.55
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
JACOB VISE
RYAN GRIFFIN
Bidders (2)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,554,019.55 | |||
| $6,333,886.66 |
-16.15%
-$1,220,132.89
|
|||
| $8,297,354.09 |
9.84%
$743,334.54
|
31%
$1,963,467.43
|
E
Engineer's Estimate
$7,554,019.55
1
Awarded
$6,333,886.66
Over/Under Est:
-16.15%
-$1,220,132.89
$8,297,354.09
Over/Under Est:
9.84%
$743,334.54
Amt Left:
31%
$1,963,467.43
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPING TECHNOLOGY, L.P. | 5.32% | $337,931.86 |
| REYNOLDS & KAY, LTD. | 4.82% | $306,171.34 |
| DREWERY CONSTRUCTION COMPANY, INCORPORATED | 4.61% | $292,831.93 |
| KENT TREE SERVICE LLC | 4.19% | $266,153.10 |
| R & G CONSTRUCTION, LLC | 4.02% | $255,354.52 |
| CAP RIVER LLC | 1.82% | $115,608.27 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 1.47% | $93,375.91 |
| PANOLA SIGN & BARRICADE, INC. | 0.31% | $19,691.52 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 0.21% | $13,339.42 |
| HIGHWAY 1 LLC | 0.16% | $10,163.36 |
| ISAACS CONSTRUCTION SERVICES LLC | 0.11% | $6,987.31 |
| Total: | 27.04% | $1,717,608.54 |
Bid Items & Bid Tabulations
76
Total
0 of 76