HARRISON US 80 (0096-07-049)

Items: 15

County: HARRISON
Length: N/A
Highway: US 80
District: ATLANTA
Control Number: 0096-07-049
DBE Goal: N/A
Project: STP 2018(194)HES
Guaranty: N/A
Time: 155 WORKING DAYS
Engineer's Estimate: $922,000.00
Date: 10/03/2017 (8 years ago)
Contract Number: N/A
Type: UPGRADE MBGF
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$922,000.00
$951,647.73
Over/Under Est: 3.22% $29,647.73
$986,190.00
Over/Under Est: 6.96% $64,190.00
Amt Left: 3.63% $34,542.27
$999,125.80
Over/Under Est: 8.37% $77,125.80
Amt Left: 4.99% $47,478.07
Delta: -1.31% -$12,935.80
Over/Under Est: 22.21% $204,765.12
Amt Left: 18.4% $175,117.39
Delta: -12.78% -$127,639.32
$1,243,923.50
Over/Under Est: 34.92% $321,923.50
Amt Left: 30.71% $292,275.77
Delta: -10.40% -$117,158.38
$1,304,442.50
Over/Under Est: 41.48% $382,442.50
Amt Left: 37.07% $352,794.77
Delta: -4.87% -$60,519.00

Bid Items & Bid Tabulations

15 Total 0 of 15
HARRISON  |  US 80  |  ATLANTA  |  0096-07-049  |  10/03/2017  |  $922,000.00  |  STP 2018(194)HES  |  UPGRADE MBGF  |  155 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
B & E CONSTRUCTION INC
ODUM SERVICES, L.P.
3LW CIVIL LLC
EAST TEXAS BRIDGE, INC.
VANN/ELLI, INC.
FNH CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 3,803.000 $7.000 $8.000 $6.000 $8.920 $10.000 $10.000 $15.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 200.000 $15.000 $10.000 $28.000 $36.000 $30.000 $36.000 $30.000
RIPRAP (MOW STRIP)(4 IN)
CY 610.000 $550.000 $515.000 $550.000 $500.000 $500.000 $550.000 $550.000
RETROFIT RAIL (TY T631)
LF 1,192.000 $95.000 $75.000 $80.000 $91.830 $80.000 $106.000 $110.000
MOBILIZATION
LS 1.000 $85,567.750 $86,513.430 $75,000.000 $50,000.000 $100,000.000 $125,000.000 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,500.000 $2,571.250 $3,500.000 $10,000.000 $13,000.000 $8,000.000 $8,500.000
MTL W-BEAM GD FEN (TIM POST)
LF 10,440.000 $20.000 $16.800 $19.000 $18.000 $20.000 $24.000 $22.000
MTL W-BEAM GD FEN (STEEL POST)
LF 176.000 $75.000 $70.350 $87.000 $33.180 $75.000 $66.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,286.250 $1,450.000 $1,695.000 $1,500.000 $1,875.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 13.000 $1,200.000 $924.000 $1,225.000 $1,089.000 $1,200.000 $1,275.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 10,912.500 $2.900 $2.100 $2.000 $2.000 $2.250 $3.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 60.000 $300.000 $210.000 $110.000 $200.000 $225.000 $200.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 69.000 $300.000 $2,205.000 $2,050.000 $2,000.000 $2,375.000 $2,750.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $300.000 $315.000 $250.000 $200.000 $225.000 $300.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 191.000 $75.000 $30.450 $40.000 $20.000 $17.000 $33.000 $100.000
Totals: $922,000.000 $951,647.730 $986,190.000 $999,125.800 $1,126,765.125 $1,243,923.500 $1,304,442.500